Cabinet, Tuesday 14 September 2021 at 6.30pm

Housing delivery Scheme at Templeton: revised costs approval

Approved Executive 1 paper

Cabinet approved this item on Tuesday 14 September 2021. Below is the council's own wording, with the papers it was decided on.

Item609

Resolved

RESOLVED to 1. Approve a gross increase of £252,193 in accordance with Contract Standing Order (CSO) 10.02.1 b) to a total contract sum of £3,302,356 to be paid to Kind Diamond Consortium Ltd in respect of the Templeton Hall and Garage Site development contract. 2. Notes that the overall Project cost increased by a net amount of £118,866 due to savings that offset the gross sum of £252,193. Reasons for decision The Templeton site has been identified as a site for the direct delivery of new Council homes by Haringey Council. The scheme has been granted planning consent and is nearing completion. The contractor was appointed following a competitive tender process and is progressing well on site. On 9 July 2019 Cabinet approved a total cost of £3,710,158 for the construction of eleven Council homes for Council rent at Templeton Road including the appointment of Kind Diamond Consortium Ltd to complete the construction for a total sum of £3,050,163 and additional on-costs of £659,995. Since signing the build contract, it has been necessary to make a number of amendments for essential elements that had not been included in the contract. There are cost implications to a number of these amendments. The most significant single elements not included in the original contract are listed below. The Council is legally bound to the contract as signed, and each of the amendments was for a necessary part of the construction process that had not been included in the initial contract as signed. The cost of the amendments to the development contract can be offset against savings made on the additional on cost £659,995 and contingencies approved by Cabinet and built into the original appraisal, so that the net overall effect is an increase of £118,296, representing approximately 3.0%. The principal increased cost changes have been: · Basic Asset Protection Agreement with Network Rail · S278 Highways Works · UKPN – new electrical connection to the site · NHBC Insurance · Cadent Gas Main diversion on site · LCP Framework Fee The principal reductions in costs have been: · Reduction is contingencies · Reduction in fees Alternative options considered An alternate option of either stopping the scheme whilst an agreement was made with Network Rail, ... view the full minutes text for item 609.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet, 5 pages

Recommendations

That Cabinet:

3.1Approve a gross increase of £252,193 in accordance with Contract Standing Order (CSO) 10.02.1 b) to a total contract sum of £3,302,356 to be paid to Kind

Page 1 of 5 Diamond Consortium Ltd in respect of the Templeton Hall and Garage Site development contract.

3.2Notes that the overall Project cost increased by a net amount of £118,866 due to savings that offset the gross sum of £252,193.

Reasons for decision

4.1The Templeton site has been identified as a site for the direct delivery of new Council homes by Haringey Council. The scheme has been granted planning consent and is nearing completion. The contractor was appointed following a competitive tender process and is progressing well on site.

4.2On 9 July 2019 Cabinet approved a total cost of £3,710,158 for the construction of eleven Council homes for Council rent at Templeton Road including the appointment of Kind Diamond Consortium Ltd to complete the construction for a total sum of £3,050,163 and additional on-costs of £659,995.

4.3Since signing the build contract, it has been necessary to make a number of amendments for essential elements that had not been included in the contract. There are cost implications to a number of these amendments. The most significant single elements not included in the original contract are listed below.

4.4The Council is legally bound to the contract as signed, and each of the amendments was for a necessary part of the construction process that had not been included in the initial contract as signed.

4.5The cost of the amendments to the development contract can be offset against savings made on the additional on cost £659,995 and contingencies approved by Cabinet and built into the original appraisal, so that the net overall effect is an increase of £118,296, representing approximately 3.0%.

4.6The principal increased cost changes have been:

 Basic Asset Protection Agreement with Network Rail  S278 Highways Works  UKPN – new electrical connection to the site  NHBC Insurance  Cadent Gas Main diversion on site  LCP Framework Fee

4.7The principal reductions in costs have been:

 Reduction is contingencies  Reduction in fees

Alternative options considered

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Housing delivery Scheme at Templeton: revised costs approvalMinutes 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Haringey

Search all
  1. Housing delivery Scheme at Templeton: revised costs approvalThis decision
  2. Updates on the Council Housing Delivery ProgrammeApproved
  3. Key Decision - Approval of a revenue budget virement from the Housing Revenue Account (HRA) reserves for the provision of services to manage housing disrepair cases, and funding for the delivery of Electrical Inspection & Condition Reports (EICR)Noted
  4. Council housing delivery programme: progress update and decisions on sites in the programmeApproved
  5. Appointment of a Programme Wide Sales and Marketing Agent to Support the Housing Delivery ProgrammeApproved
  6. Financial arrangements for the next stage of the Council's Housing Delivery ProgrammeApproved

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies