Coleridge Primary School - Condition Works - Permission to initiate tender action for a Construction Works Contract

Decided Executive 1 paper

AI summaryHaringey's Cabinet Member for Children, Education and Families approved starting a tender for roof covering and related condition works at Coleridge Primary School's west site. Contracts worth £500,000 and above need Cabinet approval to start tendering. [3.1] [3.2] [6.11] [9.2.3]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCondition works at Coleridge Primary School's west site. [3.2]
Money£500,000Approval threshold for commencing procurement. [9.2.3] [9.3.2]
What happens nextTender, then seek award approvalA further report will request award approval. [6.12]
Who it affectsPupils, staff and visitorsThe work aims to improve safety and wellbeing. [4.2]

What was decided

The Cabinet Member approved commencing a tender for a construction works contractor to deliver condition works at Coleridge Primary School's west site. Report 3.1, 3.2

The tender is based on feasibility Option 2: replace only the roof covering, not the whole roof and structure. Report 6.8, 6.11

Why

The school has an historical shortfall of investment. Moisture can weaken the wood wool roof structure and cause it to lose structural integrity. Report 4.1

Leaks compromise the building and may cause mould and respiratory problems. Replacing the roof is needed for safety, wellbeing and a suitable learning environment. Report 4.2

The feasibility study found the roof panels in good condition. A covering only approach was less disruptive and significantly less costly, while the roof could not safely carry solar PV panels. Report P20, 6.8, 6.11

What happens next

Commence the tender for a construction works contractor to deliver the west site condition works. Report 3.2

Strategic Procurement will procure through the London Construction Programme and work with the service to achieve value for money and deliver social value aligned with council priorities.

Prepare a further report after tendering to seek approval to award the contract to the successful bidder. Report 6.12

The money

  • £500,000 Contract value threshold requiring Cabinet approval before tendering begins

Options considered

  • Chosen: Use the London Construction Programme. Market engagement received positive feedback on supplier interest and availability. The proposed contract is a single stage, JCT traditional form and the route was considered suitable. Report 4.2, 5.5
  • Chosen: Replace only the roof covering under feasibility Option 2. The feasibility study recommended it because the roof panels were reported in good condition. Replacing the whole roof and structure was unnecessary, disruptive and significantly more costly. Report P20, 6.8, 6.11
  • Rejected: Replace isolated wood wool slabs to achieve compliance and health and safety under Option 1. This would address isolated deterioration, but the feasibility study recommended Option 2 instead. Report P19, 6.8
  • Rejected: Deliver both feasibility options and add solar PV cells under Option 3. The roof could not safely support the added load of PV panels. Report P21, 6.8
  • Rejected: Do nothing and continue repairing the leaking roof. Repeated repairs were considered unlikely to resolve the underlying issues and could cause recurring leaks, further damage and escalating repair costs. Report 5.1
  • Rejected: Deliver the service in house. The council had no resource with the capacity, specialist expertise or qualifications to deliver the service. Report 5.3
  • Rejected: Invite open tenders through Contracts Finder. This would create a protracted tender period and delay delivery. Report 5.4
  • Rejected: Use an alternative public sector DPS. This would not comply with CSO 8.02 because the London Construction Programme or DPS was considered suitable. Report 5.5

Implications

  • Risk: The leaking roof compromises structural integrity and creates mould and respiratory risks. Report 4.2
  • Financial: The project is expected to reduce reactive maintenance and avoid additional temporary repair costs. Report 8.2
  • Financial: Roof insulation is expected to reduce energy consumption and utility costs. Report 8.3
  • Climate: Energy efficient measures, including roof insulation, are expected to deliver approx. 20.99 tCO2pa carbon reduction. Report 8.2
  • Legal: Consultations confirmed that neither planning nor building control approval is required. Report 6.10
  • Legal: The reserved decision requires the Cabinet Member to act with the Leader's agreement under CSO 0.08.
  • Equalities: Contract management should prevent preventable or disproportionate inequality. Improved health and safety is expected for the school and its visitors.
  • Other: The scope includes replacement of circa 1670m2 of flat roof covering, drainage, roof lights, glazing, insulation, enabling services, timber and brickwork repairs. Covering only works should cause less disruption than full replacement. Report P16, 6.11

Who and where

  • Pupils, staff and visitors at Coleridge Primary School Report 4.2
  • People sharing protected characteristics
  • People across socioeconomic statuses Report 9.4
  • Users of the school kitchen, dining hall and assembly hall Report 6.2, P16
  • Strategic Procurement and the relevant council service
  • Potential construction contractors Report 3.2

Timeline

  • September 2020: A business case and programme delivery plan were submitted to the Capital Board, with approval granted for urgent projects before a final decision. Report 6.3
  • 17th October 2024: The building surveyor led, multi disciplinary design team appointment was approved under delegated powers. Report 6.6
  • March 2025: The quantity surveying services award was approved under delegated powers. Report 6.6
  • During RIBA 1: The multi disciplinary design team took on quantity surveying duties as a variation. Report 6.6
  • 2025-12-18: Cabinet Member Signing meeting on the tender approval.
  • Upon completion of the tender exercise: A further report will seek approval to award the construction works contract to the successful bidder. Report 6.12

Plain English for the jargon

  • Contract Standing Order: The council's procurement rules used for approval and value for money. [3.1] [9.2.3]
  • London Construction Programme: The programme Strategic Procurement will use to procure the contract. [9.2.2]
  • MDDT: A multi disciplinary design team appointed to develop the project. [6.6]
  • PSED: Public Sector Equality Duty under the Equalities Act (2010). [9.4.1] [P50]
  • DPS: A public sector procurement route considered suitable for the requirements. [5.5]
  • PV: Solar PV cells considered for the school roof. [P21] [6.8]
  • RIBA 1: The stage at which the design team undertook quantity surveying duties as a variation. [6.6]
  • JCT traditional: The proposed form for the construction works contract. [4.2]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

DECLARATIONS OF INTEREST FOR THIS ITEM: None
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing, 6 pages

Recommendations

3.1For the Cabinet Member for Children, Education and families, pursuant to Contract Standing Orders 0.08 and 2.01(b) to:

3.2Approve the commencement of a tendering process for a construction works contractor to deliver condition works on the west site at Coleridge Primary School.

Reasons for decision

4.1The school has suffered from an historical shortfall of investment and subsequently the roof covering of the building has deteriorated. The structure of the roof is predominantly constructed with wood wool, a deleterious material, which can lose its structural integrity if it becomes wet. Therefore, it is essential to engage a construction works delivery contractor to undertake the roof works.

4.2Replacing the leaking roof at the school is essential to ensure the safety and well-being of students, staff, and visitors. A roof constructed with wood wool, while initially cost- effective and environmentally friendly, can deteriorate over time, especially when exposed to moisture. The current leaks not only compromise the structural integrity of the building but also pose significant health risks, such as mould growth and potential respiratory issues. Additionally, a well-maintained roof is crucial for preserving the school's infrastructure, preventing further damage, and ensuring a conducive learning environment. Investing in a new roof will ultimately save on long-term repair costs and demonstrate the council's commitment to providing a safe and supportive educational setting. 4.3 It is proposed to procure a contractor on a single-stage, JCT traditional form of contract using the London Construction Programme Education Framework or DPS. Soft market engagement has been undertaken to ascertain interest and availability within the market, with positive feedback of the proposed approach.

5. Alternative options considered.

5.1Do nothing - The council could decide not to tender the scheme and continue repairing the leaking roof instead. This may seem cost-effective in the short term, but it is not a sustainable solution. The ongoing repairs are unlikely to fully resolve the underlying issues, especially given the roof's construction with wood wool, which is prone to deterioration when exposed to moisture. This approach risks recurring leaks and further damage, leading to escalating repair costs over time. Ultimately, the repeated repairs may prove to be more expensive than investing in a comprehensive roof replacement. By not addressing the root cause, the council is potentially compromising the safety and integrity of the building, which could have more serious financial and operational implications in the future.

5.3In-house – There is currently no resource within the Council that has the capacity, specialist expertise or qualifications to deliver this service.

5.4Invite open tenders via Contracts Finder. This would result in a protracted tender period and would delay delivery of the project.

5.5Use an alternative public sector DPS. This would not be compliant with CSO 8.02, given the LCP Framework or DPS has been deemed suitable for the requirements being sought.

6. Background information

6.1Coleridge Primary School occupies a split site, either side of the A103. This project concerns the west site on Crouch End Hill, bounded by Crescent Road to the south and residential properties to the rear.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Coleridge Primary School: Condition Works: Permission to initiate tender action for a Construction Works ContractMinutes 6 pages DownloadRead as text

At this meeting

Whole meeting
6Coleridge Primary School - Condition Works - Permission to initiate tender action for a Construction Works ContractThis decision
7Exclusion of the Press and PublicOn the agenda 8EXEMPT Coleridge Primary School - Condition Works - Permission to initiate tender action for a Construction Works ContractPrivate

Who was there

1 of 1 attended
ZB
Councillor Zena BrabazonCommittee Member, present, as expected, virtual

On this subject at Haringey

Search all
  1. Coleridge Primary School - Condition Works - Permission to initiate tender action for a Construction Works ContractThis decision
  2. Coleridge Primary School & Former TUC Centre Site Crouch End Hill N8 ~ Conservation Area ConsentDecided
  3. Coleridge Primary School, Crescent Road N8.Approved
  4. The Enlargement of Coleridge Primary SchoolAgreed

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies