AWARD MICROSOFT UNIFIED SUPPORT 3 YEAR RENEWAL

Decided Executive 1 paper

Cabinet Member Signing decided this item on Tuesday 12 March 2024. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

RESOLVED To award a contract to Microsoft UK Ltd for 3 years from 1/4/24 at a cost of: £582,550.92. Reasons for decision As Haringey Council’s IT infrastructure was based upon Microsoft technologies, ensuring that the on-site Digital & Change support team have access to Microsoft support engineers and consultants is a critical requirement in providing high level service availability. Failure to establish a support contract could involve disruption to Councils services, and additional costs should the Council look to Microsoft for support in the event of an issue. Alternative options considered There were five options that were considered: 1. Do Nothing–Do Not Renew While this was a theoretical option, the potential financial, technical and political impact on Haringey could be immense. This option was therefore not considered any further. 2. Unified Support Option 1 - £173,647.31 This support arrangement, while the cheapest, did not provide sufficient proactive services and should be viewed a minimum offering. Support for workshops and technical briefings would need to be costed separately, typically at a much higher price. Historically, these were services that had been used and had been very beneficial. 3. Unified Support Option 2 - £185,897.31 This option was closely aligned with Haringey’s requirements and would have been selected if it were not due to the increased focus on data sharing, information governance and the current SharePoint project. 4. Unified Support Option 3 - £196,047.31 Last year, unified support option 3 was selected as this enabled the council to fast track the enablement of E5 features. The use of an engineer aligned with the Council’s outcomes provided much value and had been very well received by the engineering team. Based upon the requirement to deliver data driven key initiatives this year i.e. assisting the SharePoint project, data retention policies, data loss prevention, information tagging, controlling data sharing, implementing GDPR and information ... view the full minutes text for item 6.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Reasons for decision

As Haringey Council’s IT infrastructure is based upon Microsoft technologies, ensuring that the on-site Digital & Change support team have access to Microsoft support engineers and consultants is a critical requirement in providing high level service availability. Failure to establish a support contract could involve disruption to Councils services, and additional costs should the Council look to Microsoft for support in the event of an issue.

5. Alternative options considered There were five options that were considered:

1. Do Nothing – Do Not Renew While this is a theoretical option, the potential financial, technical and political impact on Haringey could be immense. This option was therefore not considered any further.

2. Unified Support Option 1 - £173,647.31

This support arrangement, while the cheapest, does not provide sufficient proactive services and should be viewed a minimum offering. Support for workshops and technical briefings would need to be costed separately, typically at a much higher price. Historically, these are services that have been used and have been very beneficial.

3. Unified Support Option 2 - £185,897.31

This option is closely aligned with Haringey’s requirements and would have been selected if it were not due to the increased focus on data sharing, information governance and the current SharePoint project.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
AWARD MICROSOFT UNIFIED SUPPORT 3 YEAR RENEWALMinutes 770 KB DownloadRead as text

At this meeting

Whole meeting
6AWARD MICROSOFT UNIFIED SUPPORT 3 YEAR RENEWALThis decision

Who was there

1 of 1 attended
DC
Councillor Dana CarlinCommittee Member, present

On this subject at Haringey

Search all
  1. AWARD MICROSOFT UNIFIED SUPPORT 3 YEAR RENEWALThis decision
  2. Contract Strategy and Award Decision: Shared Digital - contract award for provision of Microsoft product licencingNoted

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open