Resolved
12 October 2021 18 October 2021 12 October 2021 18 October 2021
Cabinet decided this item on Tuesday 9 November 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
12 October 2021 18 October 2021 12 October 2021 18 October 2021
The decision to accept the grant would support the delivery of these two significant housing development schemes. Ashley Road Depot is currently expected to deliver 275 new homes in the Tottenham Hale Ward, completing in 2024. Gourley Triangle will deliver 201 homes and 73,873sqft of commercial space in the St Ann’s Ward.
The Council could decline the grant allocation. This option was rejected because the Council would have to fund the gap of £3,886,214 to be able to deliver these schemes.
The Council could decide not to build homes on these sites. This option was rejected because the Council is committed to delivering a new era of Council house building.
Please be advised that the Chair of Overview and Scrutiny has agreed that the call-in procedure shall not apply to this urgent decision. This is because the decision is urgent and any delay in implementation caused by the call-in procedure would seriously prejudice the Council's or the public's interests due to the fact that the Council would lose £3.9m of grant funding of infrastructure works to support the delivery of new homes and commercial space at Ashley Road Depot and Gourley Triangle due for payment on or before 31st October. The alternative is that the grant payment be delayed until November, with a risk that the Government might change its funding priorities in the meantime. The Chair of Overview and Scrutiny Committee has agreed that the decision is both reasonable in all circumstances, and that it should be treated as a matter of urgency. This is in accordance with Part 4, Section H, and Paragraph 18 (a) and (b) of the Council Constitution.
CABINET MEMBER: Cllr Ruth Gordon
Signed by Cabinet Member ……………………………..
Date …12 October 2021…………………………
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes Public Pack, 12/10/2021 Urgent DecisionsReports_pack | 2 pages | DownloadRead as text |
PDF |
Minutes Public Pack, 15/10/2021 Cabinet Member SigningReports_pack | 2 pages | Download |
PDF |
Minutes Public Pack, 18/10/2021 Urgent DecisionsReports_pack | 2 pages | Download |
PDF |
Minutes Public Pack, 19/10/2021 Cabinet Member SigningReports_pack | 2 pages | Download |
PDF |
Minutes of Other BodiesReports_pack | 4 pages | Download |
Follow Cabinet at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Nov 2026 | Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None | Decided | Open |
| 10 Nov 2026 | Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None | Decided | Open |
| 10 Nov 2026 | Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None | Decided | Open |
| 10 Nov 2026 | Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None | Decided | Open |
| 10 Nov 2026 | Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.