What was decided
Approved the appointment of Contractor A, found through a formal tender, to build 16 new council homes at 505-511 Archway Road, with an anticipated start on 3 August 2026. Report 3.1, 4.2
Approved appropriating the site from the General Fund for planning purposes under Section 122 of the Local Government Act 1972, and using Section 203 of the Housing and Planning Act 2016 to override easements and other third-party rights affected by the development. Report 3.2, 3.3
Approved later appropriation of the site to the Housing Revenue Account on practical completion (anticipated March 2028), the total scheme cost, and a letter of intent of up to 10% of the contract value. Report 3.5, 3.6, 3.7
Why
The site is ready to move to construction after Cabinet approval in January 2021, a planning application on 2 May 2025, a resolution to grant on 6 November 2025 and a decision notice on 16 January 2026. Report 4.1, P36
Awarding the contract now lets the council enter contract within the deadlines required to keep external grant funding. Report 4.3
The scheme will deliver 16 affordable council homes, including M4(3) wheelchair homes and family homes, supporting the council's aim of 3,000 council homes by 2031.
What happens next
Enter into a JCT Design and Build fixed-price contract with Contractor A and hand over the site in August 2026, with an 80-week build programme and a 24-month defects liability period.
Delegate authority to the Delivery Director of Capital Projects and Property, with the Corporate Director of Finance and the Cabinet Member, to agree any compensation payments to third parties whose rights are overridden. Report 3.4, P77
On practical completion, anticipated March 2028, appropriate the land to the Housing Revenue Account at a value set by an independent valuer. Report 3.5, P52, P86
The money
- up to 10% of the contract value Letter of intent to be issued pending formal contract Report 3.7, P80
- £500,000 Threshold above which Cabinet approval is required for contract award under Contract Standing Order 2.01(c) Report P66, P67
Options considered
- Chosen: Award contract to Contractor A. Highest combined quality and price score from a competitive tender via the LCP DPS Principal Contractor framework; four of five bidders were compliant Report 3.1, 4.2, P44
- Rejected: Do not develop the site for housing. Does not support the council's commitment to deliver new affordable homes Report 5.1
- Rejected: Continue without appropriating the site for planning purposes. Risks delay or stopping of the development through third-party injunction claims Report 5.2
- Rejected: Do not appropriate the land to the HRA on completion. Could prevent the council from offering the homes for occupation as affordable housing Report 5.3
Implications
- Financial: Scheme is in the Housing Revenue Account capital programme; total scheme cost and contract sum are set out in the exempt Appendix 2 and will be funded within the approved budget. Report 9.3, P85, P87, P88
- Legal: Use of Section 203 overrides third-party rights such as rights to light; any valid claims convert into compensation only. The Director of Legal and Governance raises no legal reasons preventing approval. Report 3.3, 3.4, P77, P81
- Equalities: Expected to have a positive impact on people on the housing register, families needing 3-bed homes, those in temporary accommodation, and over-represented groups including women, young people, lower socio-economic households and BAME residents. The contractor will also be subject to the public sector equality duty. Report P93, P94
- Climate: Designed to Passivhaus principles with solar PV, an Exhaust Air Heat Pump system and passive shading; modelled at 77% improvement over the 2021 building regulations baseline, with biodiversity net gain and Urban Greening Factor targets met. Report 7.2, 8.1, 8.2, 8.5
- Risk: Council has received correspondence from adjacent landowners about potential right to light impacts and is in early engagement with them. Any compensation paid will draw on the approved scheme budget. A land valuation more than 6 months after the HRA appropriation decision could be challenged. Report P51, P79, P87
- Other: Site is in the Highgate Conservation Area (Sub-area 3) at the junction of Archway Road and Bakers Lane; design has been informed by a Quality Review Panel, conservation and urban design officers, and heritage consultants. Report P22, P23
- Staffing: Construction phase expected to create jobs, contributing to the council's place and economy priorities. Report 7.3
Who and where
- Future council tenants, including wheelchair users (M4(3) homes) and families needing 3-bed homes
- People on the housing register, including those in temporary accommodation, women, young people, lower socio-economic households and BAME residents Report P93
- Adjacent landowners who have raised right to light concerns Report P51
- Local residents of the Highgate area, including the Highgate Society and the Highgate Conservation Area Advisory Committee, who were consulted during design development Report 6.2, P30, P33
- Existing residents in the area who may benefit from public realm and Section 278 works including a new pedestrian crossing
Timeline
- January 2021: Cabinet approved inclusion of 505-511 Archway Road in the Housing Delivery programme Report 4.1
- February 2022: Community engagement events began with local stakeholder groups Report P30
- 02 May 2025: Planning application submitted (reference HGY/2025/1220) Report 4.1, P35
- 06 November 2025: Planning Sub-Committee resolved to grant consent Report 4.1, P36
- 16 January 2026: Planning decision notice received with conditions and Section 106 obligations Report 4.1, P36
- 20 March 2026: Cabinet Member for Housing and Planning decision to award contract and appropriate land
- 3 August 2026: Anticipated contract commencement and start on site Report 3.1
- March 2028: Anticipated practical completion, triggering HRA appropriation Report 3.5
Plain English for the jargon
- HRA (Housing Revenue Account): Ring-fenced account that holds council rents and pays for social housing
- Section 203, Housing and Planning Act 2016: Power allowing councils carrying out development on appropriated land to override third-party rights such as easements, converting them into compensation claims
- Section 122, Local Government Act 1972: Power for councils to appropriate land they own for a different statutory purpose
- Passivhaus: Design standard for very low energy buildings, using insulation and airtight construction to cut heat loss
- DPS (Dynamic Purchasing System): Procurement framework used to invite and evaluate bids from qualified suppliers
- M4(3) homes: Wheelchair-user dwellings built to Building Regulations Optional Requirement M4(3)
- JCT Design and Build Contract: Standard contract where the contractor takes on both design and construction responsibility