Extension of current Gas Maintenance Contracts

Decided Executive 1 paper

AI summaryHaringey’s Cabinet Member for Housing and Planning and Deputy Leader approved gas servicing extensions of up to six months until 31st March 2026, with stated additional costs of £1,305,000.00 for Purdy and £1,220,000.00 for Sureserve. [3.1] [P2] [P3]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedUntil 31st March 2026, with contractor management continuing [3.2] [6.6]
Money£1,305,000.00 and £1,220,000.00Additional costs for Purdy and Sureserve [P2] [P3]
What happens nextAward new gas servicing contractThe Council advertised an opportunity within the next 6 months [P31]
Who it affectsResidents and council heating servicesContinuity, repairs and landlord safety duties [4.2] [P6] [6.5]

What was decided

The Cabinet Member for Housing and Planning and Deputy Leader approved variations to contracts dated 1st October 2020, with an initial expiry date of 30th September 2025, and extended both current terms for six months from 1st October 2025 to 31st March 2026. Report 3.1, 3.2

Purdy Contracts Limited’s extension adds £1,305,000.00, bringing its total contract value to £18,759,908.90. Sureserve Compliance South Ltd’s extension adds £1,220,000.00, while its aggregated total contract value remains £11,800,000.00. Report P2, P3

The decision was retaken after the contractor’s name and information about contract values were clarified. There were no declarations of interest for the item. Report 3.3

Why

Continuing the contracts allows servicing and maintenance of domestic and commercial heating systems to continue with minimal disruption from faults and breakdowns. Report P6

The extension supports compliance with regulation 36 landlord duties under the Gas Safety Regulations 1998 and the Council’s duty to keep residents safe. Report 4.2, 6.5

The report describes the extension as the most economically advantageous route because a new interim provider would almost certainly increase the contract sum in the current financial climate. Report 4.3

What happens next

Complete the long term domestic and commercial heating procurement, with mobilisation of the new contracts by 1st April 2026 to align with the new financial year. Report 4.4

Award the new gas servicing contract within the next 6 months. The current variation will cover the service until award. Report P31

Continue managing both contractors during the extension to ensure contract requirements, service level agreements and performance targets are met. Report 6.6

The money

  • £1,305,000.00 Additional cost of the Purdy six month extension Report P2
  • £1,220,000.00 Additional cost of the Sureserve six month extension Report P3
  • £18,759,908.90 Total Purdy contract value after the extension Report P2
  • £11,800,000.00 Aggregated Sureserve contract value, unchanged after the extension Report P3, P16
  • £2.36m Contract value per annum for Lot 1 Report P16
  • £2.39m Contract value per annum for Lot 2 Report P17
  • £11,950,000.00 Purdy total five year sum before the May 2024 increase Report P17
  • £5,504908.9 Purdy contract value increase in May 2024, producing a new total of £17,454,908.90 Report P17

Options considered

  • Chosen: Extend the current gas servicing contracts for six months. It maintains service continuity and safety and is described as more economical than appointing a new interim provider. Report 3.1, 4.2, 4.3
  • Rejected: Do nothing. It would leave the Council unable to meet its statutory health and safety obligations. Report 5.1
  • Rejected: Use a full procurement exercise to cover the immediate period. The procurement would not be complete before 1st October, which would leave no service for gas and heating repairs, maintenance and renewals. The longer term procurement was already underway. Report 5.2
  • Rejected: Deliver the service in house. The housing repair service lacks the required skills, and establishing a team would take significant time, planning and investment in a highly competitive market. Report 5.3

Implications

  • Financial: The six month extension adds £1,305,000.00 for Purdy and £1,220,000.00 for Sureserve. Capital & Revenue budgets already allocated for gas servicing, repairs and replacements will fund it, with no impact on current budgets. Report P2, P3, 6.4
  • Financial: The extension is funded from the M&E gas maintenance revenue budget (J19451) and was provisioned during the 2025/26 budget setting process. There is sufficient funding in the Major Works capital programme for boiler replacements, and the capital allocation and MTFS are unaffected. Report P28
  • Legal: Under Contract Standing Orders, a variation valued at £500K or more may be approved by Cabinet if the Public Contracts Regulations 2015, Finance Regulations and satisfactory contract outcomes requirements are met. Regulation 72 requires circumstances that a diligent contracting authority could not have foreseen, no change to the contract’s overall nature and no price increase above 50% of the original value. Report 12.2, 12.3
  • Legal: The report says the proposed variation appears to meet Contract Standing Orders 18.03.1 and 2.01(d). The Monitoring Officer is not aware of any legal reason preventing approval. Report 12.5, 12.6
  • Risk: The extension prevents a gap in gas and heating repairs, maintenance and renewals while the new contract is procured and provides cover until award. Report 5.2, P31
  • Equalities: The Council must have due regard to eliminating discrimination, harassment and victimisation, advancing equality of opportunity and fostering good relations for the listed protected characteristics. Report P41, P42, P43, P44, P45
  • Climate: The report states that the extension has no impact on carbon and climate change. Report 8.1
  • Other: The extension supports the Corporate Delivery Plan theme of Homes for the future, which aims for safe, sustainable, stable and affordable homes and better social housing and landlord services. Report 7.1

