CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Haringey
Cabinet Member Signing, Monday 7 March 2022 at 9.00am

Proposed Cycling Improvements along Station Road N22

Approved Executive 6 papers

Cabinet Member Signing approved this item on Monday 7 March 2022. Below is the council's own wording, with the papers it was decided on.

Item137

Resolved

RESOLVED To approve the implementation of the Station Road cycling improvement scheme, as set out in the plan in Appendix A, which includes: (a) Converting the northbound advisory cycle lanes on Station Road from the junction with High Road to the junction with Park Avenue to mandatory cycle lanes and the single kerb blips to double kerb blips. (b) Converting the southbound advisory cycle lane on Station Road between its junction with High Road to its junction with Mayes Road, outside St Pauls Church to No. 76 Station Road and from its junction with Park Avenue to 138 Station Road to mandatory cycle lane and the single kerb blips to double kerb blips. (c) Adding protection for cyclists by replacing the existing wand and mini orcas with longer poles installed inside the markings of the new mandatory cycle lanes where the widths of the cycle lanes exceed 1.65m. Reasons for decision The Council is required to consider the feedback received during the statutory notification period, in particular any objections to proposals, prior to proceeding to implementation. The proposed changes will make it safer for cyclists using these lanes as motor vehicles will not be allowed to enter the mandatory cycle lanes. Alternative options considered The proposals consulted upon included the moving of the parking bays located between 98 and 138 Station Road to outside of the existing advisory cycle lane, allowing the southbound cycle lane along Station Road between Park Avenue and Mayes Road to be made mandatory. This included removal of the widened footway at the junction with Barratt Avenue in order to provide a continuous cycle lane, negating the need for cyclists to weave in and out. However, following further site analysis, the road widths in this section were found to be too narrow, meaning these changes would result in the cycle lanes on both sides of the road being substandard and not meeting minimum widths set out in the London Cycling Design Standards (LCDS). For these reasons and following further discussions with Haringey Cycling Campaign, it was agreed that these measures would not be recommended for approval and instead a more holistic solution would be sought for this section, which would consider continuity towards Alexandra Palace and Bounds Green. This is subject to funding being identified to undertake this feasibility work. The proposal also included replacing the existing wand and mini orcas (small units laid inside the cycle lane markings) with longer poles installed inside the lane of the new mandatory cycle lanes. These were proposed to ... view the full minutes text for item 137.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Recommendations

The Cabinet Member for Environment, Transport, and the Climate Emergency is asked:

3.1To approve the implementation of the Station Road cycling improvement scheme, as set out in the plan in Appendix A, which includes:

(a) Converting the northbound advisory cycle lanes on Station Road from the junction with High Road to the junction with Park Avenue to mandatory cycle lanes and the single kerb blips to double kerb blips.

(b) Converting the southbound advisory cycle lane on Station Road between its junction with High Road to its junction with Mayes Road, outside St Pauls Church to No. 76 Station Road and from its junction with Park Avenue to 138 Station Road to mandatory cycle lane and the single kerb blips to double kerb blips. (c) Adding protection for cyclists by replacing the existing wand and mini orcas with longer poles installed inside the markings of the new mandatory cycle lanes where the widths of the cycle lanes exceed 1.65m.

4 Reasons for decisions

4.1The Council is required to consider the feedback received during the statutory notification period, in particular any objections to proposals, prior to proceeding to implementation. The proposed changes will make it safer for cyclists using these lanes as motor vehicles will not be allowed to enter the mandatory cycle lanes.

Alternative options considered

5.1The proposals consulted upon included the moving of the parking bays located between 98 and 138 Station Road to outside of the existing advisory cycle lane, allowing the southbound cycle lane along Station Road between Park Avenue and Mayes Road to be made mandatory. This included removal of the widened footway at the junction with Barratt Avenue in order to provide a continuous cycle lane, negating the need for cyclists to weave in and out. However, following further site analysis, the road widths in this section were found to be too narrow, meaning these changes would result in the cycle lanes on both sides of the road being substandard and not meeting minimum widths set out in the London Cycling Design Standards (LCDS). For these reasons and following further discussions with Haringey Cycling Campaign, it was agreed that these measures would not be recommended for approval and instead a more holistic solution would be sought for this section, which would consider continuity towards Alexandra Palace and Bounds Green. This is subject to funding being identified to undertake this feasibility work.

5.2The proposal also included replacing the existing wand and mini orcas (small units laid inside the cycle lane markings) with longer poles installed inside the lane of the new mandatory cycle lanes. These were proposed to be provided at regular intervals providing a safe barrier between the cyclist and motor traffic. As the road widths were found to be too narrow for the section of Station Road between Park Avenue and Mayes Road to accommodate wide cycles lanes to meet LCDS, the poles are now recommended to only be provided in sections of the cycle lanes where the widths exceed 1.65m, which would allow a clear width of 1.5m to be retained for use by cyclists.

6 Background Information

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Revised Plan: Station RoadAppendix A 444 KB Download
PDF
Station Road: Consultation LetterAppendix A 368 KB Download
PDF
Consultation Area Plan: Station RoadAppendix B 880 KB Download
PDF
Legal Notice: Station RoadAppendix C 199 KB Download
PDF
Consultation Analysis: Station RoadAppendix D 447 KB Download
PDF
Proposed Cycling Improvements along Station Road N22Minutes 397 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 2 attended
MH
Councillor Mike HakataCommittee Member, present
FR
Fiona RaeSecretary, expected

On this subject at Haringey

Search all
  1. Proposed Cycling Improvements along Station Road N22This decision
  2. Proposed Cycling Improvements along Bounds Green Road N22Approved
  3. Proposed Cycling Improvements along High Road N22Approved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies