Approve acceptance of Family Hubs and Start for Life grant funding and award the contracts to various organisations necessary to deliver the Family Hub programme as set out in the delivery plan.

Decided Executive 1 paper

AI summaryHaringey Cabinet Member approves £4,692,300 Family Hubs grant and awards three contracts to continue the Best Start Family Hubs Programme for three more years.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedPIPS, Baby's Sake and Wards Corner contracts approved
MoneyNot stated
What happens nextContracts start 1 April and 1 May 2026PIPS from 1 May 2026, others from 1 April 2026
Who it affectsHaringey families with children aged 0 to 19Plus pregnant women, new parents and Latin American families

What was decided

The Cabinet Member accepted £4,692,300 in external funding from the Department for Education and the Department of Health and Social Care to continue the Family Hubs Programme for three years. Report 3.1, P2, P43

A contract was awarded to Whittington Health NHS Trust for the Parent Infant Psychology Service for two years from 1 May 2026 to 30 April 2028, using Direct Award Process C under the Provider Selection Regime. Report P2, P18, P19, P55

Contracts were awarded to Baby's Sake and Wards Corner, with a waiver of the three-quotation requirement under Contract Standing Order 12.02, for three years from 1 April 2026 to 31 March 2029. Report P3

Why

The Council needs to continue delivering the Best Start Family Hubs Programme in areas with the highest deprivation, while meeting grant conditions and avoiding loss of funding. Report 4.1, 4.3, 5.1, 5.2

A competitive tender was ruled out due to limited time, the short funding window and the need for specialist clinical and culturally specific provision. Report 5.3

Using the existing providers avoids mobilisation delays, protects the Council from clawback of grant money and ensures uninterrupted services for vulnerable families. Report 4.2, 5.4, 6.7

What happens next

Contracts will begin between 1 April and 1 May 2026 and run for two or three years depending on the provider. Report P2, P3

Performance will be tracked through contract monitoring meetings, site visits and reports, with a Family Hub performance monitoring framework in place. Report 6.8, P32, P33

The Family Hub Project Manager will ensure processes are in place to meet grant agreement obligations and reduce the risk of having to repay funding. Report P50

The money

  • £4,692,300 Total grant from DfE and DHSC over three years Report 3.1, P2, P43
  • approx. £1.5m Grant allocation to 2026-2027 Report 6.2, P43
  • £550,620 Maximum cost of PIPS contract to Whittington Health NHS Trust for two years Report P2, P55
  • £552,548 PIPS contract value cited in finance comment for two years Report P44
  • £105,000 Three-year contract with Baby's Sake for therapeutic interventions Report P3, P44
  • £27,595 Three-year contract with Wards Corner for Latin American Stay and Play Report P3, P44

Options considered

  • Rejected: Do not accept the grant. Would lose the opportunity to continue the Family Hubs Programme and breach a key partnership objective Report 5.1
  • Rejected: Do not award the contracts. Would breach grant conditions and risk clawback of funding and non-delivery of services Report 5.2
  • Rejected: Run a competitive quotation process. Limited time, short funding window and specialist clinical and cultural requirements make this unviable Report 5.3
  • Rejected: Use Most Suitable Provider Process (PIPS) under PSR. Risk of provider challenge in a small local market Report 5.4

Implications

  • Financial: No impact on the Council's General Fund: all contract costs are met from the Best Start Family Hubs grant. Report P45
  • Financial: Changing providers now could delay mobilisation and put the grant at risk of reduction or withdrawal. Report P50
  • Legal: PIPS award uses Direct Award Process C under the Health Care Services (Provider Selection Regime) Regulations 2023 and is permitted under CSO 10.01. Report P2, P18, P19, P55
  • Legal: The waiver of competitive quotation requirements for Baby's Sake and Wards Corner is permitted under CSO 18.01.2(d)(iii). Report P3
  • Equalities: Decision expected to have a positive impact on pregnant women, new parents and young children; no disproportionate negative impact on protected groups identified. Report P62, P63
  • Other: The PIPS contract exceeds £500,000 so use of the Social Value Portal is required; the provider's social value commitments will apply.
  • Staffing: The service is linked to existing NHS core structures, referral pathways and management frameworks for cost-effective delivery. Report P25

Who and where

  • Families with children aged 0 to 19 across Haringey Report 6.1, P14
  • Pregnant women, new mothers and infants needing mental health and parenting support Report P17
  • Latin American families in the borough using Stay and Play sessions Report 6.5
  • Family Hub staff receiving training and group session support Report P17
  • Whittington Health NHS Trust, Baby's Sake and Wards Corner as contracted providers Report P2, P3

Timeline

  • 1 April 2026: Baby's Sake and Wards Corner contracts begin (run to 31 March 2029) Report P3
  • 1 May 2026: PIPS contract with Whittington Health NHS Trust begins Report P2, P55
  • 2026-2027: Approximately £1.5m of the grant is allocated Report 6.2, P43
  • 30 April 2028: PIPS contract ends Report P2, P55
  • 31 March 2029: Baby's Sake and Wards Corner contracts end Report P3

Plain English for the jargon

  • Best Start Family Hubs: Haringey programme delivering multi-agency services for children aged 0 to 19 and their families.
  • PIPS: Parent Infant Psychology Service, providing one-to-one and group work with families and infants plus training for Family Hub staff.
  • PSR: Health Care Services (Provider Selection Regime) Regulations 2023, the rules for procuring health care services.
  • Direct Award Process C: A PSR route allowing award to an incumbent provider where performance is satisfactory and there is no material change.
  • CSO: Council Contract Standing Orders, the internal rules governing procurement and contracts.
  • DfE and DHSC: Department for Education and Department of Health and Social Care, the grant funders.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

DECLARATIONS OF INTEREST FOR THIS ITEM: None
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Recommendations

3.1For the Cabinet Member for Children, Schools and Families to: 3.1.1. in accordance with CSO 21.01 to grant permission to accept £4,692,300 external funding from Department of Education (DfE) and the Department of Health and Social Care (DHSC) over the next three years, to continue the Family Hubs Programme;

3.1.2. Approve the award of contract to Whittington Health NHS Trust for the provision of Parent Infant Psychology Service, for a period of 2 year from 1st May 2026 to 30th April 2028 at a total maximum cost of £550,620 under the Health Care Services (Provider Selection Regime) Regulations 2023 (“PSR”) Direct Award Process C and

3.1.3. Approve the waiver of Contract Standing Order (CSO) 12.02 (requirement to obtain three competitive quotations) as permitted under CSO 18.01.2(d) (iii) (where the value of the contract is below the applicable threshold pursuant to the Procurement Act 2023 and it is in the Council’s overall interest to waive the requirement); and award contracts to:  Baby’s Sake, for the provision of therapeutic interventions supporting parents and babies, at a cost of £105,000 for a period of 3 years from 1 April 2026 to 31 March 2029; and  Wards Corner, for the delivery of Latin American Stay and Play sessions, at a cost of £27,595 for a period of 3 year, from 1 April 2026 to 31 March 2029.

Reasons for decision

4.1The Best Start Family Hubs programme’s core aim is to improve family services including Healthy Babies services, particularly in areas with the highest levels of deprivation and disproportionately poor health and educational outcomes. Accepting this external funding will enable the Council to continue with our commitment to successfully deliver the Best Start Family Hubs Programme over the next 3 years. This Programme is needs led, responds to resident demand and provides multi agency services that are accessible locally.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approve acceptance of Family Hubs and Start for Life grant funding and award the contracts to various organisations necessary to deliver the Family Hub programme as set out in the delivery plan.Minutes 360 KB DownloadRead as text

At this meeting

Whole meeting
1FILMING AT MEETINGSNoted
6Approve acceptance of Family Hubs and Start for Life grant funding and award the contracts to various organisations necessary to deliver the Family Hub programme as set out in the delivery plan.This decision

Who was there

1 of 1 attended
ZB
Councillor Zena BrabazonCommittee Member, present

On this subject at Haringey

Search all
  1. Approve acceptance of Family Hubs and Start for Life grant funding and award the contracts to various organisations necessary to deliver the Family Hub programme as set out in the delivery plan.This decision
  2. To approve acceptance of Local Electric Vehicle Infrastructure fundingApproved

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open