Campsbourne BSIEE Phase 1 - Variation to Construction Contract Award

Approved Executive 1 paper

Cabinet Member Signing approved this item on Friday 30 September 2022. Below is the council's own wording, with the papers it was decided on.

Item3

Resolved

RESOLVED Pursuant to Contract Standing Order 16.02, to vary the following construction contract award: (i) The original contract award approved by Cabinet for Campsbourne Primary School was in the sum of £985,887, including a 10% contingency amount. (ii) A subsequent variation of the construction contract to Mulalley and Company Limited was granted in January 2022 in the sum of £99,610 giving a revised contract sum of £1,085,497. (iii) A further sum of £384,472.90 is now requested to ensure that sufficient funds are available to settle the contractor’s final account, based on projected construction variation costs assessed to date for a projected total construction contract value of £1,439,970.00. Reasons for decision During construction, additional condition works were identified which included remedial works to address saturated and defective sections of roof decking and a requirement for additional mechanical heating works, which were discovered once the contract works commenced at Campsbourne Primary School. Additional works were initially identified and reported for request for a variation to the and increase the approved contract award sum in January 2022. However further additional works were identified, and the contract was further prolonged. Specifically, gym hall roof repair works had a considerable knock effect to the contract delivery which impacted on delivery of the heating system works. This led to the contractor requiring further time to accommodate the additional works; and the requirement for out of hours working to minimise disruption to school service delivery, due to the lack of available decanting space. The project budget is sufficient to cover the contract cost increases. Alternative options considered Do nothing – is not an option as the Council would be in breach of contract. This could lead to legal action from the Contractor for non-payment. A decision not to support the increase in the value of the construction works contract could result in reputational damage to the Council for non-payment and non-compliance with payment terms set out in the JCT contract, overarching LCP framework agreement and or other payment legalisation such as Housing Construction and Regeneration Acts Act 1996 (HGRA) CABINET MEMBER: Cllr Zena Brabazon Signed by Cabinet Member ……………………………… Date …30 September 2022……………………….
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing, 6 pages

Recommendations

The Cabinet Member is recommended:

3.1Pursuant to Contract Standing Order 16.02, to vary the following construction contract award:

(i) The original contract award approved by Cabinet for Campsbourne Primary School was in the sum of £985,887, including a 10% contingency amount.

(ii) A subsequent variation of the construction contract to Mulalley and Company Limited was granted in January 2022 in the sum of £99,610 giving a revised contract sum of £1,085,497.

Page 1 (iii) A further sum of £384,472.90 is now requested to ensure that sufficient funds are available to settle the contractor’s final account, based on projected construction variation costs assessed to date for a projected total construction contract value of £1,439,970.00.

Reasons for decision

4.1During construction, additional condition works were identified which included remedial works to address saturated and defective sections of roof decking and a requirement for additional mechanical heating works, which were discovered once the contract works commenced at Campsbourne Primary School. Additional works were initially identified and reported for request for a variation to the and increase the approved contract award sum in January 2022. However further additional works were identified, and the contract was further prolonged. Specifically, gym hall roof repair works had a considerable knock effect to the contract delivery which impacted on delivery of the heating system works. This led to the contractor requiring further time to accommodate the additional works; and the requirement for out of hours working to minimise disruption to school service delivery, due to the lack of available decanting space. The project budget is sufficient to cover the contract cost increases.

Alternative options considered

5.1Do nothing – is not an option as the Council would be in breach contract. This could lead to legal action from the Contractor for non-payment. A decision not to support the increase in the value of the construction works contract could result in reputational damage to the Council for non-payment and non-compliance with payment terms set out in the JCT contract, overarching LCP framework agreement and or other payment legalisation such as Housing Construction and Regeneration Acts Act 1996 (HGRA)

6. Background Information

6.1London Borough of Haringey are seeking to identify and address building condition and suitability issues across the Education/schools estate.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Campsbourne BSIEE Phase 1: Variation to Construction Contract AwardMinutes 6 pages DownloadRead as text

At this meeting

Whole meeting
3Campsbourne BSIEE Phase 1 - Variation to Construction Contract AwardThis decision

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies