RESOLVED 1. To note the forecast total revenue outturn for the General Fund of £15.7m comprising £5.6m base budget and £10.1m (51%) savings delivery challenges. Note that Directors are developing actions to bring the forecast down before the end of the year. (Section 6, Table 1 and Appendices 1 & 3). 2. To note the net DSG forecast of £3.8m overspend. (Section 6 and Appendix 1). 3. To note the net Housing Revenue Account (HRA) forecast a breakeven at this time in the year (Section 6 and Appendices 1 and 2). 4. To note the forecast GF & HRA Capital expenditure of £337.6m in 2022/23 (excluding enabling budgets) which equates to 72% of the revised capital budget (Section 8 and Appendix 4). 5. To note the debt write-offs approved in Quarter 1 2022/23 (Appendix 7). 6. To approve the extension of the current loan to the Credit Union as set out ... view the full minutes text for item 44.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
Lead Officer: Frances Palopoli – Head of Corporate Financial Strategy & Monitoring
Ward(s) Affected: N/A
Report for Key/ Non-Key Decision Key
1. Introduction 1.1 This budget report covers the position at Quarter 1 (Period 3) of the 2022/23 financial year including General Fund (GF) Revenue, Capital, Housing Revenue Account (HRA) and Dedicated Schools Grant (DSG) budgets. The report focuses on significant budget variances including those arising as a result of the forecast non-achievement of approved MTFS savings.
1.2The 2022/23 Budget and 2022/2027 Medium Term Financial Strategy (MTFS) report agreed by Full Council in March 2022 recognised the level of pressures faced by the care services particularly in the light of on-going demand, increased complexity of cases and the exposure to upward inflationary pressures. In response, an additional £13.7m was added to these services (£6.6m Children’s; £7.1m Adults). Additionally, due to the upward inflationary trends in the economy, budgetary assumptions for both pay and non-pay were augmented.
1.3Despite this strategy, the economy overall has been impacted by the growing cost of living crisis, rising interest rates and inflation rising significantly in the areas of food, fuel, and utilities therefore, as at Quarter 1 (Qtr1) the overall forecast GF variation from budget for the year stands at £15.7m with £10.1m attributable to non-delivery of agreed MTFS savings and £5.6m base budget pressures. The two care services account for £13.9m of the projected overspend as they continue to be adversely impacted by the direct and indirect consequences of the pandemic on demand as well as increased cost of placements. Identifying mitigations in these predominately statutory services will be challenging however, the service leads continue to review the service provision to reduce demand whilst meeting needs through innovative and efficient ways. Aside this, the Council must intensify its planned actions to identify all possible opportunities to offset this spend as far as possible before year end. Detailed mitigating actions to bring spend in line with budget to be presented at Qtr2.
1.4No new budget reductions were agreed for 2022/23 in line with the agreed financial planning strategy in recognition of the extensive existing savings programme. In total there are £20.5m GF savings to be delivered this financial year and at Qtr1 only 51% is on track, leaving a £10.1m pressure.
1.5In the light of the challenging financial environment in the Council and wider economy, officers are working to identify early opportunities for savings delivery. This is even more crucial against the cost of living pressures, increasing demand and the backdrop of inflation. The latter is becoming increasingly concerning as it is a pressure outside the Council’s direct control but is having very real impacts on both revenue and capital expenditure and plans. This is a national issue but it’s impact on the financial plans of the authority cannot be ignored.
1.6The Council’s resilience to future years challenges will be strengthened by further improvements to the in-year position.
1.7The DSG forecast at Qtr1 is £3.8m above budget an improvement on the position at Qtr1 last financial year (£6.5m). Work is underway on a DSG Management Plan (Safety Valve programme) with the Department for Education (DfE) which looks to identify strategies to bring spend more in line with agreed budgets over the short to medium term. This is covered in a further report to this meeting.
1.8The spend forecast against the 2022/23 capital programme, covering both GF and HRA, at Qtr1 is £421.6m (72.0%) of the revised budget, excluding enabling budgets which are held to allow the Council to respond to opportunities.
2. Cabinet Member Introduction
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.