SOUTH HARRINGAY PRIMARY SCHOOL - URGENT CONDITIONS WORKS

Approved Executive 1 paper

Cabinet Member Signing approved this item on Monday 4 December 2023. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

RESOLVED 1. To approve an Award to Contractor B to the value of £1,720,833.00. 2. To approve a client contingency as set out in Part B of this report which will be strictly managed under change control governance arrangements. 3. To approve the issuance of a letter of intent for up to 10% of the contract value, as set out in Part B of this report. Reasons for decision A major review of the condition and suitability of the Children’s Services estate has been undertaken which has informed the Children’s Service’s asset management plan (CSAMP). This identified condition and suitability deficiencies in the primary, secondary, and wider Children’s Service estate need addressing in the short, medium, and longterm . South Harringay Primary School is high priority for major works due to issues relating to health and safety or the school is at risk of school closure. In 2019 a commission was given to further investigate and address urgent works relating to the condition of building services. This construction contract award is to achieve the following: · Replacement of windows · Repairs to stone and ceramic tile cills · External masonry brickwork and repointing · Underpinning to brick pier of school boundary wall · Localised roof repairs and rainwater goods repairs to make full use of the scaffolding · Installation of pigeon deterrent system This construction award report requests a decision on the procurement of a contractor to undertake all the external envelope works identified, designed and approved by the project sponsor. There is no Cabinet Meeting scheduled in August. A Cabinet Member decision is required in August 2023 to enable timely mobilisation and facilitate procurement of longer lead in materials as soon as possible which will offer greater likelihood of achieving maximum grant funding available. Alternative Options Considered Do nothing – a decision not to support this award of construction contract will result in the Councils failure to suitably maintain its education estate by undertaking essential condition improvements. This would increase the likelihood of reactive works which will create greater disruption and cost to the council and potentially result in the loss of education days. All of which would undoubtedly impact on the quality of teaching and learning. Delaying a decision further would add additional time to the programme and cost to the council. Not ... view the full minutes text for item 6.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
SOUTH HARRINGAY PRIMARY SCHOOL: URGENT CONDITIONS WORKSMinutes 307 KB Copy on its way

At this meeting

Whole meeting
6SOUTH HARRINGAY PRIMARY SCHOOL - URGENT CONDITIONS WORKSThis decision
8EXCLUSION OF THE PRESS AND PUBLICOn the agenda

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies