AI summaryHaringey Cabinet Member recommended to appoint Contractor A to build 2 new council homes at Dawlish and Scales Road, Tottenham, using Section 203 powers to override third-party rights.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedMost Economically Advantageous Tender, scored 92.2
MoneynullContract sum in exempt Appendix 1; within existing budget
What happens nextIssue letter of intentPending formal JCT Design and Build 2016 Contract execution
Who it affectsCouncil tenants and homeless householdsTwo new social rent homes, one wheelchair adaptable

What was decided

Approve the appointment of Contractor A to enter into a JCT Design and Build 2016 Contract with Haringey's amendments. Report 3.1

Approve use of Section 203 of the Housing and Planning Act 2016 to override easements and other third-party rights affected by the development, and delegate to the Delivery Director authority to pay compensation on genuine third-party claims. Report 3.2, 3.3

Approve entering the contract at the sum in the Exempt Report, issuance of a letter of intent under CSO 16.04, and associated contingencies and on costs. Report 3.4, 3.5, 3.6

Why

The site was approved by Cabinet on 21st January 2020 for inclusion in the Housing Delivery programme, and planning permission for 2 new houses was granted in March 2023 under reference HGY/2022/2000. Report 4.1, 4.2

The homes will contribute to the Council's commitment to have built 3,000 new high-quality council homes by 2031. Report 4.3

Three tender bids were evaluated on 60% quality, 30% price and 10% social value. Contractor A scored 92.2 against 75.5 and 79.5, and the Employers Agent judged its bid the Most Economically Advantageous Tender. Report 8.1, 8.2, 8.3

What happens next

Issue a letter of intent under CSO 16.04 so works can commence before the formal contract is executed. Report 3.5, P56

Terminate the two garage leases on the Dawlish Road site and return the land to the Council for development. Report 6.2

Enter into the JCT Design and Build 2016 Contract at the exempt contract sum, with Contractor A obliged to have due regard to the Public Sector Equality Duty. Report 3.1, P50

Options considered

  • Rejected: Do not develop the site for housing. Would not support the Council's commitment to deliver a new generation of Council homes. Report 5.1
  • Rejected: Procure via a restricted tender, open-market competitive tender, or alternative procurement route. Not recommended by Strategic Procurement Team as providing the best value; the London Construction Programme Dynamic Purchasing System was used instead. Report 5.2, 11.2, P41
  • Chosen: Award to Contractor A via the LCP General Construction Multi Trade DPS. Procurement route compliant with CSO 8.01; Contractor A scored highest and represents value for money. Report 8.3, P40, P41, P42

Implications

  • Financial: Recent cost projections in the new build capital programme suggest the scheme can be accommodated within the existing budget and Medium Term Financial Strategy; further finance detail is in the Exempt Report. Report P37, P38
  • Legal: Contract award is compliant with CSO 2.01(c) and CSO 8.01, with Section 203 powers used to override easements. The Director of Legal and Governance confirms no legal reasons prevent approval. Report P53, P54, P55, P57
  • Equalities: Decision is likely to positively impact women, people over 65, households with young children, trans and LGBT+ individuals overrepresented in Council tenancies and homelessness. Contractor A must have due regard to the Public Sector Equality Duty. Report P44, P48, P49, P50
  • Climate: The scheme is designed to achieve a 101% reduction in emissions from Building Regulations Part L (2013), with air source heat pumps, photovoltaic panels, and a car-free layout, supporting the HCCAP 2041 target and the Government's 2030 net zero target. Report 10.2, 10.4, 10.5, 10.6
  • Risk: Two garage leases on the Dawlish Road site will be terminated, and Section 203 powers may be invoked if easements or other third-party rights are infringed; compensation on genuine claims is delegated to the Delivery Director. Report 3.2, 3.3, 6.2

Who and where

  • Council tenants and residents in temporary accommodation or needing to move to a new home Report P47, P48
  • Two garage leaseholders on the Dawlish Road site, whose leases will be terminated Report 6.2
  • Women, young people, BAME communities, LGBT+ individuals, and people with disabilities overrepresented in homelessness Report P48, P49

Timeline

  • 21st January 2020: Cabinet approved Dawlish and Scales Road site for inclusion in the Housing Delivery programme. Report 4.1
  • 21/03/22, 18/03/22: Consultation period as stated in the report (dates as given). Report P19
  • March 2023: Planning permission granted for 2 new houses under reference HGY/2022/2000. Report 4.2
  • April 2025: Council published invitation to tender. Report 8.1
  • 2026-02-09: Cabinet Member Signing decision date.
  • 2031: Council target of 3,000 new high-quality council homes built. Report 4.3
  • 2041: Haringey Climate Change Action Plan target supported by the scheme. Report 10.1

Plain English for the jargon

  • JCT Design and Build 2016: A standard UK construction contract published by the Joint Contracts Tribunal, under which the contractor designs and builds the project.
  • LCP Dynamic Purchasing System (DPS): London Construction Programme's pre-qualified supplier list used to procure public sector construction works.
  • PTAL: Public Transport Accessibility Rating, scored 1 to 6, where higher means better access; the site scores 5.
  • HRA: Housing Revenue Account, the ring-fenced account councils use for income and spending on council housing.
  • Section 203: Power under the Housing and Planning Act 2016 to override easements and other third-party rights to enable development.
  • HCCAP: Haringey Climate Change Action Plan, with a 2041 emissions target.
  • PSED: Public Sector Equality Duty under the Equality Act 2010.
  • CSO: Council's Contract Standing Orders, the rules governing procurement and contracts.
  • MTFS: Medium Term Financial Strategy, the Council's multi-year budget plan.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Recommendations

It is recommended that the Cabinet Member for Housing and Planning:

3.1Approve pursuant to Council’s Standing Orders (CSO) 2.01.1C in line with CSO Statement of Principles 0.08 the appointment of Contractor A, identified in the exempt part of the report to enter into a JCT Design and Build 2016 Contract with Haringey’s amendments. (See Appendix 1)

3.2Approve the use of the Council’s powers under Section 203 of the Housing and Planning Act 2016 to override easements and other third-party rights and interests infringed upon by the Dawlish and Scales Roads development.

3.3Delegate to the Delivery Director, after consultation with the Director of Finance & Resources and the Cabinet Member for Housing & Planning, authority to make payments of compensation of genuine claims of third-party rights affected by the Dawlish and Scales Roads development and payable under the approval in section 3.2, within the existing scheme of delegation.

3.4Approve entering the contract at the contract sum set out in the Dawlish and Scales Roads Exempt Report (Appendix 1).

3.5Approve pursuant to CSO 16.04 the issuance of a letter of intent as set out in the Dawlish and Scales Roads Exempt Report.

3.6Approve the contingencies and on costs associated with the delivery of the scheme

Reasons for the decision

4.1The site known as Dawlish and Scales Roads was approved by Cabinet on 21st January 2020 to be included in the Council’s Housing Delivery programme.

4.2Planning permission was granted in March 2023 for 2 new houses under planning reference HGY/2022/2000.

4.3These Council homes will contribute to the Councils commitment to have built 3,000 new high-quality council homes by 2031.

Alternative options considered

5.1Not to develop this site for housing purposes however this option was rejected as it does not support the Council’s commitment to deliver a new generation of Council homes.

5.2This build contract was procured via the approved London Construction Programme (LCP) Dynamic Purchasing System as recommended by the Strategic Procurement team. The alternative option would have been to procure a contractor via a restricted tender, a competitive tender on the open market, or an alternative procurement route. These options were not recommended by the Strategic Procurement Team as providing the best value.

6. Site information

The two sites are located to the east of High Road, Tottenham on the corner of Scales Road and Dawlish Road.

6.1The site on the corner of Scales Road is vacant and adjacent to an electricity sub-station.

6.2The site on the corner of Dawlish Road has three single storey council-owned garages. Two garages are leased, and one is vacant. If approved, the leases will be terminated and returned to the Council for development. 6.3. The transport and connectivity of the site is rated as ‘Good’ with a Public Transport Accessibility Rating (PTAL) of 5.

6.4The land is Council-owned and held in the Housing Revenue Account (HRA).

7. Engagement and Consultation

The consultation period was 21/03/22 – 18/03/22. (See Appendix 3 – Community Engagement information)

8. Proposed Build Contract

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Dawlish & Scales RoadMinutes 295 KB DownloadRead as text
PDF
Dawlish & Scales Roads Community Engagement & Public Consultation Appendix 3Minutes 658 KB Download
PDF
Dawlish & Scales Roads Public Consultation Boards Appendix 3Minutes 2.5 MB Download

At this meeting

Whole meeting

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies