New River Sports Ground - Options Appraisal

Approved Executive 6 papers

Cabinet approved this item on Tuesday 9 March 2021. Below is the council's own wording, with the papers it was decided on.

Item475

Resolved

RESOLVED to 1. Approve the ‘Run Directly’ option outlined in paragraphs 6.15 to 6.46 of the report and establish an in-house leisure management operation to manage New River Sport and Fitness. 2. Delegate authority to the Assistant Director Direct Services to set the actual date of transfer, in consultation with the Cabinet Member for Climate Change, Equalities and Leisure. 3. Agree to vire £0.305m from the approved general fund capital programme contingency to fund the capital costs set out in paragraph 6.38 of the report. Reasons for decision Run Directly is the option that can best deliver the Council’s objectives of implementing the new management arrangement within the 12 months of the short-term lease. This option will allow the Council direct control and ensure that the management and activity programme is closely aligned to the Borough Plan Outcomes. The business plan projects that the Council should, under stable operating conditions, be able to operate New River on a break-even basis. Allowing for mobilisation costs and essential capital upgrades, the cost of this option is less than the reintegration option. This option allows the Council to review its actual performance in 2-3 years’ time and consider in a post-pandemic period if this remains the best option for the Council. Alternative options considered The Council set out to assess six options in line with its agreed insourcing policy. The following four options were ruled out as part of that assessment on the basis that they did not meet the high importance criteria set by the Council (see table at para 6.4): 1. Sale of the site 2. Leasing the site on similar terms 3. Tender to a new provider 4. Run via a local authority trading company The options of Run Directly and reintegration with the existing leisure management contract are set out within this report. The option to reintegrate New River within the existing leisure management contract is not being recommended for several reasons. Firstly, the proposal from Fusion would require the Council to subsidise the cost of running New River by £399k over the next three years. This is more than the cost of the Council mobilising its own operation and making the business plan critical improvements identified ... view the full minutes text for item 475.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet

Recommendations

3.1That Cabinet:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Run Directly SWOT AnalysisAppendix A 158 KB Download
PDF
Core Fees and ChargesAppendix B 282 KB Download
PDF
Mobilisation and Capital Setup CostsAppendix C 165 KB Download
PDF
15 Year Lifecycle costingsAppendix D 382 KB Download
PDF
New River Sports Ground: Options AppraisalMinutes 784 KB DownloadRead as text
PDF
eqia_ New River: Run DirectlyMinutes 474 KB Download

At this meeting

Whole meeting

Who was there

10 of 23 attended
JE
Councillor Joseph EjioforChair, present
SC
Councillor Seema ChandwaniCommittee Member, present
CA
Councillor Charles AdjeCommittee Member, present
KA
Councillor Kaushika AminDeputy Chair, present
MB
Councillor Mark BlakeCommittee Member, present
GB
Councillor Gideon BullCommittee Member, present
KH
Councillor Kirsten HearnCommittee Member, present
EI
Councillor Emine IbrahimCommittee Member, present
SJ
Councillor Sarah JamesCommittee Member, present
MW
Councillor Matt WhiteCommittee Member, present
AS
Ayshe SimsekSecretary, expected
JW
Jon WarlowOfficer, expected

All 23 on the meeting page

On this subject at Haringey

Search all
  1. New River Sports Ground - Options AppraisalThis decision
  2. Buy Back of Fusion's New River Lease and Provision of a Short Term LeaseAgreed
  3. New River Sports Centre White Hart Lane N22 5QWApproved
  4. New River Village Section 106 Commitment of FundsAgreed

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies