Cabinet Member Signing, Monday 9 March 2026 at 3.00pm

Hostels - Major Works Programme

Decided Executive 1 paper

AI summaryHaringey's Cabinet Member for Housing approves a £3,600,817.13 contract to refurbish four Muswell Hill hostels, with works starting April 2026 and finishing August 2027.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedHighest tender score of 97.75%, named in exempt Appendix A
Money£3,600,817.13 contract, plus £360,000 letter of intentFunded from HRA Capital Programme, split across two financial years
What happens nextContractor mobilises from March/April 2026Handover targeted March 2027, final sign-off August 2027
Who it affectsNot stated

What was decided

The Cabinet Member for Housing and Planning approved award of a 12-month contract to Tenderer A for £3,600,817.13, covering refurbishment of four Muswell Hill hostels. Report 3.1, 3.2

A letter of intent for £360,000.00 was approved under Contract Standing Order 16.04, allowing the contractor to place supply chain orders before formal contract. Report 3.3, P84

Expenditure of sums set out in the exempt Appendix A was approved, with spend profiled across 2026/27 and 2027/28. Report 3.2, 8.1, P51

Why

Tenderer A submitted the Most Advantageous Tender, scoring 97.75% on price, quality and social value, against five compliant bids. Report 4.1, 7.2, P46

The hostels are mostly vacant and need upgrading to bring them back into use and maximise income; postponing until a partnering contractor was appointed was rejected. Report P6, 6.5, 6.6

The project supports the Housing Asset Management Strategy, the Decent Homes Standard by 2028, the borough's net zero target by 2041, and Building Safety and Social Housing Regulation Act requirements. Report 9.1, P65, 9.3, P68, P69

What happens next

Strategic Procurement will issue the formal contract and letter of intent, with mobilisation in March/April 2026 and phased decant of the least-occupied hostels first. Report 7.1, P54, 8.7

Planning applications for the conservation-area works have been submitted and are within an 8 to 16 week determination period; early engagement with Planning and Conservation Officers is underway. Report P54, 8.9, 8.10

Resident engagement will continue throughout delivery, with a dedicated quality inspector on site daily and ongoing cost monitoring by the lead consultant. Report 6.8, 8.5, 8.6

The money

  • £3,600,817.13 Contract sum awarded to Tenderer A for hostel major works Report 3.1, 7.3, P46
  • £360,000.00 Letter of intent under CSO 16.04 to let contractor place supply chain orders Report 3.3, P84
  • £3,510,796.68 Main works spend profiled in 2026/27 Report P51
  • £90,020.45 Retention and end of defects spend profiled in 2027/28 Report P51
  • £3,600,817.13 Total project cost shown in spend profile table Report P51

Options considered

  • Chosen: Award contract to Tenderer A at £3,600,817.13. Highest overall score of 97.75%, offering optimal balance of price and quality, with strongest social value and quality scores among the five compliant bidders. Report 4.1, 3.1, P46
  • Rejected: Postpone works until Partnering Contractors are appointed. Most rooms are already vacant pending refurbishment; waiting would delay bringing the hostels back into use and the income they generate. Report P6

Implications

  • Financial: Spend is funded from the Hostel Major Works Programme Budget within Asset Management's HRA Capital Programme and profiled across 2026/27 and 2027/28, with a contingency for unforeseen works and professional fees built in. Report 8.1, P51, 11.2, P78
  • Legal: Procurement was run via the LCP MW24-H Housing Framework, Lot 2.3, and the Director of Legal and Governance confirms no legal reasons preventing approval; the award is treated as a Key Decision under CSO 2.01(c). Report 11.3, P80, P81, P82, P83
  • Equalities: Decision expected to have a positive equalities impact, lifting housing quality for residents of council homes, including groups overrepresented in the stock such as BAME and disabled residents; works will be adapted where residents have disabilities. Report 12.3, 12.4, 12.5
  • Climate: Decarbonisation works include air source heat pumps, solar panels where feasible, loft insulation, and window and ventilation upgrades; average EPC rating is expected to improve from D-E to C, supporting the borough's 2041 net zero target. Report P25, 9.1, 10.1
  • Risk: Key risks include unforeseen structural defects, conservation-area planning delays, and contractor capacity, mitigated by early planning engagement, daily site inspections, and a phased decant starting with the least-occupied hostels. Report 8.4, 8.7, 8.9, 8.10, P60
  • Other: The project includes fire safety upgrades to meet current standards, such as fire-rated entrance doors, improved compartmentation in roof voids and between units, and compliant fixtures and fittings. Report P26

Who and where

  • Residents currently living in the four Muswell Hill hostel properties, some of whom will be temporarily decanted Report 6.8, 8.7
  • Future hostel residents once the properties are brought back into use, including any reconfigured self-contained units Report 6.4, P28
  • Council tenants and leaseholders in the wider Haringey housing stock, as the scheme links to the borough-wide Decent Homes and net zero programmes Report 9.1, P65, P69

Timeline

  • March 2025: Initial engagement on the hostel refurbishment project Report P54
  • April 2025: Feasibility and options appraisal underway Report P54
  • May 2025: Design proposals stage Report P54
  • 22 August 2025: Invitation to tender published by Strategic Procurement Report P42
  • 24 September 2025: Five compliant bids received Report P42
  • October 2025: Planning application submitted for the works Report P54
  • February / March 2026: Governance and approval to award Report P54
  • March/April 2026: Appointment of contractor and mobilisation Report P54
  • March 2027: Indicative handover of the hostels Report P54
  • August 2027: End of defects period and final sign-off Report P54

Plain English for the jargon

  • HRA Capital Programme: The Housing Revenue Account capital programme, which funds investment in council housing stock from rental income rather than general council tax.
  • Decent Homes Standard: A government standard setting minimum conditions for social housing, which the Council aims to meet across its stock by 2028.
  • EPC: Energy Performance Certificate, a rating from A (best) to G (worst) showing how energy efficient a building is.
  • LCP MW24-H Housing Framework: London Construction Programme's MW24-H Housing Framework, a pre-approved list used by the Council to procure housing refurbishment contractors, used here under Lot 2.3 (Multi-use Housing).
  • Article 4 Direction: A planning tool that removes permitted development rights in a defined area, often used to protect conservation areas.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

DECLARATIONS OF INTEREST RELATED TO THIS ITEM: None
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Recommendations

It is recommended that the Cabinet Member for Housing and Planning (Deputy Leader):

3.1Pursuant to Contract Standing Order (CSO) 2.01.c approves the award of contract to Tenderer A in the sum of £3,600,817.13. Details of Tenderer A is set out in Appendix A - Exempt Report. The Contract will be for a period of 12 months commencing April 2026 and concluding March 2027. It is expected that financial completion of the scheme will complete August 2027.

3.2Approves the expenditure of sums as set out in Appendix A – Exempt Report.

3.3In line with Contract Standing Orders (CSO 16.04), approves issuance of a letter of intent for the value of £360,000.00. The Letter of Intent will allow the contractor to commence the project by placing orders with their supply chain before agreeing a formal contract.

Reasons for decision

4.1Tenderer A submitted the Most Advantageous Tender, offering the optimal balance of price and quality. The bidder achieved a score of 97.75% out of 100%, securing the highest overall ranking.

Alternative options considered

Page 1 of 8 5.1 Asset Management considered postponing the works until the Partnering Contractors had been appointed. However, given that most rooms within the hostels are currently vacant pending refurbishment, and in light of the urgent need to upgrade these properties so the Council can maximise income generation, it was concluded that a standalone procurement route was required. This approach will allow the hostels to be brought back into use without further delay.

6. Background information

6.1The hostel refurbishment project comprises four properties situated at 9, 32, and 39 Queens Avenue N10, and 19 Princes Avenue N10. Although the properties are not listed in terms of their special architectural or historic interest, they are located in the Muswell Hill Conservation Area. The table below outlines the number of units per property.

Hostels – Major Works Programme

Address Number of Units Storey Height

9 Queens Avenue 12 4

32 Queens Avenue 8 3

39 Queens Avenue 12 4

19 Princes Avenue 10 4

6.2In 2025, the Council appointed a multi‑disciplinary consultant to carry out a feasibility study and condition surveys for these properties, with the aim of identifying the scope of works required to bring them back into use.

6.3The multi‑disciplinary consultant identified a comprehensive package of refurbishment works required across all four hostel properties.

Key elements of the scope are as follows:

• Structural repairs to address underlying defects and ensure the long‑term stability of the buildings.

• Replacement of roof coverings to improve weatherproofing and extend the lifespan of the structures.

• External fabric repairs to masonry and brickwork, including repointing, crack repairs, and treatment of areas affected by damp or structural movement, to restore appearance and prevent further deterioration.

• Refurbishment of communal spaces to improve safety and accessibility. Works will include redecoration, lighting upgrades, flooring replacement, and handrail repairs. Stairwells will also be assessed and upgraded as required to meet fire safety and accessibility standards.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Hostels: Major Works ProgrammeMinutes 471 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 1 attended
SW
Councillor Sarah WilliamsCommittee Member, present

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies