Cabinet Member Signing, Tuesday 9 August 2022 at 12.00pm

Energiesprong retrofit pilot project progression - Withholding the notice to proceed

Agreed Executive 2 papers

Cabinet Member Signing agreed this item on Tuesday 9 August 2022. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

RESOLVED 1. To agree to withhold issuing a notice to proceed and end the contractual arrangements with the Energiesprong solution provider Equans UK (previously Engie Regeneration Limited). This will mean that the Energiesprong project on 51 properties around Rivulet Road stops. 2. To agree that Haringey remains within the Greater London Authority (GLA) Innovation Partnership to investigate further opportunities to undertake an Energiesprong project on the Council’s housing stock. This could involve exploring options with alternative suppliers on the GLA Innovation Partnership framework. 3. To approve not drawing down £1,487,000 of Government Department of Business Energy and Industrial Strategy (BEIS) Social Housing Decarbonisation Funding (SHDF) from London Borough of Barking and Dagenham (lead partner) which was secured to deliver this pilot project. 4. To agree that an alternative deep retrofit project is investigated for the 19 tenanted homes who had signed up to the pilot Energiesprong project and 2 council properties which are void. Reasons for decision The Energiesprong designs submitted by Equans :- · did not meet the agreed gross maximum price per property of £85k. This meant that the Council would have to significantly increase its funding towards the project. · did not offer the expected maintenance savings. This meant that the Council would have to increase its maintenance programme to manage these improved properties. · could not be completed by the end of March 2023 to claim BEIS funding. This meant that the Council would have to significantly increase its funding towards the project. · included unacceptable design compromises. This would introduce issues not previously agreed with the tenants (such as internal works), may require planning requirements or did not offer a pathway to a quick and replicable solution. Alternative options considered Continue with the Energiesprong pilot project with Equans for 51 properties around Rivulet Road. This option is not recommended as the suggested approach does not satisfy the principles set out below:- · Quick installation with minimum disruption to tenants through offsite manufacture. · Financial viability, ie with the BEIS grant funding, maintenance savings and comfort charge payments, the capital outlay is recouped over a 30 year period. · A replicable approach. · A fixed gross maximum price (for the works) per property with available grant funding. · Economies of scale in future stages of the project through continued innovation. · Delivery to the BEIS funding deadlines. Without the grant funding the business case is not met. Continue with the Energiesprong pilot project with another solution provider for 51 properties around Rivulet Road. This option is not recommended as it ... view the full minutes text for item 4.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing, 9 pages

Recommendations

The Cabinet Member for Housing Services, Private Renters, and Planning is recommended:

3.1To agree to withhold issuing a notice to proceed and end the contractual arrangements with the Energiesprong solution provider Equans UK (previously Engie Regeneration Limited). This will mean that the Energiesprong project on 51 properties around Rivulet Road stops.

3.2To agree that Haringey remains within the Greater London Authority (GLA) Innovation Partnership to investigate further opportunities to undertake an Energiesprong project on the Council’s housing stock. This could involve exploring options with alternative suppliers on the GLA Innovation Partnership framework.

3.3To approve not drawing down £1,487,000 of Government Department of Business Energy and Industrial Strategy (BEIS) Social Housing Decarbonisation Funding (SHDF) from London Borough of Barking and Dagenham (lead partner) which was secured to deliver this pilot project.

Page 1 of 9 3.4 To agree that an alternative deep retrofit project is investigated for the 19 tenanted homes who had signed up to the pilot Energiesprong project and 2 council properties which are void.

Reasons for decision

4.1The Energiesprong designs submitted by Equans:-

 did not meet the agreed gross maximum price per property of £85k. This meant that the Council would have to significantly increase its funding towards the project.  did not offer the expected maintenance savings. This meant that the Council would have to increase its maintenance programme to manage these improved properties.  could not be completed by the end of March 2023 to claim BEIS funding. This meant that the Council would have to significantly increase its funding towards the project.  included unacceptable design compromises. This would introduce issues not previously agreed with the tenants (such as internal works), may require planning requirements or did not offer a pathway to a quick and replicable solution.

Alternative options considered

5.1Continue with the Energiesprong pilot project with Equans for 51 properties around Rivulet Road. This option is not recommended as the suggested approach does not satisfy the principles set out below:-  Quick installation with minimum disruption to tenants through offsite manufacture.  Financial viability, ie with the BEIS grant funding, maintenance savings and comfort charge payments, the capital outlay is recouped over a 30 year period  A replicable approach.  A fixed gross maximum price (for the works) per property with available grant funding  Economies of scale in future stages of the project through continued innovation  Delivery to the BEIS funding deadlines. Without the grant funding the business case is not met.

5.2Continue with the Energiesprong pilot project with another solution provider for 51 properties around Rivulet Road This option is not recommended as it could not be completed to the BEIS funding deadlines. The project would therefore not be financially viable.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Location of the properties that were under considerationAppendix A 1 pages Download
PDF
Energiesprong retrofit pilot project progression: Withholding the notice to proceedMinutes 9 pages DownloadRead as text

At this meeting

Whole meeting
3Rough Sleeping Initiative GrantApproved
4Energiesprong retrofit pilot project progression - Withholding the notice to proceedThis decision

On this subject at Haringey

Search all
  1. Energiesprong retrofit pilot project progression - Withholding the notice to proceedThis decision
  2. Energiesprong retrofit award of contractApproved
  3. Energiesprong retrofit pilot project progressionApproved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies