RESOLVED 1. Pursuant to Contract Standing Order (CSO) 10.02.1 (b) and 16.02, to approve the extension of the original contract in the sum of £2,043,115.00 due to complete end of March 2023, and to approve an additional sum of £900,000.00 to be added to the contract for a period up to the end of September 2023. 2. To agree the total cost contained within the exempt report. Reasons for decision The extension of the contract will enable the demolition contractor to reprogramme the works to Tangmere for the careful removal and storage of the Grade II Listed Mural. Upon removal of the Mural, the demolition programme will continue, with a view of completing the works by September 2023 to make the site ready for the Council’s New Homes Programme. Alternative options considered Do nothing – unless the Grade II Listed Mural is removed, the demolition of Tangmere cannot proceed. Therefore, the site will not be cleared to make way for the Council’s New Homes Programme. The only option available is to extend the current demolition contract to enable the existing contractor to continue to reprogramme and continue with the works.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
Report Authorised by: David Joyce, Director for Placemaking and Housing
Lead Officer: David Sherrington, Director of Broadwater Farm
Ward(s) affected: West Green
Report for Key/ Non Key Decision: Key Decision
1. Describe the issue under consideration 1.1. This report seeks approval to extend the Tangmere demolition contract in the sum of £900,000.00. The contract extension is required following the Grade II Listing of the Mosaic Mural, and the need to reprogramme the works to comply with the Listed Building Consent to carefully remove and relocate the Mural.
2. Cabinet Member introduction 2.1. Not applicable
3. Recommendations It is recommended that the Cabinet Member for Council Housebuilding, Placemaking, and Development:
3.1Pursuant to CSO 10.02.1 (b) and 16.02 approves the extension of the original contract in the sum of £2,043,115.00 due to complete end of March 2023, and approves an additional sum of £900,000.00 to be added to the contract for a period up to the end of September 2023.
3.2Agrees the total cost contained within the exempt report.
4. Reasons for decision 4.1. The extension of the contract will enable the demolition contractor to reprogramme the works to Tangmere for the careful removal and storage of the Grade II Listed Mural.
4.2Upon removal of the Mural, the demolition programme will continue, with a view of completing the works by September 2023 to make the site ready for the Council’s New Homes Programme.
5. Alternative options considered 5.1. Do nothing – unless the Grade II Listed Mural is removed, the demolition of Tangmere cannot proceed. Therefore, the site will not be cleared to make way for the Council’s New Homes Programme.
5.2The only option available is to extend the current demolition contract to enable the existing contractor to continue to reprogramme and continue with the works.
Page 1 of 6 6. Background 6.1. At the January 2022 Cabinet, it was agreed to award a contract for the demolition of Tangmere in the sum of £2,043,115.00.
6.2Demolition works commenced 19 April 2022 with a completion date of March 2023.
6.3On 13 September 2022, Historic England notified the Council that they received an application to list the Mosaic Mural on Tangmere.
6.4It was understood that if the listing was approved; the demolition programme will need to be adjusted to account for the time delay in having to draft and submit an application for Listed Building Consent (LBC) to remove the Mural.
6.5It was also recognised that in the event of the listing, the Council will need to quickly mobilise a team to manage the submission of the LBC. The team will comprise a conservation consultant from Historic England’s approved list of contractors, an architect, a planning consultant, and an expert to draft the heritage statement to accompany the LBC.
6.6On 05 October 2022 Historic England notified the Council that they approved the application, and the Mosaic Mural received a Grade II Listing.
6.7As agreed with Historic England, the Council mobilised a team of consultants to draft and submit the LBC to remove, restore and re-erect the Mural.
6.8The LBC was drafted and submitted for consideration at the December 2022 Planning Committee. The Application was supported by Historic England and the Local Planning Authority.
6.9The Planning Committee agreed to grant Listed Building Consent for the removal, restoration, and re-erection of the Mural.
6.10The Listed Building Consent came with several Planning Conditions. The main one being the works to remove the Mural must be completed by the end of April 2023. This date reflected the outline programme that was approved by Historic England and submitted with the LBC Application.
6.11Upon receiving LBC consent, the demolition contractor was instructed to work with DBR Conservation Limited – one of Historic England’s approved contractors, to agree on the best approach for dismantling the Mural.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.