London Borough of Haringey
Cabinet Member Signing, Wednesday 19 June 2024 at 10.30am

Gateway 0 Report - Phase 2, Selby Urban Village, N17 - Bruce Castle Ward

Noted Executive 2 papers

Cabinet Member Signing noted this item on Wednesday 19 June 2024. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

RESOLVED To note that the SUV was now at the end of RIBA stage 2. To approve the addition of the SUV (phase 2), Selby Centre site, as shown marked “Phase 2” in Appendix 1, to the Council’s Housing Delivery Programme in order to enable progression of RIBA stage 3. This will allow the work already undertaken by the project Design Team to be completed and will allow us to bring forward a GW1 paper to New Homes Board in due course. Reasons for decision The Council was committed to delivering 3000 council homes by 2031. This decision would contribute to Haringey achieving their ambitious house-building programme. 4.2. On 9 July 2019, Cabinet noted that all housing delivery schemes were subject to three formal stages of Member scrutiny and decision-making. The first stage was including any potential site into the council housing delivery programme with approval to progress design and consultation work. The second stage was when a site comes forward for planning, at which point members on the Planning Sub Committee make a decision. Finally, all sites would come back to Cabinet before any contracts were let to build or to purchase homes. This would also be the point at which any decision to formally appropriate any site from the General Fund into the Housing Revenue Account would be taken. So, this decision was the first of three stages in a triple lock, ensuring Members have full oversight of the delivery programme. Alternative options considered The Council had no statutory duty to develop this site. However, the Council’s top priority was the delivery of a new era of Council housebuilding. The Selby Centre would contribute around 200 council rented homes, so to exclude them from the ... view the full minutes text for item 6.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Red-line plan of SUVAppendix 1 193 KB Copy on its way
PDF
Gateway 0 Report: Phase 2, Selby Urban Village, N17: Bruce Castle WardMinutes 236 KB Copy on its way

At this meeting

Whole meeting
6Gateway 0 Report - Phase 2, Selby Urban Village, N17 - Bruce Castle WardThis decision

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies