CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Haringey
Cabinet, Tuesday 9 December 2025 at 6.30pm

Stamford Hill Primary School added to the New Homes Programme

Decided Executive 3 papers

AI summaryCabinet approved adding the former Stamford Hill Primary School site to Haringey's Housing Delivery Programme, allowing feasibility work towards 130 to 150 potential social rented homes. Any building remains subject to education consent, viability and planning permission [3.1] [6.2] [6.14] [6.7] [6.11].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedFeasibility will determine whether new council homes can be delivered [6.2]
MoneyNot stated
What happens nextFeasibility and preliminary studies [6.9]Education consent, valuation and appraisal come next [6.7] [P26]
Who it affectsCouncil homes and residents [4.6]People on waiting list and homelessness groups [4.6] [P58]

What was decided

Cabinet approved adding the former Stamford Hill Primary School site to the Council's Housing Delivery Programme [3.1]. Report 3.1

The Delivery Director can approve budgets before contract award. These cover all project costs up to a Gateway 3 construction contract award [3.2]. Report 3.2

There were no declarations of interest for this item [D].

Why

The school closed in 2020 and its children are now educated in other local schools, so the Council considers the site surplus [6.4] [6.14]. Report 6.4, 6.14

The programme targets 3,000 new homes by 2031 and more affordable homes for people on the waiting list [4.1] [4.6] [7.1]. Report 4.1, 4.6, 7.1

Initial assessment found the site potentially suitable and assessed capacity for 130 to 150 homes [6.8] [6.14]. Report 6.8, 6.14

What happens next

Secure Secretary of State for Education agreement to change the site's use from education to residential, then test viability and complete required legal consultations before any building decision [6.7] [P26]. Report 6.7, P26

Complete valuation, financial appraisal, design studies, site risk checks, legal searches, planning checks and environmental reports [P26]. Report P26

If the scheme is viable, consult the community and local stakeholders, seek planning permission, then return to Cabinet for approval of construction and the associated budget [6.10] [6.11]. Report 6.10, 6.11

Options considered

  • Chosen: Add the site to the Council's Housing Delivery Programme. It allows feasibility to be tested and supports the Council's new homes target [6.2] [7.1]. Report 6.2, 7.1
  • Rejected: Do not include the site in the Housing Delivery Programme. Exclusion would undermine the Council's capacity to deliver new council homes [5.1]. Report 5.1
  • Rejected: Dispose of the site to a private developer. A private developer disposal could reduce the number of affordable homes built by the Council [5.2]. Report 5.2

Implications

  • Financial: The Delivery Director can approve budgets before contract award. If no viable scheme emerges, the Council must bear any costs already incurred [3.2] [P47]. Report 3.2, P47
  • Financial: If the site proceeds, initial feasibility costs will form part of the overall delivery cost [P46]. Report P46
  • Legal: The site's change from education use requires Secretary of State consent. No building decision can be made until consent, viability and required legal consultations are complete [6.7] [P20] [P21] [P52]. Report 6.7, P20, P21, P52
  • Legal: The site must later be moved from the General Fund to the HRA. Cabinet approval will be needed for this transfer [P46]. Report P46
  • Equalities: The change is expected to have a positive impact on people in temporary accommodation and those vulnerable to homelessness. No negative equalities impact is expected [P58]. Report P58
  • Climate: The programme seeks Zero Carbon homes, sustainable materials, energy efficiency, heat pumps, solar panels, green spaces and wildlife improvements [8.1] [8.2]. Report 8.1, 8.2
  • Risk: Further site risk, legal and environmental checks are required. This approval does not guarantee progression beyond feasibility and capacity studies [P26] [P44]. Report P26, P44
  • Other: Planning policy requires existing social and community facilities to be protected unless a replacement meets community needs. Evidence is needed for any facility loss [6.13] [P31] [P32]. Report 6.13, P31, P32

Who and where

  • Households on Haringey's housing waiting list Report 4.6
  • People in temporary accommodation Report P58
  • People vulnerable to homelessness Report P58
  • Residents with protected characteristics Report P58
  • Existing residents who may benefit from community improvements Report 4.6
  • Future residents of new council homes Report 4.6
  • Users of any existing social or community facility Report 6.13
  • Potential residents needing bespoke housing adaptations Report 4.3, 4.6

Timeline

  • 1882: Former Stamford Hill Primary School was established [6.3]. Report 6.3
  • November 2018: An Ofsted inspection rated the school inadequate [6.3]. Report 6.3
  • 2020: Stamford Hill Primary School closed [6.4]. Report 6.4
  • After its closure: The site was temporarily used as a Covid testing centre [6.4]. Report 6.4
  • as of August 2025: 797 council homes had been completed under the housing programme [4.2]. Report 4.2
  • At a later stage: Cabinet approval will be sought to move the site from the General Fund to the HRA [P46]. Report P46
  • If planning permission is granted: Cabinet will be asked to approve the construction scheme and associated budget [6.11]. Report 6.11
  • 2031: The Council's target is 3,000 new council homes [4.1] [7.1]. Report 4.1, 7.1

Plain English for the jargon

  • Housing Delivery Programme: The Council programme for adding sites, testing feasibility and delivering new council homes [3.1] [6.2].
  • Gateway 3: The stage at which a construction contract is awarded [3.2].
  • General Fund: The Council fund currently holding the former school site [P15].
  • HRA: The fund to which the site would later be moved from the General Fund, subject to viability appraisal and Cabinet approval [P45] [P46].
  • Bespoke homes: Council homes co-designed with tenants with mobility or welfare needs, with features such as height adjustable worktops and specially designed bathrooms [4.3].
  • Local Planning Authority: The authority that must formally consult the community before deciding on planning permission [6.11].
  • Secretary of State consent: Approval required before specified school land disposal or transfer to another Council purpose [6.5] [P20] [P21] [P52].
  • Protected characteristics: Age, disability, gender reassignment, pregnancy or maternity, race, religion or faith, sex, sexual orientation, and marriage or civil partnership status for part of the duty [P54] [P55].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item359

Resolved

DECLARATIONS OF INTEREST FOR THIS ITEM: None
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet, 10 pages

Recommendations

It is recommended that Cabinet

3.1Approves the addition of the former Stamford Hill Primary School site to the Council’s Housing Delivery Programme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Red line boundary Stamford Hill Primary SchoolAppendix 1 1 pages Download
PDF
Stamford Hill School_Feasibility StudyAppendix 2 30 pages Download
PDF
Stamford Hill Primary School added to the New Homes ProgrammeMinutes 10 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 19 attended
TE
Taryn EvesCouncil Staff, expected
AO
Councillor Ajda OvatCommittee Member, present
PA
Councillor Peray AhmetChair, present
MH
Councillor Mike HakataCommittee Member, present
EA
Councillor Emily ArkellCommittee Member, present
ZB
Councillor Zena BrabazonCommittee Member, present
DC
Councillor Dana CarlinCommittee Member, present
SC
Councillor Seema ChandwaniCommittee Member, present
LD
Councillor Lucia das NevesCommittee Member, present
RG
Councillor Ruth GordonCommittee Member, present
SW
Councillor Sarah WilliamsCommittee Member, apologies
AD
Andy DonaldOfficer, expected

All 19 on the meeting page

On this subject at Haringey

Search all
  1. Stamford Hill Primary School added to the New Homes ProgrammeThis decision
  2. The future of Stamford Hill Primary SchoolNoted
  3. Options for the future of Stamford Hill Primary SchoolNoted
  4. Results of the non-statutory consultation on the options for the future of Stamford Hill Primary School and its possible amalgamation with Tiverton Primary SchoolAgreed
  5. Options for the future of Stamford Hill Primary SchoolAgreed
  6. Stamford Hill Primary School, Berkeley Road, N15 6HDApproved

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies