Lordship Lane Primary School - New Nursery Building - Variation of Construction Works Contract

Approved Executive 1 paper

Cabinet Member Signing approved this item on Wednesday 11 May 2022. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

RESOLVED That pursuant to Contract Standing Order 16.02 : To approve a variation of the construction contract for Lordship Lane New Nursery to CityAxis Ltd in the sum of £243,574.84, giving a varied contract value from £1,143,688.61 to £1,387,263.45. To approve an increase to the contingency allowance totalling 12.5% from £114,368.86 to £173,407.93 offering a varied award value up to £1,560,671.38. The contingency will be managed under strict change control governance Reasons for decision . Following the appointment of CityAxis Ltd some internal design changes were requested by the Client, Haringey Schools and Learning, increasing the scope of the works, to support the developed needs of the school curriculum and community. This required re-design of the internal spaces within the new nursery building, in full collaboration with the School’s senior leadership team, providing a revised package of employer’s requirements to be priced by the contractor. An increase has been realised during this period on material prices which has been taken into consideration with this variation. The Cabinet Member approval (received on 9 November 2021) to award the construction contact, was subject to receipt of planning approval, which was received on 24 January 2022. Draft planning conditions were included in the tender package for the contractor to price following some pre-planning consultation, as approval was not yet available. The issue of the planning decision with associated conditions resulted in an increase in project scope, with elements to the conditions that had not previously been allowed for (specifically related to ecology and sustainability). The full planning permission with conditions was issued to the contractor, to price the uplift and variance to deliver the full planning approval and manage its conditions. ... view the full minutes text for item 6.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing, 5 pages

Recommendations

For Cabinet Member for Early Years, Children, and Families pursuant to Contract Standing Order 16.02 to:

3.1Approve a variation of the construction contract for Lordship Lane New Nursery to CityAxis Ltd in the sum of £243,574.84, giving a varied contract value from £1,143,688.61 to £1,387,263.45.

3.2Approve an increase to the contingency allowance totalling 12.5% from £114,368.86 to £173,407.93 offering a varied award value up to £1,560,671.38. The contingency will be managed under strict change control governance

4. Reasons for decision .

4.1Following the appointment of CityAxis Ltd some internal design changes were requested by the Client, Haringey Schools and Learning, increasing the scope of the works, to support the

Page 1 developed needs of the school curriculum and community. This required re-design of the internal spaces within the new nursery building, in full collaboration with the School’s senior leadership team, providing a revised package of employer’s requirements to be priced by the contractor. An increase has been realised during this period on material prices which has been taken into consideration with this variation.

4.2The Cabinet Member approval (received on 9 November 2021) to award the construction contact, was subject to receipt of planning approval, which was received on 24 January 2022. Draft planning conditions were included in the tender package for the contractor to price following some pre-planning consultation, as approval was not yet available. The issue of the planning decision with associated conditions resulted in an increase in project scope, with elements to the conditions that had not previously been allowed for (specifically related to ecology and sustainability). The full planning permission with conditions was issued to the contractor, to price the uplift and variance to deliver the full planning approval and manage its conditions.

4.3The Children’s Services Capital Programme Budget is sufficient to cover this contract increase.

Alternative options considered

5.1Do nothing – a decision not to support the increase in the value of the construction works contract will result in delays in completing urgent condition and replacement works, would leave the school with inadequate facilities to meet curriculum requirements, further disruption to children’s education and would risk the loss of a large portion of Salix Public Sector Decarbonisation Grant, see paragraph 6.4.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Lordship Lane Primary School: New Nursery Building: Variation of Construction Works ContractMinutes 5 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Haringey

Search all
  1. Lordship Lane Primary School - New Nursery Building - Variation of Construction Works ContractThis decision
  2. Acquisition of 32 Council homes at 255 Lordship Lane, London N17 6AADecided
  3. Variation of contract for works at Lordship Lane depotApproved
  4. Lordship Lane Primary School - New Nursery Building - Award of Construction ContractApproved
  5. Lordship Lane Primary School - Building Services Improvement and External Envelope Works - Award of Construction ContractApproved
  6. 673 Lordship Lane, N22 5LAApproved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies