Covid 19 Temporary Accommodation - Development of Ermine Road Site - Construction Contract Award

Approved Executive 1 paper

Cabinet Member Signing approved this item on Monday 24 August 2020. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

RESOLVED i. To approve an award of contract (up to the value stated in Part B of this report) to Hill Partnerships Limited (Hill Partnerships) as the main contractor, to develop Ermine Road site including the provision of 39 modular single person accommodation units and 1 office unit, as allowed under Regulation 32(2)(c) of the Public Contract Regulations and Council’s Contract Standing Orders (CSO) 9.07.1d (all contracts valued at £500k or more may only be awarded by Cabinet) and CSO 9.01.2 g) (negotiated procedure without prior publication of an advertisement where Regulation 32 of the Public Contract Regulations are made out) to the contract sum as set out in Part B. ii. To delegate authority to the Director of Housing, Regeneration and Planning to approve any subsequent variations which may be required during construction provided that the contract figure does not exceed £3,050,000 Reasons for decision The decision is required in order to urgently reduce the risk of the Council being unable to provide accommodation for 39 homeless people. Additional information is set out in Part B of the report. As stated in section 1 there is a risk that the current contracts for hotel accommodation may be withdrawn as the economy opens up leaving the possibility that there is no accommodation available for the people identified to occupy this modular accommodation. The direct award of Hill Partnerships as Principal Contractor will help facilitate a speedy delivery of the project and provide a consistency of module being provided which is a requirement of the end user and planners. Hill Partnership manufacture these units and are experienced in installing the units. They are able to provide the units within the required timescales, enabling the site to be handed over by the end of December 2020 (subject to planning). Using a single contractor will mitigate any issues with warranties and liabilities, should they arise. The project is to be awarded on a single stage Design and Build contract which will be priced as an ‘all risk’ contract. The defects liability period (rectification ... view the full minutes text for item 13.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing, 7 pages

Report for: Cabinet Member decision

Title: Covid 19 Temporary Accommodation – Development of Ermine Road Site – Construction Contract Award

Report authorised by: David Joyce, Director of Housing, Regeneration and Planning

Lead Officer: Robbie Erbmann, Assistant Director of Housing Telephone: 020 8489 1784 Email: [email protected]

Ward(s) affected: Seven Sisters

Report for Key/ Non Key Decision: Key

1. Describe the issue under consideration

1.1Following the start of the Covid-19 crisis the London Borough of Haringey has been providing accommodation for more than 600, mainly single, homeless people in emergency accommodation. This has primarily been in hotel accommodation. The contracts for this accommodation are not a secure long term arrangement (month to month arrangements), with the risk of providers now withdrawing from these arrangements as the hotel sector recovers from lock down. Therefore, there is an urgent need to provide more suitable, sustainable and ‘secure’ accommodation for the rough sleeping cohort which can take time to source.

1.2As part of the process to identify alternative provision to hotel accommodation the Council’s Property Team undertook an assessment of alternative meantime sites that could be used for housing and developed quickly. Ermine Road, which is 1600m2 in area, was identified as the best of the available sites. This site is currently identified as being within Cross Rail 2 / new station allocation and is therefore not suitable as a ‘permanent’ housing development.

1.3In order to deliver the project as quickly as possible to provide more ‘secure’ accommodation it has been assessed that using modular accommodation units is the quickest way of delivering the project and meeting these urgent needs. Modular accommodation has the benefit that it can be transferred to another site should the site have to be vacated for the development of Cross Rail 2.

1.4This report seeks an approval to award a contract to Hill Partnerships Limited as the main contractor, under Public Contract Regulations (PCR) 2015, Regulation 32(2)(c) (negotiation without prior notification), to develop the Ermine Road site to provide accommodation for 39 people currently housed in emergency accommodation and office accommodation for support staff. The use of a direct award is considered expedient as tendering works will add significant delays to establishing the accommodation. Soft market testing of similar accommodation has

Page 1 been undertaken and the cost of the Hill Partnerships units is consistent with those provided by other suppliers. However, there is added value which is described in Part B of this report that demonstrates value for money compared to another provider. The use of one supplier will also provide consistency of appearance for the development which is one of the stipulations of Planning Officers at a Pre-app meeting.

2. Cabinet Member Introduction

2.1Most importantly the development will quickly reduce the risk of the Council not being able to provide accommodation for some of its’ rough sleeping cohort as contracts with hotels etc. near the end of their contract term. With the provision of 16 gifted units from the Hill Foundation and the 24 procured units the Council will be able to provide 39 residential units for the rough sleeping cohort and office accommodation for support services.

2.2This report sets out an excellent opportunity to develop the Council owned brownfield site at Ermine Road into new purpose-built supported single person accommodation.

2.3The new scheme design proposal works within the Council’s Zero Carbon Policy reducing the carbon footprint of traditional residential accommodation by having carbon emissions 31% lower than the building regulations requirements, a Band A energy rating and being built to Future Homes standards.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Covid 19 Temporary Accommodation: Development of Ermine Road Site: Construction Contract AwardMinutes 7 pages DownloadRead as text

At this meeting

Whole meeting
13Covid 19 Temporary Accommodation - Development of Ermine Road Site - Construction Contract AwardThis decision

On this subject at Haringey

Search all
  1. Covid 19 Temporary Accommodation - Development of Ermine Road Site - Construction Contract AwardThis decision
  2. Novation of contract from London Hotel Group Ltd T/A Ibis Styles Hotel to London Walthamstow Ltd for temporary accommodation for vulnerable homeless adults (Covid-19).Approved
  3. Written response to deputation - temporary service changes made in response to covid-19Noted

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies