Tottenham Green Leisure Centre - Phase Two of Year One Works

Approved Executive 1 paper

Cabinet approved this item on Tuesday 18 March 2025. Below is the council's own wording, with the papers it was decided on.

Item158

Resolved

That Cabinet: Approved the award of a contract to Bidder A, for the Phase 2 refurbishments works at Tottenham Green Leisure Centre, for the sum of £687,418.82. Approved a contingency amount of 10% of the contract value, to be managed by the Haringey ... view the full minutes text for item 158.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet

Recommendations

3.1That Cabinet approves the award of a contract to Bidder A, for the Phase 2 refurbishments works at Tottenham Green Leisure Centre, for the sum of £687,418.82.

3.2To approve a contingency amount of 10% of the contract value, to be managed by the Haringey Council project manager.

Reasons for decision

4.1In July 2023, Cabinet took the decision to end the Council’s contract with Fusion Lifestyle Ltd (‘Fusion’) and to review how its leisure services are to be run in the future. As part of the decision to bring the Leisure Service back in house, the council committed to investing to improve facilities offered to residents.

4.2Building condition surveys were undertaken as part of the Leisure Centres insourcing programme for Tottenham Green and Park Road and have revealed urgent works are required across both sites. The condition surveys informed the scope of the phase one and phase two works at both sites, with the most urgent works being included, added to client instructions from Leisure Services.

4.3The scope of works proposed in this report is the second phase of improvements. Phase 1 works were delivered from day 1 of the new service (October 2024) and focused on the most urgent works. These Phase 1 works concluded in December 2024. The Phase 2 works are the remaining urgent works identified.

Alternative options considered

5.1Do nothing The option to not proceed with further works was discounted, given the poor state of the leisure centres, and the feedback from service users.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Tottenham Green Leisure Centre: Phase Two of Year One WorksMinutes 369 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 21 attended
AO
Councillor Ajda OvatCommittee Member, present
PA
Councillor Peray AhmetChair, present
MH
Councillor Mike HakataCommittee Member, present
EA
Councillor Emily ArkellCommittee Member, present
ZB
Councillor Zena BrabazonCommittee Member, apologies
DC
Councillor Dana CarlinCommittee Member, apologies
SC
Councillor Seema ChandwaniCommittee Member, present
LD
Councillor Lucia das NevesCommittee Member, apologies
RG
Councillor Ruth GordonCommittee Member, present
SW
Councillor Sarah WilliamsCommittee Member, present
AD
Andy DonaldOfficer, expected
FA
Fiona AldermanCouncil Staff, expected

All 21 on the meeting page

On this subject at Haringey

Search all
  1. Tottenham Green Leisure Centre - Phase Two of Year One WorksThis decision
  2. Application for a New Premises Licence at Unit 1 314 West Green Road, Tottenham, London N15 3AN (West Green ward)Noted
  3. Approve extension (and variation where it applies) of the Bounds Green, Bruce Grove, Harringay, Noel Park, Northumberland Park, Seven Sisters, St Anns, Tottenham Green, Tottenham Hale, West Green and Woodside Wards Alcohol Control PSPO'sDecided
  4. Ratification of the decision to go out to consultation on the extension and minor variation of the Tottenham Green Alcohol Control PSPONoted
  5. Tottenham/Wood Green landowner forumsAgreed
  6. To seek approval to extend the Public Spaces Protection Order in the Seven Sisters Area [St Ann's and Tottenham Green Wards]Agreed

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies