Cabinet Member Signing, Monday 16 March 2026 at 12.30pm

Hamilton Close Major Works Programme

Approved Executive 1 paper

AI summaryHaringey awards £1.9m contract for major works to seven blocks on Hamilton Close estate, with a £191,000 letter of intent to allow early supply chain orders.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedMajor works programme for seven timber-framed blocks
Money£1,909,942.00 plus £190,994.00 letter of intentFunded from HRA Capital Budget across 2025/26 to 2027/28
What happens nextContractor appointment and mobilisationApril/May 2026, with handover in April 2027
Who it affectsHamilton Close estate residents and leaseholdersSeven blocks, including 45 leasehold properties

What was decided

The Cabinet Member for Housing and Planning approved the award of a contract to Tenderer A for £1,909,942.00, alongside related expenditure set out in the Exempt Report. Report 3.1, P3

A letter of intent for £190,994.00 was approved so the contractor can place supply chain orders before a formal contract is signed. Report 3.3

The award follows a competitive tender through Lot 2.3 of the London Construction Programme, which received eight compliant bids. Report 6.6, 6.7, P101

Why

Surveys in 2024 found deterioration to the timber-framed entrances and identified a fire-stopping breach at the interface with the external cladding, requiring replacement of the main entrances and the u-PVC cladding. Report 4.4, 4.5, 4.6

The works will deliver fire safety compliance, energy efficiency upgrades, and protect the Council's housing stock from further deterioration, supporting the Council's net-zero by 2041 target. Report 4.9, 4.10, 4.11, P20

Officers considered a 'do nothing' option and a longer-term partnering contract route, but both were ruled out due to the urgency of fire safety and disrepair risks. Report 5.1, 5.3, 5.4, 5.5

What happens next

The contractor is expected to be appointed and mobilised in April or May 2026, with handover in April 2027 and end of defects in March 2028. Report P77

Leaseholders will be invoiced via their service charge accounts in line with the Section 20 consultation process already completed. Report 4.16, 4.17, P32, P33, P34

Resident Liaison Officers will continue to engage residents, who can choose colours for communal decorations and flooring. Report 4.13, P24

The money

  • £1,909,942.00 Contract sum awarded to Tenderer A Report 3.1, P63
  • £190,994.00 Letter of intent to enable early supply chain orders Report 3.3
  • £100,000.00 Main works spend in financial year 25/26 Report P74
  • £1,762,194.00 Main works spend in financial year 26/27 Report P74
  • £47,748.00 End of defects spend in financial year 27/28 Report P74
  • £310,780.00 Estimated total to be recovered from leaseholders for the works Report P35
  • £6,906.00 Average leaseholder charge Report P35

Options considered

  • Rejected: Do nothing. Would breach the Council's duty to maintain housing stock and risk disrepair claims Report 5.1, P38
  • Rejected: Deliver the works through the Council's long-term partnering contractors. Works are urgent due to fire safety and deterioration, and cannot wait until partnering contractors mobilise in April 2026 Report 5.2, 5.3, 5.4, 5.5

Implications

  • Financial: Funded from Asset Management's HRA Capital Budget, with spend spread across 2025/26, 2026/27 and 2027/28. Report 6.10, 6.11, P74
  • Legal: Recovery from leaseholders is limited in some areas by Part 5 of the Building Safety Act 2022, and standard Section 20 consultation has been completed. Report 4.17, 4.18, P32, P33, P34, P114
  • Equalities: The works are expected to have a positive equalities impact, with adaptations for disabled residents and engagement to identify specific needs. Report P122, P123
  • Climate: Upgraded insulation and high-performance glazing support the Council's net-zero by 2041 target and the Housing Energy Action Plan. Report 4.11, P20, 10.1, P98
  • Risk: Key risks include contractor capacity, cost control, unforeseen works and programme delays; mitigations include LCP framework vetting, value engineering, and detailed programmes with contingencies. Report 8.1, 8.2, 8.3, 8.5, 8.6, P79, P81, P85, P87

Who and where

  • Residents of the seven timber-framed blocks on Hamilton Close estate Report 4.1, 4.9, 6.1, P48
  • 45 leaseholders on the Hamilton Close estate who will contribute via service charges Report 4.15, 4.16, P28
  • The contractor (Tenderer A) and the wider supply chain for the refurbishment works Report 3.1, 6.7, P100
  • The multi-disciplinary consultant continuing to provide project, design and principal designer services Report 4.2, 6.3, P9, P57

Timeline

  • 2022: Programme of works first identified for the seven blocks Report 5.5, 6.2, P50
  • February 2024: Initial feasibility surveys of communal areas Report 4.3
  • 23 April 2024 to 26 May 2024: Section 20 Notice of Intention consultation Report P33
  • May 2024: Intrusive surveys, including removal of selected cladding sections Report 4.4
  • 25th June 2025: Tenders invited via Lot 2.3 of the London Construction Programme Report 6.6
  • 13th August 2025: Tender closing date, with eight compliant bids received Report 6.6
  • 24 November 2025 to 27 December 2025: Section 20 Notice of Estimate consultation Report P34
  • 16 March 2026: Cabinet Member decision to award contract and issue letter of intent Report 3.1, 3.3
  • April/May 2026: Appointment of contractor and mobilisation Report P77
  • April 2027: Project handover Report P77
  • March 2028: End of defects period and final sign-off Report P77

Plain English for the jargon

  • Letter of intent: An early commitment allowing the contractor to place supply chain orders before a formal contract is signed.
  • Section 20 consultation: Statutory process under the Landlord and Tenant Act 1985 and Service Charges Regulations 2003 requiring landlords to consult leaseholders before carrying out qualifying works.
  • London Construction Programme (LCP): A framework agreement used by the Council to procure construction services, with Lot 2.3 covering housing refurbishment works.
  • Part 5 of the Building Safety Act 2022: Provisions that limit the ability of freeholders to recover service charges from leaseholders for works addressing certain 'relevant defects' in 'relevant buildings'.
  • Principal Designer: A duty-holder role under the Construction (Design and Management) Regulations with responsibility for coordinating health and safety during the pre-construction phase.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

RESOLVED To approve, Pursuant to Contract Standing Order (CSO) 2.01c and 0.08, the award of contract to Tenderer A for the sum of £1,909,942.00. Full details of Tenderer A, along with information on the other bidders, were provided in Appendix A – Exempt Report. To approve the expenditure of sums as set out in Appendix A – Exempt Report. To approve, in line with Contract Standing Orders (CSO 16.04), issuance of a letter of intent for the value of £190,994.00. The Letter of Intent will allow the contractor to commence the project by placing orders with their supply chain before agreeing a formal contract. Reasons for decision Feasibility and Condition Surveys The Council appointed a multi?disciplinary consultant in 2024 to undertake a feasibility study of the seven timber framed blocks on the Hamilton Close estate. The purpose of the study was to gather essential technical information to inform and develop a comprehensive major works programme. In addition to the feasibility study, the consultant was commissioned to provide a suite of specialist services, as outlined below. The corresponding fees for these services were set out in the Exempt Report (Appendix A). These services included: • Project and cost management • Architectural design and technical support • Building surveying • Mechanical, electrical, structural engineering • Principal Designer services in compliance with the Construction (Design and Management) Regulations and Building Safety Regulations The feasibility study was carried out in two phases. The initial phase, undertaken in February 2024, focused on evaluating the condition of the communal areas, including the main entrances, with a ... view the full minutes text for item 7.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet Member Signing

Recommendations

It is recommended that the Cabinet Member for Housing and Planning (Deputy Leader):

3.1Pursuant to Contract Standing Order (CSO) 2.01c and 0.08 approves the award of contract to Tenderer A for the sum of £1,909,942.00. Full details of Tenderer A, along with information on the other bidders, are provided in Appendix A – Exempt Report.

Page 1 of 10 3.2 Approves the expenditure of sums as set out in Appendix A – Exempt Report.

3.3In line with Contract Standing Orders (CSO 16.04), approves issuance of a letter of intent for the value of £190,994.00. The Letter of Intent will allow the contractor to commence the project by placing orders with their supply chain before agreeing a formal contract.

Reasons for decision

The decision to award this contract is based on several critical factors:

Feasibility and Condition Surveys

4.1The Council appointed a multi‑disciplinary consultant in 2024 to undertake a feasibility study of the seven timber framed blocks on the Hamilton Close estate. The purpose of the study was to gather essential technical information to inform and develop a comprehensive major works programme.

4.2In addition to the feasibility study, the consultant was commissioned to provide a suite of specialist services, as outlined below. The corresponding fees for these services are set out in the Exempt Report (Appendix A). These services include:

• Project and cost management • Architectural design and technical support • Building surveying • Mechanical, electrical, structural engineering • Principal Designer services in compliance with the Construction (Design and Management) Regulations and Building Safety Regulations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Hamilton Close Major Works ProgrammeMinutes 492 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 1 attended
SW
Councillor Sarah WilliamsCommittee Member, present

More from Haringey Cabinet Member Signing

All decisions
MeetingDecisionOutcome
2 Nov 2026 Deaf Outreach Services ContractDECLARATIONS FOR THIS ITEM: NONE Decided Open
28 Oct 2026 Administrative amendment to Merchant Acquirer Re-ProcurementRESOLVED 1. To note the administrative error in the original report referring to Global Pay and Global Payments; 2. T... Noted Open
20 Oct 2026 Approval of Additional Expenditure and Final Payment to Accora Limited reportDECLARATIONS FOR THIS ITEM: NONE RESOLVED The Cabinet Member for Adults and Health: 1. Approved the variation of cont... Approved Open
16 Oct 2026 Approve Funding from Arts Council England to Haringey Music Service for the North London Music HubDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
13 Oct 2026 Filming at meetingsThe notice of filming at meetings was noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies