Recomendations The Cabinet Member for Children, Education and Families, pursuant to contract standing order 16.02, approved the following actions: 3.1 Awarded a contract, in accordance with contract standing order (CSO) 9.07.1d, for the construction of a new modular two-classroom block at The Brook on Broadwaters School, based on a tendered contract sum of £1,154,231.54. 3.2 Approved a client contingency, as detailed in Part B of the report, which was to be strictly managed under change control governance arrangements. 3.3 Approved the issuance of a Letter of Intent, up to the value of £115,423.15, in line with CSO 9.07.3. Reasons for decisions: The reasons for the decision were as follows: 4.1 In February 2024, Cabinet approved The Brook on Broadwaters as the location to provide up to 18 places for Key Stage 2 (KS2) children with Complex Needs under the Safety Valve Programme. 4.2 A feasibility study, completed in July 2024, recommended a modular building in the southeast corner of the site to expand the school and create 18 additional places for children with severe learning difficulties. 4.3 A design and build contract was proposed as the most efficient way to meet the project deadline of September 2025. Alternative options considered. 5.1 Do nothing – This would result in ... view the full minutes text for item 34.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
For the Cabinet Member for Children, Education and Families, pursuant to contract standing order 16.02, to:
3.1Approve, pursuant to contract standing order (CSO) 9.07.1d an award of contract to construct a new build modular two classroom block at The Brook on Broadwaters school based on a tender contract sum of £1,154,231.54.
3.2Approve a client contingency as set out in Part B of this report which will be strictly managed under change control governance arrangements.
3.3To Approve the issuance of a Letter of Intent up to the value of £115,423.15 pursuant to CSO 9.07.3.
Reasons for decision
4.1In February 2024, Cabinet granted permission for The Brook on Broadwaters to be a location to provide up to 18 places for key stage two (KS2) children with Complex Needs as part of the Safety Valve Programme.
1 4.2 A feasibility study was completed in July 2024 that recommended a modular building, situated in the South East corner of the site. This is for the expansion of the existing school site for the creation of an additional 18 new places for children with severe learning difficulties.
4.3A design and build contract was recommended as the most efficient solution to meet the project deadline of September 2025.
5. Alternative options considered.
5.1Do nothing – This would result in Haringey failing to meet its commitment to deliver additional SEN spaces by September 2025 under the Safety Valve Programme.
5.2In-house – There is currently no resource within the Council that has the capacity, specialist expertise or qualifications to deliver this service.
6. Background information
6.1The Brook Special School is a special school for primary age children, co- located within the same building as the Willow Primary School and sharing one playground, car park and other amenities. The Brook has places for 128 pupils aged from 4-11 and specialises in coeducational day school provision for children with Autism (ASD); profound, severe and severe learning difficulties plus associated physical, medical, communication and emotional needs.
6.2The school building is a decade old, designed as a single building in a ‘C’ shape, with two teaching wings and shared facilities in the central block. Both the Brook and Willow are at capacity. The current site configuration replaced three other schools, including Moselle Primary on a site immediately to the east. This is being developed for housing by the council (see below for more details). 6.3 The school site was selected to host a unit that the school will run for up to 18 KS2 students with Complex Needs, as part of the Safety Valve programme, which was approved by Cabinet in September 2024.
6.4A multi-disciplinary design team was appointed in July 2024. The design team prepared a number of options considering different locations on the site and presented a feasibility report to key stakeholders in September 2024, where a preferred option was selected. This option has been developed to RIBA stage 2 and a tender prepared for a modular building.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.