Resolved
That Cabinet: Approved the Highways and Street Lighting 5-Year Investment Plans in Appendices 1 and 2 of the report. Delegated decisions relating ... view the full minutes text for item 185.
Cabinet approved this item on Tuesday 22 April 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
That Cabinet: Approved the Highways and Street Lighting 5-Year Investment Plans in Appendices 1 and 2 of the report. Delegated decisions relating ... view the full minutes text for item 185.
Report for: Cabinet – 22 April 2025
Title: Highways and Street Lighting 5-year Delivery Plan.
Report authorised by Barry Francis, Director of Environment and Resident Experience.
Lead Officers: Ann Cunningham, Head of Highways and Parking [email protected]
Peter Boddy, Group Manager Highways Infrastructure [email protected]
Ward(s) affected: All
Report for Key/ Non-Key Decision: Key Decision
1 Describe the issue under consideration. 1.1 The Council, as a highway authority, is responsible for maintaining all highway assets that fall within its 355km network and, as such, is responsible for ensuring these assets are safe and fit for purpose. In recognition of this, the Council has a long-term commitment to improve the overall quality of the local highway network. To this end, detailed investment strategies were set out in the Highway Asset Management Strategy and a Street Lighting Strategy which were both presented to and approved by Cabinet in March 2024.
1.2The levels of investment approved in the Council’s Medium Term Financial Strategy (MTFS), underpinned by a clear investment strategy, allows the development of a more strategic delivery plan comprising a rolling programme of funded improvements over the next 5 years. This report sets out a 5-year Delivery Plan, which is attached as Appendix 4. It proposes that, following approval of the Plan, maintenance /improvement programmes are developed on a rolling basis, in line with the framework set out in paragraphs 7.3 to 7.9 of this report, and that only Key Decisions are reported to Cabinet.
2 Member Introduction 2.1 Highways play a pivotal role in our daily lives. Whether we are working from home, commuting to work, taking exercise or meeting family and friends - we all rely upon welcoming and accessible streets and public realm.
2.2As a major destination, known for our rich cultural diversity, vibrant arts scene, and iconic football club, Tottenham Hotspur, Haringey is one of London’s best- connected boroughs and the local highway network is and will continue to be well used by our residents, businesses and by people from across the city and beyond. 2.3 The Borough of Culture and UEFA European Football Championships (Euros) are planned to take place in 2027 and 2028. The importance of the image of the borough during these prestigious events has been recognised. There will therefore be a particular focus on allocating capital funding for carriageway and footway maintenance in the initial three years of the delivery plan to ensure that there will be safe access to all relevant venues. There will also be a focus across service areas to assure alignment with other funded work streams that would contribute to the overall fabric of the public realm. External funding will be sought wherever possible to supplement our own funding.
2.4The Council has adopted highway asset management policies and practices that ensure the greatest benefit for the whole community. I am pleased that we can now move to longer-term planning which will ensure the best use of our resources, including alignment with other improvements to our public realm, utility planned works where these opportunities arise, and in addition, the phased introduction of new innovative treatments as they emerge.
2.5This report sets out our first 5-year Delivery Plan, comprising some £35.775m investment to improve Haringey’s highway infrastructure. This includes over £2m towards essential repairs to three highways bridge structures namely, Ferry Lane, Wareham Road and Cornwall Road, to be delivered in year one and £4.925m of street lighting improvements to be delivered over the 5-year period. Should any additional funding be allocated to the Council, where possible, these funds should in the first instance be considered to reduce the Council’s borrowing.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Five Year Delivery PlanAppendix 4 | 2.9 MB | Download |
PDF |
Highways and Street Lighting Delivery Plan 25/26 to 29/30Minutes | 562 KB | DownloadRead as text |
Follow Cabinet at Haringey and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Nov 2026 | Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None | Decided | Open |
| 10 Nov 2026 | Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None | Decided | Open |
| 10 Nov 2026 | Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None | Decided | Open |
| 10 Nov 2026 | Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None | Decided | Open |
| 10 Nov 2026 | Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.