RESOLVED To approve the appointment of Kind Diamond Consortium Ltd to complete construction works to develop 11 Council rented homes for a total sum of £3,050,163. To approve the issue of a letter of intent prior to the formal contract signature for £305,016, 10% of the total contract sum. Reasons for decision The Templeton site has been identified as a site for the direct delivery of new Council homes by Haringey Council. The scheme has been granted planning consent and is ready to progress to construction. Following a competitive tender process, a contractor has been identified to undertake these works. Alternative options considered The authority procured the contract through the London Construction programme (LCP) Major Works 2014 Framework Agreement. The authority considered the use of alternative frameworks but to deliver the quickest and most effective route to market, it was decided to proceed with the LCP.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
Title: Templeton Hall & Garage Site Redevelopment – Construction Contract Award to develop 11 Council rented homes
Report authorised by: Dan Hawthorn, Director of Housing, Regeneration and Planning
Lead Officer: Alan Benson, Head of Housing Strategy & Commissioning
Ward(s) affected: Seven Sisters
Report for Key/ Non Key Decision: Key Decision
1. Describe the issue under consideration 1.1. This report seeks approval to appoint the recommended contractor, Kind Diamond Consortium Ltd, to complete a new build development of 11 Council rented homes at the Templeton Hall and Garage site for a total contract cost of £3,050,163.
1.2This report also seeks approval to issue a letter of intent prior to the formal contract signature in the sum of £305,016 as allowed under Contract Standing Order 9.07.3.
2. Cabinet Member Introduction
2.1This Cabinet report marks an important point in our Council housing delivery programme. It requests Cabinet approval of the first major construction contract for new Council homes, for the development of eleven Council homes at Council rents on the Templeton site in Seven Sisters. These homes will allow eleven individuals, couples or families to live in well built, well designed and well maintained homes, at Council rents. Templeton was originally going to be given to a Housing association to be developed entirely for shared ownership. I am very proud that we have instead been able to develop this site ourselves.
2.2Building a thousand Council homes - and then further thousands once we have achieved that - will be a marathon and not a sprint. But I am delighted that this report marks a very significant milestone in delivering our ambitions, and I am looking forward to many more.
Page 1 of 5 3. Recommendations 3.1. It is recommended that Cabinet:
Approve the appointment of Kind Diamond Consortium Ltd to complete construction works to develop 11 Council rented homes for a total sum of £3,050,163.
Approve the issue of a letter of intent prior to the formal contract signature for £305,016, 10% of the total contract sum.
4. Reasons for decision 4.1. The Templeton site has been identified as a site for the direct delivery of new Council homes by Haringey Council. The scheme has been granted planning consent and is ready to progress to construction. Following a competitive tender process, a contractor has been identified to undertake these works.
5. Alternative options considered 5.1. The authority procured the contract through the London Construction programme (LCP) Major Works 2014 Framework Agreement. The authority considered the use of alternative frameworks but to deliver the quickest and most effective route to market, it was decided to proceed with the LCP.
6. Background information 6.1. The Templeton Road site, located in Seven Sisters ward, was granted full planning consent on 21 September 2017. It was formerly identified as an infill site to be developed by Sanctuary as a shared ownership block of eleven one- and two-bedroom flats, but will now be delivered by the Council as Council rented homes. The works have been designed up to stage 4 of the Royal Institute of British Architects (RIBA) Plan of Works 2013. A contractor is now needed to undertake construction works. The contract period is 18 months. Start on site is expected later in July 2019 and completion in January 2021.
6.2The project tender was a single stage selective tendering – JCT Design and Build form of Contracts 2016. A list of seven companies was generated using LOT 2 of the London Construction Programme (LCP) Major Works 2014 Framework Agreement, and following an Expression of Interest stage, two were invited to submit a proposal in response to an invitation to tender. Two responses were received and evaluated. During the evaluation process, requests for post tender clarification were sought, and the Council responded to these.
6.3The tender was evaluated on 60% quality and 40% price.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.