Borough Wide Kitchen & Bathroom Modernisation & Associated Works (2025-2027)

Approved Executive 1 paper

Cabinet Member Signing approved this item on Tuesday 10 June 2025. Below is the council's own wording, with the papers it was decided on.

Item13

Resolved

RESOLVED 2.1 Pursuant to the council’s contract Standing Order (CSO) 2.01. c and in accordance with Statement of Principles CSO 0.08., for the Cabinet Member for Housing and Planning approved the award of a Measured Term Contract to the preferred contractor identified in exempt Appendix A for the renewal of kitchens, bathrooms and associated works to borough wide dwellings. This would be for the maximum sum of £4.8m for the period of 2 years, with the option of a time and value extension of one year. 2.2 Approved the issue of a letter of intent for approval for the issue of a letter of intent to the approved contractor. This will be for an amount up to £480,000 which represents 10% of the contract sum. 2.3 Approved the professional fees of £443,302 that represents 9.24% of the contract sum. 2.4 Noted and approved the total project costs set out in the exempt part of the report. Reasons for decision 3.1 One of the key objectives of the Housing Asset Management Strategy is to bring all of the Council’s Housing stock up to the Decent Homes Standard by 2028. The Decent Homes Standard is a minimum standard regulatory requirement for all social housing landlords and was established to ‘bring health benefits to tenants and reduce health inequalities’ (Decent Homes Guidance 2006). This work is key in helping the Council maintain a principal strategy, by providing modern facilities with the modernisation of kitchens and bathrooms for our residents. 3.2 Cabinet Member approval is required to award a Measured Term Contract (MTC) for internal modernisation works to circa 300 dwellings boroughwide over a period of two years, with further addresses being added in the second year of the contract. The contract will enable essential internal works such as the renewal of kitchens, bathrooms and associated works to progress. This is following a tendering ... view the full minutes text for item 13.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Recommendations

2.1Pursuant to the council’s contract Standing Order (CSO) 2.01. c and in accordance with Statement of Principles CSO 0.08., for the Cabinet Member for Housing and Planning to approve the award of a Measured Term Contract to the preferred contractor identified in exempt Appendix A for the renewal of kitchens, bathrooms and associated works to borough wide dwellings. This will be for the maximum sum of £4.8m for the period of 2 years, with the option of a time and value extension of one year.

2.2For Cabinet Member for Housing and Planning to approve the issue of a letter of intent for approval for the issue of a letter of intent to the approved contractor. This will be for an amount up to £480,000 which represents 10% of the contract sum.

2.3For Cabinet Member for Housing and Planning to approve the professional fees of £443,302 that represents 9.24% of the contract sum.

2.4For Cabinet Member Housing and Planning to note and approve the total project costs set out in the exempt part of the report.

Reasons for decision

3.1One of the key objectives of the Housing Asset Management Strategy is to bring all of the Council’s Housing stock up to the Decent Homes Standard by 2028. The Decent Homes Standard is a minimum standard regulatory requirement for all social housing landlords and was established to ‘bring health benefits to tenants and reduce health inequalities’ (Decent Homes Guidance 2006). This work is key in helping the Council maintain a principal strategy, by providing modern facilities with the modernisation of kitchens and bathrooms for our residents.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Borough Wide Kitchen & Bathroom Modernisation & Associated Works (2025-2027)Minutes 263 KB DownloadRead as text

At this meeting

Whole meeting
13Borough Wide Kitchen & Bathroom Modernisation & Associated Works (2025-2027)This decision
14Exclusion of the Press and PublicOn the agenda

On this subject at Haringey

Search all
  1. Borough Wide Kitchen & Bathroom Modernisation & Associated Works (2025-2027)This decision
  2. Borough Wide External & Communal Measured Term Contract (2025-2027)Approved
  3. Borough Wide bin Chute repair, maintenance & installationApproved
  4. To approve decision to implement a borough wide PSPONoted
  5. Borough Wide Kitchen & Bathroom Modernisation & Associated Works (2024-2026)Approved
  6. Public space protection order - haringey borough-wideApproved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies