Pendarren House Outdoor Education Centre - Phase 2 Annex Works - Construction Contract Award

Approved Executive 1 paper

Cabinet Member Signing approved this item on Tuesday 9 November 2021. Below is the council's own wording, with the papers it was decided on.

Item49

Resolved

RESOLVED to 1. Approve an award of contract to Contractor A of £777,872.19 ((subject to planning approval (see section 6.5 below)). 2. Approve a client construction contingency of 10% that equates to £77,787.22 which will be strictly managed under change control governance arrangements. 3. The above offers a total award value of up to £855,659.41. 4. In accordance with Contract Standing Order 9.07.3 to approve the issuance of a letter of intent for £100,000. Reasons for decision Works to Pendarren were split into two phases, following the identification of health and safety issues, which led to the closure of the Activity Centre in September 2019. During these phase 1 works the opportunity was taken to review the accommodation on site to seek to increase the bed availability within the Annex Building to allow the Centre to be used by two schools simultaneously, thereby increasing potential revenue. This will provide opportunities for Haringey School pupils to benefit from the positive experiences the centre provides. Phase 1 works to the Main House were completed in June 2021and bookings are being taken with schools currently using the Centre. This construction award report requests a decision on the procurement of Contractor A to undertake the following Phase 2 works to the Annexe Building: · External window and door renewal · Roof repairs · New outbuildings · Refurbishment of an existing outbuilding to accommodate a climbing wall · New heating and ventilation system · Reconfiguration internally including new partitions and doors · New floor coverings · Electrical installation · Repairs to underground drainage Alternative options considered Do nothing option - a decision not to support this award of construction contract will result in the Council’s failure to suitably maintain its education estate by undertaking essential condition and fire safety works. This would prevent the Centre from being able to use the Annex Building and would limit revenue income.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing, 6 pages

Recommendations

For Cabinet Member to:

3.1Approve an award of contract to Contractor A of £777,872.19 ((subject to planning approval (see section 6.5 below)).

3.2Approve a client construction contingency of 10% that equates to £77,787.22 which will be strictly managed under change control governance arrangements.

3.3The above offers a total award value of up to £855,659.41.

3.4In accordance with Contract Standing Order 9.07.3 to approve the issuance of a letter of intent for £100,000.

Reasons for decision

4.1Works to Pendarren were split into two phases, following the identification of health and safety issues, which led to the closure of the Activity Centre in September 2019. During these phase 1 works the opportunity was taken to review the accommodation on site to seek to increase the bed availability within the Annex Building to allow the Centre to be

Page 1 used by two schools simultaneously, thereby increasing potential revenue. This will provide opportunities for Haringey School pupils to benefit from the positive experiences the centre provides. Phase 1 works to the Main House were completed in June 2021and bookings are being taken with schools currently using the Centre.

4.2This construction award report requests a decision on the procurement of Contractor A to undertake the following Phase 2 works to the Annexe Building:

 External window and door renewal  Roof repairs  New outbuildings  Refurbishment of an existing outbuilding to accommodate a climbing wall  New heating and ventilation system  Reconfiguration internally including new partitions and doors  New floor coverings  Electrical installation  Repairs to underground drainage

Alternative options considered

5.1Do nothing option - a decision not to support this award of construction contract will result in the Council’s failure to suitably maintain its education estate by undertaking essential condition and fire safety works. This would prevent the Centre from being able to use the Annex Building and would limit revenue income.

6. Background Information

6.1Pendarren House Outdoor Activity Centre was closed to visitors from the 21st of September 2019. This followed the issue of the 2019 Condition Report and analysis by Council Officers, which highlighted significant risk to occupants including fire safety and other compliance issues. It was determined that these issues could not be addressed by reactive remedial works and the centre was shut subject to a strategic review of condition and suitability.

6.2This strategic review led to the recommendation to undertake works in two phases, being works to the Main House and the Annex. Phase One was completed in June 2021 and this has allowed the Centre to be re-opened with the first cohort of schools using the facility in September 2021. Phase Two (which is the subject of this report) consists of addressing the condition and fire precaution works as above and reordering the accommodation to allow the use of the Annex by a full school group (potentially increasing revenue). The reordering of the accommodation will also aid the logistics of running the centre by allowing equipment to be accessed more easily than current arrangements.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Pendarren House Outdoor Education Centre: Phase 2 Annex Works: Construction Contract AwardMinutes 6 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Haringey

Search all
  1. Pendarren House Outdoor Education Centre - Phase 2 Annex Works - Construction Contract AwardThis decision
  2. Options appraisal for the future of the Council's Outdoor Education Centre, Pendarren House in Powys, WalesAgreed

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies