London Borough of Haringey
Cabinet Member Signing, Thursday 4 December 2025 at 11.45am

Variation of contracts for the delivery of fire safety works

Approved Executive 1 paper

AI summaryThe Cabinet Member for Housing & Planning and Deputy Leader approved 167% variations to three fire safety contracts, allowing work to continue while a longer term contract is procured. Each variation is £833,333. [D] [4.2] [P2]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedEach contract varied by 167%. [D] [P2]
Money£833,333 variation per supplier [P2]Each supplier's original value was £499,999. [P2]
What happens nextLonger term contract procurement [5.5] [P13]Variations cover the interim procurement period. [4.2] [6.7]
Who it affectsResidents and fire safety work [4.1]Continuity helps reduce overdue actions. [4.1] [4.5]

What was decided

The Cabinet Member for Housing & Planning and Deputy Leader approved contract variations for three suppliers. [D]

Each of the three existing contracts is varied by 167%. [D] [P2] Report P2

The variation covers new and existing fire safety actions for the remainder of the financial year within available budgets. [6.6] Report 6.6

Why

Work had to continue because stopping would increase actions, the risk of overdue work and danger to resident safety. [4.1] Report 4.1

External contractors were needed for flexibility, resources, skills and certification. [4.3] Report 4.3

Keeping 2024/25 rates offered value for money, while variation protected the Council's commitment to reduce high risk overdue actions. [4.4] [4.5] Report 4.4, 4.5

What happens next

Continue procurement of a longer term contract, with the existing variations providing interim cover. [4.2] [6.7] [P13] Report 4.2, 6.7, P13

Complete new and existing fire safety actions for the rest of the financial year within available budgets. [6.6] Report 6.6

Monitor expenditure and address any variances promptly. [P33] Report P33

The money

  • £499,999 Original contract value for each of three suppliers. Report P2
  • £833,333 (167%) Variation for each of three suppliers. Report P2
  • 40% Revenue share covered by the Residential Buildings Fire Risk budget. Report P33
  • 60% Capital share funded through Fire Safety capital programmes. Report P33
  • £500,000 or more Aggregate contract value threshold for Cabinet approval. Report P43

Options considered

  • Chosen: Vary the three existing contracts. This maintains fire safety work while the longer term contract is procured and retains the existing rates. [4.2] [4.4] Report 4.2, 4.4
  • Rejected: Do nothing. Actions would build up with no suitable compliant delivery capacity, and the Council's commitments to the regulator would be missed. [5.1] [5.2] Report 5.1, 5.2
  • Rejected: Utilise the DLO to deliver works. The DLO was under significant pressure to deliver the Responsive Repairs Service and lacked the competencies and resources needed for the fire safety work. [5.3] [5.4] Report 5.3, 5.4
  • Chosen: Procure new contracts. This procurement is being progressed. The variations allow enough time for it and maintain delivery in the interim. [5.5] [P13] Report 5.5, P13
  • Rejected: Use an external framework for a direct award to a separate contractor. Strategic Procurement considered that the Council needed to maintain internal control over the procurement process. [5.6] [P15] Report 5.6, P15

Implications

  • Risk: Without variation, the backlog and overdue actions could grow, putting resident safety and the commitment to the regulator at risk. [4.1] [4.5] [6.5] [6.6] Report 4.1, 4.5, 6.5, 6.6
  • Legal: Cabinet has approval powers for aggregate contract values of £500,000 or more, subject to the Leader's agreement. The total across the three suppliers is below the Public Contracts Regulations 2015 threshold, and the Director of Legal and Governance saw no legal reason preventing approval. [P39] [P43] [P44] [P45] Report P39, P43, P44, P45
  • Financial: Using the rates agreed during the original procurement was intended to provide value for money because market rates had increased. [4.4] Report 4.4
  • Financial: The revenue portion is 40% and the capital portion is 60%. The decision leads to a net saving to the service budget, with monitoring and prompt action on variances. [P33] Report P33
  • Financial: The contracts operate on a call off basis, so the Council will only be charged for completed work. [6.10] Report 6.10
  • Staffing: External contractors provide the needed resources, flexibility, skills and certification, while the DLO lacks sufficient capacity for this work. [4.3] [5.4] Report 4.3, 5.4
  • Equalities: The equality impact is unchanged from the original award reports. [P47] Report P47
  • Climate: The decision does not affect the carbon and climate change agenda. [8.1] Report 8.1

Who and where

  • Residents Report 4.1, 4.5
  • Three external suppliers Report 3.1, 4.3, P2
  • Council in house teams Report 4.2
  • Regulator for Social Housing Report 4.5, 6.1
  • DLO and Responsive Repairs Service Report 5.3, 5.4
  • Council fire safety service Report 6.9, P33

Timeline

  • 2024: Three contracts were placed within a wider award to five contractors for overdue fire risk assessment actions. [6.1] Report 6.1
  • 2024/25: The existing contractor rates were agreed during the original procurement. [4.4] Report 4.4
  • March 2025: The one year contract period commenced. [6.3] Report 6.3
  • May 2025: The Council committed to complete the remaining actions by this point. [6.5] Report 6.5
  • November 2025: The original contract values were due to be exhausted. [6.2] Report 6.2
  • remainder of this financial year: New and existing fire safety actions are to be delivered within available budgets. [6.6] Report 6.6
  • March 2026: Current contractual arrangements and rates will continue until this point. [6.3] Report 6.3

