London Borough of Haringey
Cabinet Member Signing, Friday 2 July 2021 at 1.30pm

Chestnuts Primary School - External Envelope and Building Services Improvement - Award of Construction Contract

Approved Executive 1 paper

Cabinet Member Signing approved this item on Friday 2 July 2021. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

RESOLVED that the Cabinet Member i. Approve an award of contract to Kind Diamond Build Consortium Ltd to the value of £3,691,165.66. ii. Approve a contingency allowance of 10% that equates to £369,116.56 which will be strictly managed under change control governance arrangements iii. Approve the issuance of a letter of intent for up to 10% of the contract value, totalling £369,116.56. Reasons for decision A major review of the condition and suitability of the Children’s Services estate has been undertaken which has informed the Children’s Service’s asset management plan (CSAMP). This identified condition and suitability deficiencies in the primary, secondary, and wider Children’s Service estate need addressing in the short, medium, and long-term. Chestnuts Primary School is high priority for major works due to issues relating to health and safety or the school is at risk of school closure. In 2019 a commission was given to further investigate and address urgent works relating to the condition of building services (i.e. heating, electrics and plumbing), external envelope (i.e. roofs, windows) and boundary security. The scheme has been granted an allocation of funding £0.262m from the public sector decarbonisation programme, a government initiative sponsored by the Department for Business, Energy & Industrial Strategy and administered by Salix (Salix works). The grant will be used to part fund the scheme thus reducing the amount of borrowing that the Council will need to undertake. The terms of the grant are that the relevant works need to be completed by the 30 th September 2021. If this date is missed, then there is a risk that the grant allocation will need to be repaid. A scheme for Chestnuts Primary School has been developed, with sectional completion dates in order to achieve the following: · Salix Public Sector Decarbonisation grant funding works (Window replacement, LED Lighting, Loft Insulation, Building Management System). · Boiler and heating works completion prior to the heating season starting in October. · Decant classroom spaces completed prior to the start of the September term. · Roof replacement, brick repointing, small power and data This construction award report requests a decision on the procurement of a contractor to undertake all of the external envelope and building services infrastructure works identified, designed and approved by the project sponsor. A Cabinet Member decision is required in July 2021 to enable timely mobilisation and facilitate procurement of longer lead in materials as soon as possible which will offer greater likelihood of achieving maximum grant funding available. Alternative Options Considered Do nothing – a decision not to support this award of construction contract will result in the Councils failure to suitably maintain its education estate ... view the full minutes text for item 9.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing, 8 pages

Recommendations

For Cabinet Member for Children, Education and Families pursuant to Contract Standing Order 16.02 to:

3.1Approve an award of contract to Kind Diamond Build Consortium Ltd to the value of £3,691,165.66.

3.2Approve a contingency allowance of 10% that equates to £369,116.56 which will be strictly managed under change control governance arrangements.

3.3Approve the issuance of a letter of intent for up to 10% of the contract value, totalling £369,116.56.

Reasons for decision

Page 1 4.1 A major review of the condition and suitability of the Children’s Services estate has been undertaken which has informed the Children’s Service’s asset management plan (CSAMP). This identified condition and suitability deficiencies in the primary, secondary, and wider Children’s Service estate need addressing in the short, medium, and long- term.

4.2Chestnuts Primary School is high priority for major works due to issues relating to health and safety or the school is at risk of school closure.

4.2In 2019 a commission was given to further investigate and address urgent works relating to the condition of building services (i.e. heating, electrics and plumbing), external envelope (i.e. roofs, windows) and boundary security.

4.3The scheme has been granted an allocation of funding £0.262m from the public sector decarbonisation programme, a government initiative sponsored by the Department for Business, Energy & Industrial Strategy and administered by Salix (Salix works). The grant will be used to part fund the scheme thus reducing the amount of borrowing that the Council will need to undertake. The terms of the grant are that the relevant works need to be completed by the 30th September 2021. If this date is missed, then there is a risk that the grant allocation will need to be repaid.

4.4A scheme for Chestnuts Primary School has been developed, with sectional completion dates in order to achieve the following:

 Salix Public Sector Decarbonisation grant funding works (Window replacement, LED Lighting, Loft Insulation, Building Management System).  Boiler and heating works completion prior to the heating season starting in October.  Decant classroom spaces completed prior to the start of the September term.  Roof replacement, brick repointing, small power and data

4.5This construction award report requests a decision on the procurement of a contractor to undertake all of the external envelope and building services infrastructure works identified, designed and approved by the project sponsor.

4.6A Cabinet Member decision is required in July 2021 to enable timely mobilisation and facilitate procurement of longer lead in materials as soon as possible which will offer greater likelihood of achieving maximum grant funding available.

Alternative options considered

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Chestnuts Primary School: External Envelope and Building Services Improvement: Award of Construction ContractMinutes 8 pages DownloadRead as text

At this meeting

Whole meeting

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies