London Borough of Haringey
Cabinet Member Signing, Monday 1 December 2025 at 10.30am

Park View Secondary School Block A Roof Replacement - Award of Contract for Construction Related Consultancy Services

Decided Executive 1 paper

AI summaryHaringey Council's Cabinet Member for Children, Education and Families approved a contract with Consultant B for RIBA stages 2 to 6 roof replacement consultancy at Park View School, up to £688,956.80, and approved a £100,000 letter of intent.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedBlock A and part of Block B roof replacement
Money£688,956.80; £100,000Contract ceiling and approved letter of intent
What happens nextIssue letter of intentDesign stages 2 to 6 and funding application support
Who it affectsPark View School pupils and staffExtra temporary accommodation during replacement works

What was decided

The Cabinet Member for Children, Education and Families approved the award of a contract to Consultant B for RIBA stages 2 to 6 construction related multidisciplinary consultancy services. It will support replacement of the Block A roof and a section of the Block B roof at Park View School. Report 3.1

The contract value is up to £688,956.80. Report 3.1

The Cabinet Member also approved issuance of a letter of intent to the value of £100,000. Report 3.2

Why

An external structural engineer found Reinforced Autoclaved Aerated Concrete in the roof structural slab. Due to the risk of failure and collapse, the top floor, containing 14 classrooms and office space, was vacated on the 14th of April 2023. The other floors were confirmed safe for students and staff. Report 4.1

A curriculum and space analysis found that the school needed temporary accommodation, including 13 classrooms, one shared office and four toilets, until the structural issue could be remediated. Interim teaching in shared spaces such as the sports gym was not sustainable and affected teaching and learning. Report 4.1, 4.2

Consultant B ranked first with a total score of 73.94, ahead of Consultant C at 70.85 and Consultant A at 61.25. Bids were assessed on a 50:40:10 quality, price and social value weighting. Report 6.5, P29, P30, P31

What happens next

A letter of intent with a value of £100,000 is to be issued. Report 3.2

Consultant B will develop the design from RIBA stages 2 to 6 and assist with funding application documents to confirm the Department for Education funding amount. The delivery contract form will be reviewed during RIBA stage 2 for a more economical approach. Report 4.8

The project will remove all RAAC panels and install a new roof deck and covering on Block A and the affected Block B section. Levels 2 and 3 of Block A and one section of Block B will be vacated, with extra temporary classrooms provided. Pupils can then return to Blocks A and B and existing temporary accommodation will be removed. Report 4.7

The money

  • £688,956.80 Maximum consultancy contract value. Report 3.1
  • £100,000 Approved letter of intent value. Report 3.2
  • £500,000 Contract value normally requiring Cabinet approval. Report P50
  • 10% Alternative letter of intent ceiling based on contract value. Report P51
  • 10% Usual design development contingency allowance from end of RIBA stage 1. Report 4.12
  • 20% Risk allowance recommended for the design team fees. Report 4.12
  • 10% Contingency included in the award value. Report 6.7

Options considered

  • Chosen: Option 2: remove all RAAC from Blocks A and B and replace the affected building fabric.. It removes all RAAC, allows classes to return to Blocks A and B and is the option the Department for Education advised it would fund. Report P24
  • Rejected: Do nothing.. The Department for Education has stated that all RAAC must be removed, and the Council would fail its statutory duty to provide sufficient school places. Report 5.1
  • Rejected: Option 1: retain and brace the existing RAAC panels from below.. It would not comply with the Department for Education requirement to remove all RAAC. Report P23
  • Rejected: Option 3: construct a new modular block and demolish Block A.. The feasibility study found that the existing building was in good condition and that the option would not provide potential future savings. Report P25, 6.4
  • Rejected: Deliver the service in house.. The Council has no current resource with the capacity, specialist expertise or qualifications needed. Report 5.2
  • Rejected: Invite open tenders through Contracts Finder.. It would create a protracted tender period and delay the project. Report 5.3
  • Rejected: Extend the contract of the design team that completed the feasibility study.. It would not comply with the Public Procurement Regulations, so a new tender was required. Report 5.4
  • Rejected: Use an alternative public sector DPS.. It would not comply with CSO 8.02 because the London Construction Programme DPS had been deemed suitable. Report 5.5

Implications

  • Financial: The Department for Education will reimburse Haringey for most roof replacement and temporary accommodation costs. Haringey must still fund some elements, mainly internal resource costs. Report 4.10
  • Risk: RAAC in the roof structural slab created a risk of failure and collapse, requiring the top floor to be vacated. Report 4.1
  • Legal: Doing nothing would breach Haringey's statutory duty to provide sufficient school places, and the Department for Education has stated that all RAAC must be removed. Report 5.1
  • Equalities: No impacts on people with protected characteristics are envisaged. The existing temporary building is DDA compliant on the ground floor, with ramps and disabled toilets, and contract management will guard against preventable or disproportionate inequality. The consultant must comply with the Public Sector Equalities Duty. Report P55, P56, P57
  • Climate: The design includes a green roof and a photovoltaic array. The report says these will improve building energy costs and reduce heat build up in the top floor. Report 8.2, 8.3
  • Risk: The Quantity Surveyor recommended a 20% risk allowance instead of the usual 10%, based on the feasibility risk log and pending intrusive surveys. Report 4.12
  • Financial: The award includes money for surveys paid through the consultant and a 10% contingency managed through change control arrangements. Report 6.7
  • Legal: The tender used the LCP Minor Works DPS, and Strategic Procurement supported the award. As the award is a Key Decision, contracts valued at £500,000 or more normally go to Cabinet, although the Leader may take or delegate the decision between meetings. Report P45, P47, P50

Who and where

  • Pupils at Park View School Report 4.1, 4.7
  • Staff at Park View School Report 4.1
  • Disabled users of temporary buildings Report P55
  • Haringey Council Report 4.10, 4.11
  • The Department for Education Report 4.6
  • Consultant B Report 3.1

Timeline

  • 14th of April 2023: The top floor of Block A was vacated because of the risk of failure and collapse. Report 4.1
  • September 2023: Construction and installation of the temporary accommodation was completed. Report 4.4
  • September 2024: A multidisciplinary design team was appointed to complete the feasibility study. Report 4.5
  • January 2025 and July 2025: The temporary accommodation rental period was extended while the permanent solution was developed. Report 4.4
  • May 2025: The Department for Education agreed funding for the recommended permanent approach. Report 4.6
  • 3rd September 2025: Approval was granted to begin the tender exercise. Report 6.5
  • 2025-12-01: The contract award and letter of intent approval were considered at the Cabinet Member Signing meeting.
  • summer 2028: Completion of the chosen permanent remediation option is currently forecast.

Plain English for the jargon

  • RAAC: Reinforced Autoclaved Aerated Concrete found in the roof structural slab.
  • DfE: Department for Education.
  • RIBA stages: The design stages covered by the consultant's appointment.
  • CSO: Contract Standing Order.
  • LCP DPS: London Construction Programme Dynamic Purchasing System, the route used to invite tenders.
  • DDA: The compliance standard applied to the ground floor of temporary buildings.
  • Letter of intent: A letter approved for issuance with a stated value of £100,000.
  • Photovoltaic array: A design feature that the report says will improve building energy costs and reduce heat build up.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14

Resolved

DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing, 6 pages

Recommendations

For the Cabinet Member for Children, Education and Families, pursuant to Contract Standing Order (CSO) 0.08, to:

3.1Approve the award of Contract to Consultant B for RIBA 2-6 construction related multi- disciplinary consultancy services up to the value of £688,956.80, to support the replacement of Block A roof and a section of Block B roof at Park View School, pursuant to CSOs 0.08, 2.01c and 8.01.

3.2In accordance with CSO 16.04, approve issuance of a letter of intent to the value of £100,000.

Reasons for decision

4.1Following an inspection of the teaching Block A at Park View School by an external structural engineer, Reinforced Autoclaved Aerated Concrete (RAAC) was discovered forming part of the structural slab of the roof. On the 14th of April 2023 due to the risk of failure and collapse of this building element it was recommended that the top floor of the building, consisting of 14 classrooms and office space, immediately be vacated. It had been confirmed by the structural engineer that the other floors of the building could be safely used by students and staff. A curriculum and space analysis was undertaken and it was determined that the school required temporary accommodation including 13 classrooms, 1 shared office and 4 toilets until the structural issue can be remediated.

4.2Interim teaching arrangements were initially put in place at the school from Monday 17th April 2023. These consisted of teaching many pupils in shared/communal spaces such as the sports gym. This was not considered to be a sustainable solution and was impacting the quality of teaching and learning and additionally the gym was required to support GCSE exams from mid-May.

4.3A Cabinet Member approval was granted in May 2023 to award a contract to Portakabin Ltd to provide required temporary accommodation by September 2023 for an 18 month hire period at Park View School.

4.4Construction and installation of the temporary accommodation was completed on programme in September 2023. Variations of the Cabinet approval was granted by the Director of Schools and Learning in January 2025 and the Cabinet Member for Children, Education and Families in July 2025, for an extension of the rental period whilst a permanent solution to remediate the RAAC is developed.

4.5A multi-disciplinary design team was appointed in September 2024 to undertake a feasibility study to determine the most appropriate solution to fully remediate the RAAC.

4.6Agreement for funding of the recommended approach for a permanent solution to remediate the RAAC was received from the Department for Education (DfE) in May 2025, which on completion, will allow students to return to the main building.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Park View Secondary School Block A Roof Replacement: Award of Contract for Construction Related Consultancy ServicesMinutes 6 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 1 attended
ZB
Councillor Zena BrabazonCommittee Member, present

On this subject at Haringey

Search all
  1. Park View Secondary School Block A Roof Replacement - Award of Contract for Construction Related Consultancy ServicesThis decision
  2. Review of Parking Fees and Charges 2026-2027Decided
  3. Park View Secondary School Block A Roof Replacement - Permission to initiate tender action for Construction Related Consultancy ServicesApproved
  4. Park View Secondary School Temporary Accommodation – Variation of Hire ContractApproved
  5. Car parking charges reviewApproved
  6. Parking strategy and policy/charges review - feedback to statutory consultationApproved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies