RESOLVED The Cabinet Member for Children, Schools and Families authorises the Council: To agree and enter into the funding agreement between the Council, the London Diocesan Board for Schools and the Governing Body and/or Trustees of the St Mary’s Church of England Primary School in the agreed form annexed to Part B (exempt) of this report. Alternative options considered: Do Nothing – If the Council did not proceed with the capital schemes as outlined the High Needs Block would continue to come under sustained pressure. In academic years 27/28 and 28/29 the cost to the service would be approx. £2.5m. To commence the site surrender as recommend in this document. The new provision at St Marys Church of England Primary (run by Park View) once scaled would provide an avoidance between 27/28 and 28/29 of £1.757.457. This figure had been calculated (see table one) once the Councils placement costs are deducted, and the mobilisation payment provided to Park View in the initial scaling up period. This cost avoidance alone covered the cost of the site surrender. The St Marys site has further potential for cost avoidance in future years to scale up from 34 places to 42 which provided further flexibility within the system if required.
Word for word from the decision Haringey published for this meeting.Source: www.minutes.haringey.gov.uk
Title: Legal Agreement between Haringey Council and St Mary’s Infant School
Report authorised by: Ann Graham, Corporate Director Children's Services
Lead Officer: Caroline Brain, Director CYP Commissioning & Programmes
Ward(s) affected: All
Report for Key Decision:
1. Describe the issue under consideration.
1.1Haringey Children Service’s Team secured £7m of DfE Capital funding, alongside HNPCA contribution of £3.2m and other LA contributions of £2.2m, totalling £12.4m to develop education provision for children and young people with special education needs and disabilities (SEND) as part of the Safety Valve Programme.
1.2This scheme is one of the six of the original schemes approved by Cabinet on the 6th of February 2024, each provision to be delivered within the £12.4m Safety Valve Programme Funding envelope - refer to background paper (Haringey Safety Valve Programme SEND Resources Provision Cabinet Paper 2023).
1.3This paper focuses on St Mary’s Infant School site, which will be operated as a satellite site by Park View Secondary School. This will enable the Council to create the 34 key stage 3/4, Social, Emotional & Mental Health (SEMH) resource provision places.
1.4Cabinet approval is required for the signing of a funding agreement, whereby the London Diocesan Board for Schools (LDBS) will surrender all occupational rights and interests in the St Mary’s Church Lane Infant site (“Church Lane Site”) and any claims to call forth the statutory transfer of the site under the Schools and Framework Act 1998. The Council in return for this surrender will provide funding towards LDBS for the value amount (see exempt appendix one), this is for the expansion of St Mary’s Junior School Site at Rectory Road (“Rectory Road Site”) This will allow the infant pupils to vacate the Church Lane site, allowing the Council to take possession on a permanent basis for the programme team to build the required SEN provision.
1.5The Councils’ interests are protected as the Church Lane Site will be surrendered on the signing of the funding agreement along with the caretaker’s house also located within the Church Lane Site. The Council will then immediately grant a licence back to allow the school to remain on the Church Lane site. The funding value for site surrender as detailed will be released in two instalments, the first instalment will be subject to condition precedents
1 will be initially released to enable LDBS to complete their pre-application work (see exempt appendix one). The remaining funding will be released in arrears monthly according to evidence provided by the LDBS of works completed in that monthly period. The retention will be paid when the Church Lane Site is entirely vacated under the licence.
1.6The LDBS has confirmed they have the remaining balance will be provided by the Grieg Trust for the development costs for the completion of the works at the Rectory Road Site and are not just solely relying on the agreed funding.
1.7The Council would then undertake phase two works to reconfigure the Church Lane site upon vacant possession whereby Haringey’s business as usual procurement rules would apply. The cost of delivering the site surrender and the capital alteration works at Church Lane site is detailed in the (exempt appendix one,) including the full costs of the funding agreement. This outline proposal has already been approved by Cabinet. However, this paper is solely concerned with the presenting the detail of this specific scheme comprising the site surrender of the Church Lane site and the release of the detailed costings in the (exempt appendix one) to the LDBS under the funding agreement as described in this report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.