Resolved
That Cabinet: Approved a variation of the contract with Equans Regeneration Ltd (formerly Engie Regeneration Ltd) by an increasing the Noel Park project budget from £21.46m to £32.2m, an increase of £10.7m; and also approve an increase in the professional fees budget from £847,000 to £1,270,500, an increase of £423,500, to enable the completion of essential Health & Safety and Decent Homes as part of Noel Park project, with funding allocated from the existing Cabinet approved HRA capital investment programme budget.