Report for: Regulatory Committee 16 January 2020
Title: Planning Services 2019/20 October-December update
Report authorised by : Emma Williamson, Assistant Director, Planning, Building Standards & Sustainability
Lead Officer: Dean Hermitage, Rob Krzyszowski, Neil Goldberg, Fortune Gumbo, Bob McIver
Ward(s) affected: N/A
Report for Key/ Non Key Decision: for information
1. Describe the issue under consideration A report on the work of the Planning Service in –October - December 2019 as well as figures for the application performance in the last financial year
2. Recommendations a) That this report be noted
3. Reasons for decision Not applicable
4. Alternative options considered This report is for noting and as such no alternative options were considered.
5. 2019/20 (Q3) to date work report
Development Management
Applications during 2019/20: 2340 Applications in same period 2018/19: 2665 Number of cases on-hand end of December 2019: 464 Appeals during 2019/20: 85 Appeals dismissed (won) during 2019/20: 65 Cumulative performance (applications in time) 2019/20: o Majors : 100% o Minors : 94% o Others : 97% o PSO : 91% o Validation: 11 working days
As requested previously at Regulatory Committee, Appendix One explains the categories of applications.
Page 1 of 12 Performance overview
5.1Performance is at 100% for „Majors‟ Applications and remains at the top quartile in London. Our performance for „Minor‟ applications has remained in the top quartile in London at 94%. „Other‟ applications are also maintained at top quartile in London at 97%. Performance has continued to improve and we expect to continue to be top quartile in all categories.
5.2In 2019/20 April – December we have decided a total of 15 „Major‟ applications compared to 20 decided during the same period in 2018/19. The average time of decision has decreased from 250 to 165 days between these time periods, however all of these have been subject to planning performance agreements / extensions of time which are mutually agreed with applicants and encouraged in national guidance. The level of major applications submitted in the latter part of this year has reduced over previous years. The Government has three measures of performance which the Council must remain within thresholds for. If we breach these thresholds we will be designated as a poorly performing planning authority and developers will then have the option of applying directly to the Planning Inspectorate for Planning permission. This would mean that we don‟t get the fee income for that application but we are still required to undertake the consultation. In addition we lose the democratic right to determine the application. The first of these measure is our performance on a two year rolling period for determination of major applications. We are at 100% for this measure (the threshold is 50%)
5.3In 2019/20 April – December we have decided 327 „Minor‟ applications compared to the 394 „Minor‟ applications decided during the same period in 2018/19. The average decision day has slightly decreeased from 78 to 76. During 2019/20 we have decided 826 „Other‟ applications compared to the 914 „Other‟ applications decided during the same period in 2018/19. The cumulative average decision time has slightly increased from 56 days to 61 days. The second of the government thresholds relates to performance on minor and other applications over a two year period. We are at 98% on this measure (the threshold is 70%). The third of the government thresholds relates to overturns of refusals of applications on appeal and relates to minor and other applications. We are at 2% on this measure (the threshold is to remain below 5%).
5.4The length of time taken to validate an application has remained at an average of 11 days compared to last year, however this is a product of the Systems thinking approach where there is a delay before validation rather than before decision.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Planning Services 2019/20 October-December updateMinutes | 277 KB | DownloadRead as text |
Follow Regulatory Committee at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jan 2021 | Urgent businessRESOLVED 1. To a gree the appointment of Councillor Sheila Peacock to the Planning Sub-Committee , replacing Councill... | Agreed | Open |
| 5 Oct 2020 | Recent Government Announcements on PlanningRESOLVED that: A) The response to the changes to the current planning system consultation, which was submitted on 1 O... | Noted | Open |
| 2 Oct 2020 | Establishment of Planning and Licensing Sub Committees 2020/21RESOLVED that: 1. The terms of reference of the Regulatory Committee as set out within the Council’s Constitution, at... | Noted | Open |
| 31 Jul 2020 | Business and Planning Act 2020 - Pavement Licence conditions and fees as part of the Covid 19 recovery measuresRESOLVED to i. Agree the p avement licence conditions as outlined in Appendix A which will be the Council’s published... | Agreed | Open |
| 14 Jul 2020 | Amendment to Committee MembershipsRESOLVED that i. Councillor Sarah Williams be appointed as Chair of the Planning Sub Committee, and Licensing Sub Com... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.