London Borough of Haringey
Cabinet Member Signing, Thursday 27 March 2025 at 10.00am

Re-procurement of construction works delivering new housing schemes at: Cornwall Rd N15 5BN and Morley Avenue N22 6NT

Approved Executive 1 paper

Cabinet Member Signing approved this item on Thursday 27 March 2025. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

Recommendations 2 .1. The Cabinet Member for Housing and Planning was recommended to: 2.1.1. Approved the appointment of Contractor A, identified in the exempt part of the report, to undertake construction works to complete the schemes known as Cornwall Road N15 and Morley Avenue N22. 2.1.2. Approved the total scheme costs set out in the exempt part of the report. 2.1.3. Approved to delegate to the Assistant Director of Housing authority to sign off any instructions that may be required to be discharged from the contingencies we are seeking approval for in this report. Reasons for decision 3.1. Construction contracts were awarded to Contractor X for the separate developments known as Cornwall Road N15 and Morley Avenue N22, approved by Cabinet Member signings in July 2021 and July 2023. 3.2. Contractor X entered liquidation in December 2024. Please refer to the exempt part of report for further details. 3.3. The Council secured both sites and released a competitive procurement opportunity on the Haringey Dynamic Purchasing System using the JCT Intermediate Building Contract 2016. 3.4. Contractor A has been identified by a formal tender process to undertake these completion works. 3.5. The two sites will contribute to our commitment to build 3,000 new high-quality council homes by 2031. Alternative options considered 4.1. The Council could choose not to complete the construction of these developments and either demolish the structures or sell the partially completed sites on the open market. This option was rejected as it does not support the Council’s commitment to delivering a new generation of Council homes and would present a significant financial loss against investment to date. ... view the full minutes text for item 13.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Report for: Cabinet Member Signing

Item number: 4

Title: Re-procurement of construction works delivering new housing schemes at: Cornwall Road N15 5BN and Morley Avenue N22 6NT Report authorised by : Robbie Erbmann, Assistant Director Housing

Lead Officer: Ishen Stewart-Dowding, Senior Housing Delivery Project Manager

Ward(s) affected: St Ann’s and Noel Park

Report for Key/ Non Key Decision: Key Decision

1. Describe the issue under consideration 1.1. This report seeks approval from the Cabinet Member for Housing and Planning to approve the appointment of the recommended contractor to complete construction works of the schemes known as Cornwall Road N15 and Morley Avenue N22.

2. Recommendations 2.1. The Cabinet Member for Housing and Planning is recommended to:

2.1.1. Approve the appointment of Contractor A, identified in the exempt part of the report, to undertake construction works to complete the schemes known as Cornwall Road N15 and Morley Avenue N22.

2.1.2. Approve the total scheme costs set out in the exempt part of the report.

2.1.3. Approve to delegate to the Assistant Director of Housing authority to sign off any instructions that may be required to be discharged from the contingencies we are seeking approval for in this report.

3. Reasons for decision 3.1. Construction contracts were awarded to Contractor X for the separate developments known as Cornwall Road N15 and Morley Avenue N22, approved by Cabinet Member signings in July 2021 and July 2023.

3.2Contractor X entered liquidation in December 2024. Please refer to the exempt part of report for further details.

3.3The Council secured both sites and released a competitive procurement opportunity on the Haringey Dynamic Purchasing System using the JCT Intermediate Building Contract 2016.

3.4Contractor A has been identified by a formal tender process to undertake these completion works.

3.5The two sites will contribute to our commitment to build 3,000 new high-quality council homes by 2031. 4. Alternative options considered 4.1. The Council could choose not to complete the construction of these developments and either demolish the structures or sell the partially completed sites on the open market. This option was rejected as it does not support the Council’s commitment to delivering a new generation of Council homes and would present a significant financial loss against investment to date.

5. Background information 5.1. Please see Section 8 of this report for links to the background documents for the Cornwall Road N15 and Morley Avenue N22 developments which provide detail on the site context, design, engagement and consultation and statutory comments.

6. Statutory Officers comments

6.1Finance 6.1.1. The cost to complete these schemes is provided for in the recently approved HRA capital programme budget and included in the medium-term financial strategy (MTFS).

6.1.2. Further finance comments are provided in the ‘Exempt report’ attached.

6.2Procurement 6.2.1. Award Approval: Strategic procurement recommends approving an award to Contractor A (details in the exempt section) for construction works at Cornwall Road N15 and Morley Avenue N22.

6.2.2. Competitive Tender Process: A competitive tender was conducted via the LCP’s DPS for Minor Works. The strategy was inclusive, treating projects separately to allow SMEs to bid, while also enabling the possibility of awarding a single supplier to enhance efficiency through applied learning across projects, benefiting the council.

6.2.3. Compliance: The procurement process adheres to Contract Standing Order (CSO) 9.04.1(b) and Regulation 34 of the Public Contracts Regulations.

6.2.4. Value for Money: Aspires tender was the most competitive, demonstrating value for money in both commercial and technical aspects.

6.2.5. Cost Certainty: Aspires tender provided better cost certainty with no provisional costs, reducing financial risks for the council.

6.2.6. Recommendation: SP supports the recommendation to approve the award in accordance with CSO 9.07.1(d).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Re-procurement of construction works delivering new housing schemes at: Cornwall Rd N15 5BN and Morley Avenue N22 6NTMinutes 148 KB DownloadRead as text

At this meeting

Whole meeting
13Re-procurement of construction works delivering new housing schemes at: Cornwall Rd N15 5BN and Morley Avenue N22 6NTThis decision
14Exclusion of the Press and PublicOn the agenda

Who was there

1 of 1 attended
SW
Councillor Sarah WilliamsCommittee Member, present

On this subject at Haringey

Search all
  1. Re-procurement of construction works delivering new housing schemes at: Cornwall Rd N15 5BN and Morley Avenue N22 6NTThis decision
  2. Procurement of contractor for the construction of Stanhope Road BridgeApproved
  3. London Construction Programme (LCP) Collaborative Procurement InitiativesApproved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies