RESOLVED To approve the implementation of Contract Standing Order 9.07.1c. and award two contracts for: a) DEN technical advisory services to Bidder A ,set out in the exempt report for a period of 3 years from 1/11/19 to 31/10/22, with provision for extension for 12-months. The contract allows for work to be instructed incrementally with additional fees determined by the precise scope of work. The contract value over the life of the contract (contract period + extension) is estimated to be up to £1m. The first phase of work which will be instructed has a value of c£270k. And b) DEN legal advisory services to Bidder 1, set out in the exempt report, for a period of 3 years from 1/11/19 to 31/10/22, with provision for extension for 12-months. The contract allows for work to be instructed incrementally with additional fees determined by the precise scope of work. The contract value ... view the full minutes text for item 41.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
Title: Decentralised Energy Network Programme Award of Contracts
Report authorised by : Dan Hawthorn, Director of Housing Regeneration and Planning
Lead Officer: Tim Starley-Grainger, Energy Infrastructure Manager, x1180 [email protected]
Ward(s) affected: All
Report for Key/ Non Key Decision: Key Decision
1. Describe the issue under consideration
1.1Haringey Council has a programme of Decentralised Energy Network (DEN) projects.
1.2DENs are energy infrastructure which supply heat to buildings via a network of buried, insulated pipes. By connecting multiple buildings together, DENs create a single large heat load. The scale of the heat load makes it possible for DENs to source heat from technologies and/or locations which would not normally be viable for smaller loads. There are several heat producing technologies which can produce lower cost, more environmentally friendly heat but which only work at very large scale and/or particular locations. DENs make these sustainable energy sources available to customers who would not normally be able to access them
1.3Construction is underway to refurbish and expand the DEN at Broadwater Farm. Other projects are in development. An Outline Business Case for the North Tottenham DEN was approved by Cabinet in January 2017 and a scheme will proceed here assuming the High Road West development scheme proceeds. Projects at Tottenham Hale and Wood Green are currently at feasibility stage and, through the planning system (notably s106 agreements with St William in Wood Green and Argent-Related in Tottenham Hale), the Council is committed to engaging with developers to seek to bring these schemes forward.
1.4Extensive professional advice will be required to support delivery over the coming years and this paper makes recommendations for appointments and explains the procurement processes followed.
Page 1 of 12 1.5 Note that the Council has already appointed technical and legal advisors for North Tottenham jointly with the GLA. However, this work is currently on hold due to delays at High Road West; the North Tottenham contracts cannot be varied easily to include additional work; and the contracts allow for the GLA to fund the work but the GLA‟s budget is potentially expiring in March 2020. The scope of work considered here is therefore focussed on Wood Green, Tottenham Hale, Broadwater Farm and the Council‟s other housing and regeneration projects many of which will involve decentralised energy networks. If the GLA‟s budget expires in 2020, the Council has the option to either vary the new contracts to include the North Tottenham work or to novate the existing North Tottenham contracts from the GLA to the Council.
1.6Estimated spend for professional advice for the DEN programme (excluding North Tottenham) over the next 12-18-months across three workstreams covering technical, legal and financial services is estimated to be in the region of £300k/£200k/£100k respectively. Beyond this period, more work is likely to be required which is expected to increase to total spend on technical/legal/financial advisors to be in the region of £500k/£500k/£200k respectively.
1.7The intent is to agree an initial scope of work and then to instruct follow-on work through the same contract in due course. The scope (and therefore cost) of future work is currently unclear and will be determined by work over the next 12-18 months. Once the scope is clarified, a price for the work can be agreed with the consultants before being presented to the Council as part of the decision to proceed / release additional budget.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.