Resolved
RESOLVED To note the report.
Strategic Planning Committee noted this item on Tuesday 20 June 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED To note the report.
Report for: Strategic Planning Committee 20 June 2023
Title: Planning and Building Control 2022/23 Update
Report authorised by: Rob Krzyszowski, Assistant Director, Planning, Building Standards & Sustainability
Lead Officer: Robbie McNaugher, Head of Development Management & Enforcement
Bryce Tudball, Interim Head of Planning Policy, Transport & Infrastructure
Bob McIver, Head of Building Control
Ward(s) affected: N/A
Report for Key/ Non Key Decision: For information
1. Describe the issue under consideration A report on the work of the Planning and Building Control services to March 2023.
2. Recommendations That this report be noted.
3. Reasons for decision Not applicable.
4. Alternative options considered This report is for noting and as such no alternative options were considered.
5. Planning and Building Control 2022/23 Update
Page 1 of 17 Development Management
Performance overview
5.1An overview of performance is as follows. Appendix One explains the categories of applications.
Applications received during 2022/23 (1st April – 31st March): 3,385 Applications received during same period 2022/22: 3,527 Number of cases on-hand end of March 2023: 725 (the transition to the new system means this figure is not fully accurate and likely to be higher) Number of cases on-hand end of March 2022: 726 Appeals decided during 2022/23 (1st April – 31st March): 97 Appeals decided during same period 2021/22: 100 Appeals dismissed (won) during 22/23 (1st April – 31st March): 75 (77%) Appeals dismissed (won) during same period 2021/22: 73 (73%) Cumulative performance (applications in time) 2022/23 (1st April – 31st March) Majors: 100% Minors: 80% Others: 87% PS1 Only: 87% Decisions excluded from statutory figures: 73%
5.2As set out above performance is at 100% for ‘Majors’ applications. Our performance for ‘Minor’ applications has declined slightly due to delays relating to the change to the new system at 80%. However given the resource it has taken to deliver the transition to a new database and associated delays to applications during this transition in October the figures are very positive. Appeal performance has also increased which is positive.
2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23 Majors 100% 100% 100% 100% 100% 100% 100% Minors 88% 98% 98% 94% 95% 90% 80% Others 90% 98% 98% 96% 97% 91% 87% PS0/ 86% 89% 90% 91% 91% 91% 87% PS1 Exclud 73% e A.O.D. 68% 69% 86% 90% 91% 88% 79% Cumulative Performance (April-March from 2016/17 onwards) Note: As of 2022/23 ‘PS1’ and ‘Exclude’ figures are reported separately within the new Arcus system. Prior to that both PS1 and Exclude were reported as a single return under ‘PS0’
5.3The Government has three measures of application performance which the Council must remain within thresholds for. If we breach these thresholds we may be designated as a poorly performing planning authority and developers will then have the option of applying directly to the Planning Inspectorate for planning permission. This would mean that we don’t get the fee income for that application but we are still required to undertake the consultation. In addition we
Page 2 of 17 lose the democratic right to determine the application. These are (assessed over a two-year rolling period):
Majors applications performance at least 50% Minor and Other applications performance at least 70% Appeals lost (below 10% in both categories)
5.4For 2022/23 we have decided the following:
16 ‘Major’ applications (compared to the 15 during the same period last year) The average time of decision has increased from 257 to 268 days but all have been subject to planning performance agreements or extensions of time due to the need for S106 agreements on applications of this scale.
18/19 19/20 20/21 21/22 22/23
No. of Major Apps decided 27 19 20 15 16 Major applications decided over past five years
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Tech Consultation: Stronger Performance of LPAs through Planning Fees: LBH ResponseAppendix 2 | 8 pages | Download |
PDF |
NPPF text + LURB reforms to national planning policy: LBH ResponseAppendix 3 | 13 pages | Download |
PDF |
PLANNING AND BUILDING CONTROL 2022-23 UPDATEMinutes | 17 pages | DownloadRead as text |
Follow Strategic Planning Committee at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Nov 2026 | MINUTESRESOLVED To confirm and sign the minutes of the Strategic Planning Committee held on 13 th July as a correct record. | Decided | Open |
| 20 May 2026 | Establishment of the Planning Sub-Committee 2026/27RESOLVED 1. To note the terms of reference of the Strategic Planning Committee and Planning Sub-Committee as set out ... | Noted | Open |
| 23 Feb 2026 | MINUTESRESOLVED To confirm and sign the minutes of the Strategic Planning Committee held on xxx as a correct record. | Decided | Open |
| 10 Sep 2025 | MINUTESRESOLVED To confirm and sign the minutes of the Strategic Planning Committee held on 7 th July as a correct record. | Decided | Open |
| 7 Jul 2025 | MINUTESRESOLVED To confirm and sign the minutes of the Strategic Planning Committee held on 24 th February as a correct reco... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.