RESOLVED That the Committee resolve to GRANT planning permission and that the Head of Development Management is authorised to issue the planning permission and impose conditions and informatives subject to the signing of a section 106 Legal Agreement providing for the obligation set out in the Heads of Terms below. 2.2 That delegated authority be granted to the Head of Development Management and Planning Enforcement or the Director of Planning & Building Standards is authorised to make any alterations, additions or deletions to the recommended heads of terms and/or recommended conditions as set out in this report and to further delegate this power provided this authority shall be exercised in consultation with the Chair (or in their absence the Vice-Chair) of the SubCommittee. 2.3 That the section 106 legal agreement referred to in resolution (2.1) above is to be completed no later than 30 April 2025 or within such extended time as the Head of Development Management or the Director Planning & Building Standards shall in her/his sole discretion allow; and 2.4 That, following completion of the agreement(s) referred to in resolution (2.1) within the time period provided for in resolution (2.3) above, planning permission be granted in accordance with the Planning Application subject to the attachment of the conditions. Conditions 1. Three years 2. Drawings 3. Detailed Drawings and External Materials 4. Boundary treatment 5. Hard and Soft Landscaping 6. External Lighting 7. Site levels 8. Secure by Design Accreditation 9. Secure by Design Certification 10. Secure by Design Accreditation at ... view the full minutes text for item 10.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
1. The development hereby authorised must be begun not later than the expiration of 3 years from the date of this permission, failing which the permission shall be of no effect.
Reason: This condition is imposed by virtue of the provisions of the Planning & Compulsory Purchase Act 2004 and to prevent the accumulation of unimplemented planning permissions.
2. The development hereby authorised shall be carried out in accordance with the following approved plans and specifications:
Drawings - D01-02 – 01 – Proposed Basement GA Plan - D01-02 – 02 – Proposed Ground Floor GA Plan - D01-02- 03 – Proposed First Floor GA Plan - D01-02 – 04 – Proposed Second Floor GA Plan - D01-02 – 05 – Proposed Third Floor GA Plan - D01-02- 06 – Proposed Roof Plan - D01-02 – 21 – Proposed Elevations - D01-02 – 22 – Proposed Elevations – Colour - D01-02 – 23 – Proposed Elevations – Context Indicated - D01-02 – 24A – Proposed View Road Boundary Wall – Plan, Elevation & 3D Visual (Updated) - D01-02 – 31 – Basement Floor – Planning Approved Overlay - D01-02 – 32 – Ground Floor – Planning Approved Overlay - D01-02 – 33 – First Floor – Planning Approved Overlay - D01-02 – 34 – Second Floor – Planning Approved Overlay - D01-02 – 35 – Third Floor – Planning Approved Overlay - D01-02 – 36 – Proposed Elevations – Previous Planning Approved Outline Indicated - D01-02 – 41 – Proposed Site Sections - D01-02 – 51 – 3D Visual 1 - D01-02 – 52 – 3D Visual 2 - D01-02 – 53 – 3D Visual 3 - D01-02 – 54 – 3D Visual 4 - D01-02 – 55 – 3D Visual 5 - D01-02 – 56 – 3D Visual 6 - D01-02 – 57 – 3D Visual 7 - D01-02 – 71H Proposed Site Plan - D01-02 – 81 – Site Location Plan - D01-02 – SK44 – Proposed Basement GA Plan – Apartments – Accommodation Schedule (Additional) - D01-02 – SK45 – Proposed Ground Floor GA Plan – Apartments – Accommodation Schedule (Additional) - D01-02 – SK46 – Proposed First Floor GA Plan – Apartments – Accommodation Schedule (Additional) - D01-02 – SK47 – Proposed Second Floor GA Plan – Apartments – Accommodation Schedule (Additional) - D01-02 – SK48 – Proposed Third Floor GA Plan – Apartments – Accommodation Schedule (Additional) - D01-02 – SK49 – ASHP Enclosure Visuals – Comparison (Additional) D01-02 – SK50 – ASHP Enclosure Visuals – Additional & Roof Plan (Additional o 2169-GUA-DR-L-001 10 Illustrative Landscape Masterplan (Updated) o 21069-GUA-DR-L-002 9 Urban Greening Factor Plan (Updated) o 21069-GUA-DR-L-003 8 Planting Schedules (Updated) o 21069-GUA-DR-L-004 12 Landscape General Arrangement (Updated) - 21047_Mary Feilding Internal Daylight Sunlight Report March 2025 + Appendices (Additional) o 21034-MA-DR-TS01-REV A Appendices-1-4 (Updated) Report No: 13786_R02e (Updated)
Documents
Design & Access Statement; Heritage Assessment; • Ecological Assessment; • Energy Statement; • Circular Economy Statement and Appendices; • Surface Water and Foul Drainage Statement; • Healthy Streets Transport Assessment; • Framework Operational Site Waste Management Plan; • Sustainability Statement; • Air Quality Assessment; • Whole Life Cycle Carbon Emissions Assessment and Template; • Daylight and Sunlight Report; • Fire Statement; • Planning Statement
Reason: In order to avoid doubt and in the interests of good planning.
Detailed Drawings and External Materials
3 Prior to the commencement of building works above grade, detailed drawings, including sections, to a scale of 1:20 to confirm the detailed design and materials of the:
a) Detailed elevational treatment; b) Detailing of roof and parapet treatment; c) Details of windows and doors d) Details of entrances, which shall include a recess of at least 115mm; e) Details and locations of rain water pipes; and f) Details of balconies, privacy screens and balustrading g) Details of decorative brickwork (scale of 1:10 or 1:5) h) Details of plant screening
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.