Templeton Hall & Garage Site Redevelopment - Construction Contract Award to develop 11 Council rented homes

Approved Executive 1 paper

Cabinet approved this item on Tuesday 9 July 2019. Below is the council's own wording, with the papers it was decided on.

Item191

Resolved

RESOLVED To approve the appointment of Kind Diamond Consortium Ltd to complete construction works to develop 11 Council rented homes for a total sum of £3,050,163. To approve the issue of a letter of intent prior to the formal contract signature for £305,016, 10% of the total contract sum. Reasons for decision The Templeton site has been identified as a site for the direct delivery of new Council homes by Haringey Council. The scheme has been granted planning consent and is ready to progress to construction. Following a competitive tender process, a contractor has been identified to undertake these works. Alternative options considered The authority procured the contract through the London Construction programme (LCP) Major Works 2014 Framework Agreement. The authority considered the use of alternative frameworks but to deliver the quickest and most effective route to market, it was decided to proceed with the LCP.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet, 5 pages

Report for: Cabinet 9 July 2019

Item number:

Title: Templeton Hall & Garage Site Redevelopment – Construction Contract Award to develop 11 Council rented homes

Report authorised by: Dan Hawthorn, Director of Housing, Regeneration and Planning

Lead Officer: Alan Benson, Head of Housing Strategy & Commissioning

Ward(s) affected: Seven Sisters

Report for Key/ Non Key Decision: Key Decision

1. Describe the issue under consideration 1.1. This report seeks approval to appoint the recommended contractor, Kind Diamond Consortium Ltd, to complete a new build development of 11 Council rented homes at the Templeton Hall and Garage site for a total contract cost of £3,050,163.

1.2This report also seeks approval to issue a letter of intent prior to the formal contract signature in the sum of £305,016 as allowed under Contract Standing Order 9.07.3.

2. Cabinet Member Introduction

2.1This Cabinet report marks an important point in our Council housing delivery programme. It requests Cabinet approval of the first major construction contract for new Council homes, for the development of eleven Council homes at Council rents on the Templeton site in Seven Sisters. These homes will allow eleven individuals, couples or families to live in well built, well designed and well maintained homes, at Council rents. Templeton was originally going to be given to a Housing association to be developed entirely for shared ownership. I am very proud that we have instead been able to develop this site ourselves.

2.2Building a thousand Council homes - and then further thousands once we have achieved that - will be a marathon and not a sprint. But I am delighted that this report marks a very significant milestone in delivering our ambitions, and I am looking forward to many more.

Page 1 of 5 3. Recommendations 3.1. It is recommended that Cabinet:

 Approve the appointment of Kind Diamond Consortium Ltd to complete construction works to develop 11 Council rented homes for a total sum of £3,050,163.

 Approve the issue of a letter of intent prior to the formal contract signature for £305,016, 10% of the total contract sum.

4. Reasons for decision 4.1. The Templeton site has been identified as a site for the direct delivery of new Council homes by Haringey Council. The scheme has been granted planning consent and is ready to progress to construction. Following a competitive tender process, a contractor has been identified to undertake these works.

5. Alternative options considered 5.1. The authority procured the contract through the London Construction programme (LCP) Major Works 2014 Framework Agreement. The authority considered the use of alternative frameworks but to deliver the quickest and most effective route to market, it was decided to proceed with the LCP.

6. Background information 6.1. The Templeton Road site, located in Seven Sisters ward, was granted full planning consent on 21 September 2017. It was formerly identified as an infill site to be developed by Sanctuary as a shared ownership block of eleven one- and two-bedroom flats, but will now be delivered by the Council as Council rented homes. The works have been designed up to stage 4 of the Royal Institute of British Architects (RIBA) Plan of Works 2013. A contractor is now needed to undertake construction works. The contract period is 18 months. Start on site is expected later in July 2019 and completion in January 2021.

6.2The project tender was a single stage selective tendering – JCT Design and Build form of Contracts 2016. A list of seven companies was generated using LOT 2 of the London Construction Programme (LCP) Major Works 2014 Framework Agreement, and following an Expression of Interest stage, two were invited to submit a proposal in response to an invitation to tender. Two responses were received and evaluated. During the evaluation process, requests for post tender clarification were sought, and the Council responded to these.

6.3The tender was evaluated on 60% quality and 40% price.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Templeton Hall & Garage Site Redevelopment: Construction Contract Award to develop 11 Council rented homesMinutes 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Haringey

Search all
  1. Templeton Hall & Garage Site Redevelopment - Construction Contract Award to develop 11 Council rented homesThis decision
  2. Templeton Hall and garages beside 52 Templeton Road N15 6RXApproved

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies