Cabinet Member Signing, Wednesday 26 July 2023 at 2.30pm

New contractual arrangement with an existing Construction Company contracted with the Council

Approved Executive 1 paper

Cabinet Member Signing approved this item on Wednesday 26 July 2023. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

RESOLVED To grant approval of the mutual termination of Construction Contracts between the Council and Contractor A at Sites 1,2 and 3. To grant approval for a Contract for Construction Management between the Contractor A for Sites 1, 2 and 3 at a fee of 4% of the outstanding costs to complete fixed at the date of entry in to the Construction Management Contract with no mechanism for uplift. To grant approval for direct award Contracts between the Council and nominated sub contractors for the Sites 1,2 and 3 and delegate to the Director of Placemaking and Housing authority to award individual sub contracts subject to approval from the Head of Procurement to each of those direct awards and approval from the Head of Legal and Head of Finance ( Housing ) to the terms of those direct awards. 4. To approve to delegate to the Assistant Director of Housing authority to sign off any instructions that may be required to be discharged from the contingencies being sought for approval in the report. Reason for Decision To ensure that the Council’s Housing Delivery Programme continued to provide high quality Council Housing at affordable rents, constructed to a good standard and made available to new Tenants as soon as possible in accordance with the Council’s overriding Policy objective of providing 3,000 new Council Homes by 2032. Alternative options considered Following discussions with Contractor A, which accorded with the Mediation Provisions of the JCT ( Joint Contracts Tribunal ), the Council have considered a number of mitigations which include: a. Increased spend on Sites 1, 2 and 3 without additional Contractual variations, or, financial checks – This mitigation would not satisfactorily protect the Council’s financial position. b. Terminated contracts on Sites 1, 2 and 3 either by mutual consent, or, by virtue of Contractor A having to enter insolvency – This mitigation would require the Council to reprocure all of those Works at costs that would be disproportionately high. It is considered that neither of the alternatives listed above would meet the Council’s value for money requirements and would result in an unacceptable delay to the completion of much needed Council Housing in the Borough.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing, 4 pages

Report for: Cabinet Member Signing Title: New contractual arrangement with an existing Construction Company contracted with the Council Report Authorised by: Robbie Erbmann – Assistant Director Housing Lead Officer: Anna Blandford – Head of Development Report Prepared by: Jack Goulde, Senior Housing Delivery Project Manager Ward(s) affected: Noel Park, St. Ann’s and Tottenham Green Report for Key/ Non Key Decision: Key Decision

1. Describe the issue under consideration 1.1. This report seeks approval from the Cabinet Member for Council Housebuilding, Placemaking, and Development to terminate existing Construction Contracts with Contractor A for Sites 1,2 and 3 and simultaneously enter in to an alternative Construction Management Agreements for Sites 1,2 and 3 with Contractor A and direct Contracts with sub – contractors

2. Cabinet Member Introduction N/A

3. Recommendations 3.1 The Cabinet Member for Council Housebuilding, Placemaking, and Development is recommended to approve the mutual termination of Construction Contracts between the Council and Contractor A at Sites 1,2 and 3.

3.2Approve a Contract for Construction Management between the Contractor A for Sites 1, 2 and 3 at a fee of 4% of the outstanding costs to complete fixed at the date of entry in to the Construction Management Contract with no mechanism for uplift.

3.3Approve direct award Contracts between the Council and nominated sub contractors for the Sites 1,2 and 3 and delegate to the Director of Placemaking and Housing authority to award individual sub contracts subject to approval from the Head of Procurement to each of those direct awards and approval from the Head of Legal and Head of Finance ( Housing ) to the terms of those direct awards.

3.4Exempt

3.5Approval to delegate to the Assistant Director of Housing authority to sign off any instructions that may be required to be discharged from the contingencies we are seeking approval for in this Report.

4. Reasons for decisions

Page 1 of 4 4.1. To ensure that the Council’s Housing Delivery Programme continues to provide high quality Council Housing at affordable rents, constructed to a good standard and made available to new Tenants as soon as possible in accordance with the Council’s overriding Policy objective of providing 3,000 new Council Homes by 2032.

5. Alternative options considered 5.1. Following discussions with Contractor A, which accord with the Mediation Provisions of the JCT ( Joint Contracts Tribunal ), the Council have considered a number of mitigations which include:

a. Increasing the spend on Sites 1, 2 and 3 without additional Contractual variations, or, financial checks – This mitigation would not satisfactorily protect the Council’s financial position. b. Terminate the Contracts on Sites 1, 2 and 3 either by mutual consent, or, by virtue of Contractor A having to enter insolvency – This mitigation would require the Council to reprocure all of those Works at costs that would be disproportionately high.

5.2It is considered that neither of the alternatives listed above would meet the Council’s value for money requirements and would result in an unacceptable delay to the completion of much needed Council Housing in the Borough.

6. Background information Exempt

7. Contribution to Strategic Outcomes 7.1. The recommendations in this report will support the delivery of the Housing Priority in the new Borough Plan, which sets out in its first outcome that “We will work together to deliver the new homes Haringey needs, especially new affordable homes”. Within this outcome, the Borough Plan sets the aim to “Ensure that new developments provide affordable homes with the right mix of tenures to meet the wide range of needs across the borough, prioritising new social rented homes”.

8. Statutory Officers comments (Chief Finance Officer (including procurement), Head of Legal and Governance, Equalities)

8.1Legal 8.1.1. The Head of Legal Services (Monitoring Officer) has been consulted in the drafting the report.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
New contractual arrangement with an existing Construction Company contracted with the CouncilMinutes 4 pages DownloadRead as text

At this meeting

Whole meeting
6New contractual arrangement with an existing Construction Company contracted with the CouncilThis decision
8EXCLUSION OF THE PRESS AND PUBLICOn the agenda

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies