Cabinet Member Signing, Thursday 7 December 2023 at 2.00pm

CANNING CRESCENT

Approved Executive 1 paper

Cabinet Member Signing approved this item on Thursday 7 December 2023. Below is the council's own wording, with the papers it was decided on.

Item26

Resolved

For the Cabinet Member for health, social care, and wellbeing to Waive CSO 9.01.1 (requirement to publish an appropriate tender advertisement) and approve the award of contract to Diamond Build Group PLC to undertake the refurbishment works at Canning Crescent (2c), based on their tender price of £1,690,324.97. 2. Approve a client contingency as set out in Part B of this report which will be strictly managed under change control governance arrangements. This is in addition to the award value noted in 3.1.1 Refer to Part B section 3 for the contingency value and total award value. 3. To vire £1.528m from approved General Fund capital programme contingency. 4. To note Phase 2a and 2b previously awarded to Diamond Build Plc under delegated powers. 5. To note a total award for phase 2a, 2b and 2c up to the aggregated value of £1,756,468 excluding phase 2c contingency. 6. Approve the issuance of a Letter of Intent up to the value of £100,000. Reasons for decision There were significant delays in the work being completed by the original contractor Cosmur Construction (London) ltd with a contract completion date of 18th March 2022 and the last projected completion date of 27th January 2023. These delays we suspect were attributed to issues with their supply chain payment and poor management which in part was explained by the company entering a Compulsory Voluntary Arrangement on 11th May 2023. Following a review by Major Projects, Haringey Procurement and Legal it was decided the best course of action was to terminate the contract with Cosmur Construction (London) Ltd which was completed on the 31st of March 2023 and for expediency to directly award a contract to a supplier with a track record of delivering similar projects using the Haringey Procurement Contract System (HPCS). With a refurbishment scheme of this nature that had extensive mechanical and electrical (M&E) alterations there is a level of complexity relating to a replacement contractor taking liability for the installation of works by the original contractor. In recognition of this Major Projects instigated a process of validation (by the incoming provider) to assist in ... view the full minutes text for item 26.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
CANNING CRESCENTMinutes 378 KB Copy on its way

At this meeting

Whole meeting
26CANNING CRESCENTThis decision
29EXEMPT - CANNING CRESCENTPrivate

On this subject at Haringey

Search all
  1. CANNING CRESCENTThis decision
  2. Canning Crescent 176 High Road, Wood Green, N22 8JT Refurbishment Works - Increase of project budget and variation of construction works contractApproved
  3. Canning crescentApproved
  4. Canning crescent n22, adaptions & conditions for mental health recovery college - construction contract awardApproved
  5. Briefing Note providing information regarding the award of the Construction works for Canning Crescent Refurbishment WorksNoted
  6. Canning Crescent Mental Health Recovery CentreAgreed

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies