Resolved
RESOLVED That the Cabinet Member for Housing and Planning (Deputy Leader): 3.1. In line with Contract Standing Orders (CSO) 8.01, and 18.03.3, approval is sought for a variation to the existing contract in the sum of £1,751,359.36, revising the total contract value to £10,164,213.00. Additionally, approval is requested to amend the programme duration from 78 weeks to 150 weeks. This extended timeframe will accommodate the process of obtaining Gateway 2 approval for the works from the Building Safety Regulator (BSR), as well as provide sufficient allowance for final sign-off at Gateway 3. 3.2. It should be noted that any variation in the contract sum or programme will not affect the total amount rechargeable to leaseholders, as outlined in the Notice of Estimates issued on 23 August 2024. 3.3. Issue a Letter of Intent to the contractor in line with CSO 16.04 for the sum of £900k which is no more than 10% of the revised contract sum. The Letter of Intent will enable the contractor to place an order with their supply chain to enable the revised programme to be met. Alternative options considered. Do nothing was considered and ruled out. This is because the works to Kenneth Robbins House is essential to ensure the building meets current fire safety regulations. Therefore, the Council has no option but to appoint a competent contractor to deliver the works. Retendering was also considered; however, the appointed contractor was awarded the contract having submitted the most economical and advantageous tender. There is no guarantee that retendering the project will result in a better outcome in terms of cost and programme. It should also be noted that the extended period for securing Building Safety Regulator approval will still apply, therefore any alternatives bids will include a significant risk profile and cost for a delayed start to the works. The only option available to the Council is to accept the uplifted costs submitted by the appointed contractor. This will ensure the works commence as soon as possible thus ensuring the building meets current fire safety regulations.