Plain English for the jargon

  • Contract Standing Orders (CSOs): Council rules used to approve this contract variation. [3.1] [P43] [P44]
  • Public Contracts Regulations 2015 (PCR 2015): Procurement rules under which the total is below the relevant threshold, so the variation requirement does not apply. [P39] [P45]
  • Call off contract: A contract under which the Council is charged only for completed work. [6.10]
  • Fire risk assessment: Regular assessment of blocks and communal areas used as means of escape, used to identify and manage deficiencies. [6.4]
  • DLO: An alternative delivery body rejected because it lacked resources and competencies for the required work. [5.3] [5.4]
  • Regulator for Social Housing: The body receiving Haringey's reports and commitments about overdue high priority actions. [4.5] [6.1] [6.5]
  • Voluntary undertaking: Haringey's commitment to close the remaining actions reported to the regulator by May 2025. [6.1] [6.5]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

RESOLVED For the Cabinet Member for Housing & Planning and Deputy Leader, pursuant to Contract Standing Orders 18.03.3 & 2.01(d) to approve variation of contracts to three suppliers as per the table below Each of the 3 existing contracts are to be varied by 167% due to the urgent need for continued delivery of works by existing contractors, following unavoidable delays in procuring a longer-term contract. Reasons for decision It was essential to maintain continuity to complete actions from the fire risk assessments, as stopping this for any period, will increase the number of actions, as we continue to carry out fire risk assessments in accordance with our statutory obligations and will further increase risk of them becoming overdue and putting resident safety at risk. The Council aimed to ensure that fire risk assessment actions were completed in a timely manner in line with our policy objectives for Fire & Building Safety. Varying these contracts would enable actions to continue to be completed whilst procurement of a long-term contract is undertaken, that would support and compliment delivery of actions by in-house teams. External contractors were essential to this delivery programme due to the flexibility and amount of resource required as well as the level of skill and certification required to demonstrate competency. The variation would also ensure that remediation works could be delivered at the existing rates agreed with the contractors, during the original procurement in 2024/25. As market rates will undoubtedly have increased since this time, this helped to ensure value for money through these variations. Haringey had also given a commitment to the regulator For Social Housing to reduce high-risk overdue actions and to ensure they are completed in a timely manner. Failure to vary the current contracts would put that commitment at risk of failure. Alternative options considered Do nothing: This option had been rejected because this would mean an accumulation of actions from the fire risk assessment remain unallocated without an appropriate facility to complete works in a compliant manner, at the required scale to meet the overarching strategic objectives, to reduce actions and meet our commitments to the Regulator for Social Housing. Utilise the DLO to deliver works: This option had been rejected as the DLO is already under significant pressure to deliver the Responsive Repairs Service. This option is not a viable proposition for the either the short or ... view the full minutes text for item 6.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing, 6 pages

Recommendations

3.1For the Cabinet Member for Housing & Planning and Deputy Leader, pursuant to Contract Standing Orders 18.03.3 & 2.01(d) to approve variation of contracts to three suppliers as per the table below

Supplier Original Contract Value Variation A £499,999 £833,333 (167%) B £499,999 £833,333 (167%) C £499,999 £833,333 (167%) 3.2 Each of the 3 existing contracts are to be varied by 167% due to the urgent need for continued delivery of works by existing contractors, following unavoidable delays in procuring a longer-term contract.

Reasons for decision

4.1It is essential to maintain continuity to complete actions from the fire risk assessments, as stopping this for any period, will increase the number of actions, as we continue to carry out fire risk assessments in accordance with our statutory obligations and will further increase risk of them becoming overdue and putting resident safety at risk.

4.2The Council aims to ensure that fire risk assessment actions are completed in a timely manner in line with our policy objectives for Fire & Building Safety. Varying these contracts will enable actions to continue to be completed whilst procurement of a long-term contract is undertaken, that will support and compliment delivery of actions by in-house teams.

4.3External contractors are essential to this delivery programme due to the flexibility and amount of resource required as well as the level of skill and certification required to demonstrate competency.

4.4The variation will also ensure that remediation works can be delivered at the existing rates agreed with the contractors, during the original procurement in 2024/25. As market rates will undoubtedly have increased since this time, this helps to ensure value for money through these variations.

4.5Haringey has also given a commitment to the regulator For Social Housing to reduce high-risk overdue actions and to ensure they are completed in a timely manner. Failure to vary the current contracts would put that commitment at risk of failure.

Alternative options considered

5.1Do nothing

5.2This option has been rejected because this would mean an accumulation of actions from the fire risk assessment remain unallocated without an appropriate facility to complete works in a compliant manner, at the required scale to meet the overarching strategic objectives, to reduce actions and meet our commitments to the Regulator for Social Housing.

5.3Utilise the DLO to deliver works

5.4This option has been rejected as the DLO is already under significant pressure to deliver the Responsive Repairs Service. This option is not a viable proposition for the either the short or medium to long term planning of the Council, due to the lack of competencies and resources to meet the required standards.

5.5Procure new contracts without first varying existing contracts

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Variation of contracts for the delivery of fire safety worksMinutes 6 pages DownloadRead as text

At this meeting

Whole meeting
6Variation of contracts for the delivery of fire safety worksThis decision
7Exclusion of the Press and PublicOn the agenda

Who was there

1 of 1 attended
SW
Councillor Sarah WilliamsCommittee Member, present

On this subject at Haringey

Search all
  1. Variation of contracts for the delivery of fire safety worksThis decision
  2. Extension and variation of the contracts for Mental Health Pathway servicesApproved
  3. Variation of Contracts Awarded to Three Law Firms in relation to Housing Disrepair CasesApproved
  4. Variation to a work contracts for renovation and repurposing of 20A & 20B Waltheof Gardens, Tottenham N17 1DX with Sol Services Ltd under CSO 16.02.Approved
  5. Extension and variation of Housing Related Support Contracts - Mental Health Pathway- Short Term Supported AccommodationApproved
  6. Extension and variation of single homeless pathway contractsApproved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies