CHARITABLE TRUST - PROGRESS REPORT

Noted Committee 2 papers

AI summaryHaringey Alexandra Park and Palace committee notes trust progress: 10-year Strategic Plan completed, wetland access crowdfunder forecast at £20,000, and solar PV planned at the Boathouse.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo formal action taken; progress report received
Money£20,000 forecastWetlands crowdfunder target hit at £10,000 in two days
What happens nextDecarbonisation plan dueConsultancy report expected end of June 2026
Who it affectsPark visitors and community196-acre park and Alexandra Palace estate users

What was decided

The committee noted the charitable trust progress report without formal resolution. Report 1.1

The 10-year Strategic Plan covering Park and Palace projects is complete. Report 9.6

A wetland accessibility crowdfunder launched 15 May reached its £10,000 target in two days and is projected to raise £20,000 by 15 June. Report 9.7

Why

The report summarises FY 2026/27 progress against the Trust's Vision to be a sustainable home for all that it does, set out across 12 strategic goals. Report 2.1

Officers report strong delivery across the commercial and cultural programme, climate, heritage, park, archive and community engagement work. Report 3.1, 4.1, 5.1, 8.1

Both the Director of Legal and Governance and the Chief Financial Officer were consulted and had no comment on the report. Report P57, P58

What happens next

A Planning Performance Agreement is being sought for the Panorama Room Replacement Project, following a late February pre-application meeting. Report 10.1

The Trust will submit a National Lottery Heritage Fund development phase bid this financial year for the Creative Campus project. Report 10.2

A new Park Management Plan is being developed for the next ten years, with 2026/27 work including a herb garden, boardwalk, swales and a boating lake improvement plan. Report 6.4, P27

A decarbonisation delivery plan and funding master bid template, funded by the Mayor of London's Zero Carbon Accelerator, is due at the end of June. Report 4.3

The money

  • £10,000 Crowdfunder target for Alexandra Park Wetlands accessibility measures, reached in two days Report 9.7
  • £20,000 Projected total raised by wetlands crowdfunder at close on 15 June Report 9.7
  • 8,000kWh per annum Projected generation from planned solar PV installation at the Boat House
  • approximately 3,400 Attendees across all North London Book Fest and Biblio-Buzz events Report P35

Options considered

  • Chosen: Proceed with Planning Performance Agreement for Panorama Room. To provide a structured framework for planning and listed building consent Report 10.1
  • Chosen: Submit NLHF development phase bid for Creative Campus. Following successful Expression of Interest to the National Lottery Heritage Fund Report 10.2

Implications

  • Legal: The Council's Director of Legal and Governance was consulted and had no comment on the report. Report P57
  • Financial: The Council's Chief Financial Officer was consulted and had no comment on the report. Report P58
  • Climate: Secondary glazing installed in Old Station (CUFOS) and a Boat House solar PV system is at planning stage, expected to generate around 8,000kWh per annum; Haringey Community Carbon Fund has now supported three on-site projects. Report 4.1
  • Climate: The 2025/26 carbon footprint report is being compiled and will be shared at a future meeting. Report 4.3
  • Other: Heritage works completed include about 60 metres of Alexandra Palace Way reconstructed, heating vent grille safety works in Palm Court, pigeon deterrent measures at East Court Café, electrical and emergency lighting upgrades, Great Hall gantry safety works, and refurbishments of the Roman Bar and Willis Bar. Report 5.1, 5.2, 5.3, 5.5, 5.6, 5.7, 5.8, 5.9
  • Risk: Thames Water is planning a large project to slip-line two water mains through the Park, with trial holes completed and main excavations expected next year. Report 6.3

Who and where

  • Visitors to Alexandra Palace events, theatre, ice rink, boathouse, café and the Summit rooftop Report 3.1, 3.2, 3.3, 3.4
  • Park users, volunteers and the local community using the 196-acre park and boating lake Report 6.1, P7
  • Young people, schools, families and emerging artists taking part in creative learning and talent programmes Report 8.1, 8.2, 8.3, 8.4, 8.5
  • Trust staff, contractors and partner organisations delivering the programme Report 5.7, 11.1, 12.1
  • Heritage sector partners, including SPAB, BFI, BBC and National Science & Media Museum Report 7.2, 11.2

Timeline

  • April 2026: Boating lake pedalos reopened Report P7
  • 23 to 26 April 2026: North London Book Fest and Biblio-Buzz Children's Book Awards held Report 8.1
  • 30 April 2026: Mayor's Cultural Leadership Board quarterly meeting hosted at the Palace Report 11.3
  • 15 May 2026: Wetlands accessibility crowdfunder launched with Friends of Alexandra Park Report 9.7
  • End of June 2026: Decarbonisation delivery plan and funding master bid template due from engineering consultants Report 4.3
  • 5 June 2026: Drill Baby Drill early-stage work presented by Frank Wurzinger and John Wright Report P38
  • 9 and 11 June 2026: Behind-the-scenes BBC Studios Tours at Alexandra Palace for London Festival of Architecture
  • 13 June 2026: Wanna Play? The Playground performance and Ally Pally SkateJam Report 8.3, 9.3
  • 15 June 2026: Wetlands crowdfunder closes Report 9.7
  • 19 to 21 June 2026: Display loan to Campsbourne Community Collective for London Festival of Architecture at the Kurdish Centre Report 7.3
  • 22 June 2026: Heritage skills workshop open to visitors Report 9.2
  • August 2026: TownsWeb Digitisation grant application outcome expected Report 7.3

Plain English for the jargon

  • HCCF: Haringey Community Carbon Fund, which has funded three retrofit projects on the estate
  • PPA: Planning Performance Agreement, a structured framework for preparing and determining a planning application
  • NLHF: National Lottery Heritage Fund, approached for Creative Campus development phase funding
  • SPAB: Society for Protection of Ancient Buildings, hosted at the Palace in May and a likely heritage skills partner
  • EICR: Electrical Installation Condition Reporting inspections and associated remedial works
  • CUFOS: The Old Station building in which secondary glazing has been installed
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

The report was noted
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Alexandra Park and Palace Statutory Advisory Committee

Recommendations

1.1To note the contents of this report.

Executive summary

2.1This report summarises progress to date in FY 2026/27, aligned to the Trust’s Vision to “Create a Sustainable Home for All That We Do.” Updates under each strategic goal highlight the most material delivery milestones, issues, and achievements since the previous report. Vision and Goals can be found at Appendix 1

3. Provide Great Entertainment and Culture for All: Accessible and welcoming, we will continue to challenge ourselves to gain better understanding of our current and future audiences and their needs, ensuring our Cultural and Entertainment programme reflects the tastes and innovations of the time. We will support and develop opportunities for artists to showcase their talents and reach new and diverse audiences.

3.1Delivery remains strong across both the commercial and cultural programme, with a varied and high-quality schedule spanning concerts, theatre, corporate events and exhibitions. Several high-profile concerts have performed well while the Theatre programme continues to attract audiences through a diverse mix of spoken word, comedy, sporting events and rehearsals. Highlights in the Great Hall have included performances from Chris Stussy, Marina and PinkPantheress. The Theatre programme has delivered a broad range of activity, including the London Bollywood Orchestra, Ellen Kent Opera, Friday Night is Music Night, filming for North London Laughs and Later… with Jools Holland, as well as hosting the National Badminton League Finals in partnership with Badminton England. June also saw the return of the highly regarded ABTT Theatre Show, which experienced increased visitor numbers alongside a growth in exhibitor participation.

3.2Leisure and ancillary offers continue to play an important role in the year-round visitor experience. The Ice Rink has maintained strong performance across both public skating sessions and course provision, building on a successful spring period. The Hockey seasons came to an end, in May for the Huskies and the Greyhounds, female hockey team who won the league. Food and beverage outlets have continued to maximise trading opportunities linked to event and Ice rink footfall.

3.3The Boathouse offer continues to perform well, with The Boathouse receiving consistently positive feedback. Opening hours are weekdays 10:00–16:00, weekends 09.00-17.00. In May we had to temporarily close for maintenance.

The pedalos on the boating lake reopened in April and have proven extremely popular.

3.4The Summit rooftop experience continues to attract both local and national audiences, establishing itself as an important additional year-round attraction. A summer campaign is now live to attract more footfall.

3.5The team is now preparing for the upcoming outdoor events programme, with further detail provided in a separate report.

4. Build Climate Change Resilience: Actively responding to the climate change emergency, we will strive and challenge ourselves to take the Palace off grid within a generation, lessening our impact on the environment, reducing our energy consumption and harnessing the parkland to build climate resilience.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Progress Report Alexandra Park and Palace Vision and Goals 2023 to 2033Appendix 1 6.9 MB Download
PDF
CHARITABLE TRUST: PROGRESS REPORTMinutes 557 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 13 attended
AE
Councillor AJ EgemonyeCommittee Member, present
MJ
Councillor Marc JennerCommittee Member, present
EA
Councillor Emily ArkellCommittee Member, present
DB
Councillor Dawn BarnesCommittee Member, present
LB
Councillor Luisa BrandsCommittee Member, present
KB
Councillor Karolina BraunCommittee Member, present
EW
Councillor Elin WestonCommittee Member, expected
EW
Councillor Erin WolsonCommittee Member, present
JC
John CromptonAdvisory Committee Member, expected
ER
Elizabeth RichardsonAdvisory Committee Member, expected
JB
Jason BeazleyAdvisory Committee Member, present
JR
Joyce RosserAdvisory Committee Member, apologies

All 13 on the meeting page

On this subject at Haringey

Search all
  1. CHARITABLE TRUST - PROGRESS REPORTThis decision
  2. Charitable Trust Progress ReportNoted
  3. Charitable trust - progress reportNoted
  4. Alexandra Park and Palace Charitable Trust Governance ReviewAgreed
  5. Alexandra palace and park charitable trust financial resultsNoted
  6. 2015/16 alexandra palace and park charitable trust budget for approvalApproved

More from Haringey Alexandra Park and Palace Statutory Advisory Committee

All decisions
MeetingDecisionOutcome
18 Jun 2026 Response to traffic-related anti-social behaviour on alexandra palace wayThe update was noted and the ongoing partnership work to address traffic-related anti-social behaviour. Noted Open
18 Jun 2026 Alexandra park outdoor events reportThe report was noted. Noted Open
9 Mar 2026 MINUTESAgreed the minutes of the Statutory Advisory Committee held on 2 nd February 2026 as correct record subject to the am... Agreed Open
2 Feb 2026 MINUTESAgreed the minutes of the Statutory Advisory Committee held on 6th October 2025 as a correct record subject to the am... Agreed Open
6 Oct 2025 Chief Executive ReportThe Committee: 1.1 Noted the contents of this report 1.2 Provided comments on applications relating to Solar Panels (... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies