RESOLVED That Corporate Committee Noted the progress made to date on actions following the Corporate Committee report on 30th July 2020. Noted that all actions from the Council House Delivery Programme Audit from December 2019 have now been completed.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
Title: Update on the Audit of the Housing Delivery Programme following Corporate Committee on 30th July 2020 Report Authorised by: David Joyce, Director of Housing, Regeneration and Planning Lead Officer: Robbie Erbmann, Assistant Director of Housing Ward(s) affected: N/A Report for Key/ Non-Key Decision: Non-Key Decision
1. Describe the issue under consideration 1.1. This report provides an update on recommendations from the Council House Delivery Programme Audit, that have been implemented since Corporate Committee report on 30th July 2020.
2. Cabinet Member Introduction 2.1. N/A.
3. Recommendations 3.1. It is recommended that Corporate Committee: 3.2. Note the progress made to date on actions following the Corporate Committee report on 30th July 2020. 3.3. Note that all actions from the Council House Delivery Programme Audit from December 2019 have now been completed. 4. Reasons for decisions N/A 5. Alternative options considered N/A
6. Background information 6.1. As part of the 2019/20 Internal Audit Plan, an internal audit was carried out by Mazaars of the Council House Delivery Programme. The outcome of the Audit was Limited Assurance. 6.2. The objective of the Audit was to evaluate the adequacy of key controls and the extent to which controls have been applied, with a view to Audit providing an opinion on the extent to which risks in this area are managed. 6.3. A draft report was provided by Audit in December 2019 and after management responses were given and accepted by Audit, the Final Report was issued on 27th January 2020. 6.4. Audit analysed and reviewed the following risk areas: Strategy and Objectives Project Planning Governance Monitoring Funding and Budget Management Risk Management Change Management Management Reporting
6.5From this review, Audit initially identified 6 areas for further improvement which were: Estimate of Final Cost and Cashflow Programme Highlight Report Strategic Risk Register Project Brief Project Tracker Communications Plan
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.