That Cabinet: Pursuant to the Council’s Contract Standing Order (CSO) 8.01 (use of Council Dynamic Purchasing System) and CSO 2.01.1C (Cabinet approval required for contracts valued at £500,000 or more), approved the award of a Solar Photovoltaic (PV) maintenance, metering, and monitoring contract to Contractor A (identified in Part B exempt section of the report). The contract was for an initial period of two years from 1 July 2025 to 30 June 2027, with an option to extend by one year to 30 June 2028 and a further option to 30 June 2029, with the total contract value identified in the Part B exempt report. Reasons for Decision The Council had its own established DPS, the LCP DPS, which was the preferred DPS for works. The tender was run as a mini competition via the DPS and was open from 17 March to 10 April 2025. ... view the full minutes text for item 210.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
Title: Award of a Maintenance, Metering and Monitoring Contract for the Council's Solar PV Installations
Report authorised by : Barry Francis, Corporate Director of Environment & Resident Experience, [email protected]
Lead Officer: Joe Baker. Head of Carbon Management, 020 8489 3976, [email protected] Ekene Ngadaonye, Renewable Energy Officer, [email protected], 020 8489 4651
Ward(s) affected: All Wards
Report for Key/ Non Key Decision: Key
1. Describe the issue under consideration
1.1The purpose of this report is to seek Cabinet approval for the award of a solar photovoltaic (PV) maintenance, metering and monitoring contract with a two-year initial period from 1 July 2025 to 30 June 2027, then two options to extend by one year each, from to 1 July 2027 to 30 June 2028 and 1 July 2028 to 30 June 2029, to Contractor A.
1.2This contract is needed to ensure that the electrical systems remain safe and secure on the buildings where they are located, and that they remain operationally sound to ensure maximum energy is generated. Thus, reducing energy spend by the building users.
1.3The maintenance element includes annual inspection and testing of all PV components; repair of any damaged or faulty parts; and cleaning, where necessary. The metering element includes upgrading traditional meters to smart/automatic meters so the solar PV generation can be monitored remotely. The monitoring elements includes the remote monitoring of our systems on an online platform.
1.4The contract will be a measured term Joint Contracts Tribunal (JCT) contract. The contract will commence with 37 solar PV systems managed by the Council’s Energy Team and four sites managed by the Council’s Corporate Landlord team. These systems form the “core offer” within the contract. The contract has been designed to be flexible so that other sites can join or leave the contract at any point during the contract period. Other sites may include housing newbuilds, schools, and any other third-party owned installation located on a Council building. These systems have formed the “additional offer” as they are not yet guaranteed. The total costs of the “core” and “additional” works have been included in the procurement process and has set the upper contract value that all bidders have provided.
1.5The procurement was run as a mini competition under the Council’s own established Dynamic Purchasing System (DPS), the London Construction Programme Dynamic Purchasing System (LCP DPS).
2. Cabinet Member Introduction Behind every flagship climate programme there are the nuts and bolts that hold its moving parts together. And indeed, this solar PV maintenance contract sits at the heart of our borough-wide push for climate resilience and renewable energy.
Our solar installations tell a story of Haringey's commitment to sustainable infrastructure. From the initial 37 systems installed to the 46 recent systems in our housing developments, we've built an impressive network capable of generating clean electricity across our estates. This borough’s hugely ambitious council house building programme is not simply about numbers - although we are well on track to deliver 3000 by the end of the decade - it’s about delivering high-quality, comfortable homes, designed to reduce carbon emissions and household bills. On- site renewables, like solar panels, now come as standard.
Yet the harsh reality remains that even the most robust renewable technology requires proper care to deliver its full potential. Many of our earliest systems now approach their teenage years without the structured maintenance regime they deserve. This contract marks a critical turning point in our approach.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.