Who and where

  • Purdy Contracts Limited Report P2, P17
  • Sureserve Compliance South Ltd, formerly K&T Heating Services Ltd Report P3, P16
  • Residents relying on the Council’s domestic and commercial heating services Report P6, 4.2
  • Haringey Council housing repair service Report 5.3, 6.6

Timeline

  • September 2019: Homes for Haringey began procurement under the Public Contract Regulations 2015 Restricted Procedure. Report 6.1
  • October 2020: The two contracts commenced, with an initial two year term and options to extend in one year increments up to October 2025. Report 6.1
  • 23 June 2022: Both contracts were novated from Homes for Haringey to Haringey Council. Report 6.3
  • May 2024: Purdy’s contract value increased to cover additional services needed for safety, heat and hot water. Report P17, P18
  • 15 September 2025: The original decision to be amended was signed. Report P49
  • 1st October 2025: Both six month extensions took effect. Report 3.2, P2, P3
  • 31st March 2026: Both six month extensions end. Report 3.2
  • 1st April 2026: The new long term domestic and commercial heating contracts are planned to mobilise. Report 4.4

Plain English for the jargon

  • Contract Standing Order (CSO): Council rules used to approve the contract variation. [3.1] [12.2]
  • Public Contracts Regulations 2015: Procurement rules governing the original award and the proposed variation. [6.1] [P32] [12.2]
  • Regulation 72: The provision cited as allowing this contract variation. [P32] [12.3]
  • Gas Safety Regulations 1998: Safety rules including regulation 36 duties for landlords. [4.2] [6.5]
  • M&E gas maintenance revenue budget (J19451): The budget from which the extension is funded. [P28]
  • MTFS: The Council’s medium term financial strategy, which the extension does not affect. [P28]
  • Service level agreements: Contract requirements and performance targets that the Council will manage during the extension. [6.6]
  • Novation: The transfer of both contracts from Homes for Haringey to Haringey Council. [6.3]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item32

Resolved

Declarations of Interest for this Item: None
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing, 6 pages

Recommendations

3.1It is recommended that the Cabinet Member for Housing and Planning and Deputy Leader, in accordance with the Council’s Contract Standing Order 18.03.3 in accordance with CSO 2.01(d) approves a variation/extension to the contracts dated 1st October 2020 with an initial Expiry Date of 30th September 2025 between the Council and the Service Provider for [a gas servicing programme in Haringey – Lot 1 and Lot 2] (the “Contracts”) under Contract Standing Order 18.03.3 in accordance with CSO 2.01(d) and agree to extend both current Gas Servicing contracts with the following contractors, by extending the current term of the Service by up to six (6) months until 31st March 2026.

 Purdy Contracts Limited, effective from 1st October 2025 to provide for a further extension of six (6) months to 31st March 2026, at an additional cost of £1,305,000.00. Bringing the total contract value to £18,759,908.90.

 Sureserve Compliance South Ltd, (formerly K&T Heating Services Ltd) - effective from 1st October 2025 to provide for a further extension of six (6) months to 31st March 2026, at an additional cost of £1,220,000.00. The aggregated total value of the contract value will remain the same as the original contract value figure of £11,800,000.00 and only the duration of the Contract is to be amended.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Extension of current Gas Maintenance ContractsMinutes 6 pages DownloadRead as text

At this meeting

Whole meeting
27FILMING AT MEETINGSNoted
32Extension of current Gas Maintenance ContractsThis decision

Who was there

1 of 1 attended
SW
Councillor Sarah WilliamsCommittee Member, present

On this subject at Haringey

Search all
  1. Extension of current Gas Maintenance ContractsThis decision
  2. Extension of current Gas Maintenance ContractsAgreed

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies