RESOLVED To approve a variation of the construction contract to Cosmur Construction London Ltd in the sum of £385,000. The original construction contract award approved by Cabinet for Stroud Green Primary School was in the sum of £1,648,491.33 (£1,498,628.48 construction contract sum plus client construction contingency of 10% that equates to £149,862.85). Approval of the variation will give a total contract sum of up to £2,033,491.33 . Reasons for decision During construction, and once the scaffold was erected around the main building, it became apparent that the roof tiles were in a far worse condition than originally surveyed and it is far more economical to re-roof the main building then undertake patch repairs. Under guidance of the Haringey Conservation officer (as the building is Grade 2 listed) an independent heritage specialist was procured to survey the roof. The heritage specialist reported the ... view the full minutes text for item 3.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
The Cabinet Member for Early Years, Children, and Families is asked:
3.1To approve a variation of the construction contract to Cosmur Construction London Ltd in the sum of £385,000. The original construction contract award approved by Cabinet for Stroud Green Primary School was in the sum of £1,498,628.48. Approval of the variation will give a total contract sum of £1,883,628.48.
4. Reasons for decision .
4.1During construction, and once the scaffold was erected around the main building, it became apparent that the roof tiles were in a far worse condition than originally surveyed and it is far more economical to re-roof the main building then undertake patch repairs. Under guidance of the Haringey Conservation officer (as the building is Grade 2 listed) an independent heritage specialist was procured to survey the roof. The heritage specialist reported the same conclusion that viewing the tiles from afar and even from a few meters away the outer slopes appear sound, but closer inspection and removal of a number of larger sample tiles revealed significant concealed delamination
Page 1 and damage. The recommendation is to retile the outer slopes with new tiles and reuse as many tiles as possible on the inner slopes.
4.2The original project budget set at the client brief stage for each of the schools remains in place and overall is sufficient to cover the contract variation.
Alternative options considered
5.1Do nothing – a decision not to support the increase in the value of the construction works contract will result in delays in completing urgent condition works and would also leave the schools with a defective roof with a short life span remaining.
6. Background Information
6.1London Borough of Haringey are seeking to identify and address building condition and suitability issues across the Education/schools estate.
6.2A major review of the condition and suitability of the Children’s Services estate has been undertaken, which informed the Children’s Service’s asset management plan (CSAMP). This identified condition and suitability deficiencies in the primary, secondary, and wider Children’s Service estate that need addressing in the short, medium, and long-term. Stroud Green Primary Schools was considered high priority for major works due to issues relating to health and safety or risk of school closure.
6.3These condition projects bring several benefits to the schools and the council, with the primary objective of providing improved educational environments for Children in line with Haringey’s borough plan. Along with improving educational outcomes, this project will significantly reduce the risk of a health and safety incident or school closure through condition failure such as mechanical failure or roof leaks. The projects will also help the schools reduce its energy demands and thus reduce carbon emissions through technologies and insulation including double glazing. This work also benefits the Council in reducing the reactive maintenance requirements at the school in future by economically fixing the root cause of the condition issues within a single project whilst avoiding additional temporary repairs costs.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.