CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Haringey
Alexandra Park and Palace Board, Thursday 29 October 2026 at 7.00pm

Environmental Sustainability Update

Noted Committee 2 papers

AI summaryThe Alexandra Park and Palace Board approved the Carbon Reduction Plan, targeting Net Zero carbon in 2041 with actions for 2026-27. [D][P2][P59] A green electricity tariff costs an additional £12k per annum, and the plan states a preference to avoid it. [P70]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedThe Board also noted the report contents [D]
Money£12k per annum [P70]Additional cost stated for a green tariff [P70]
What happens nextCarbon Reduction Actions 2026-27 [P59]
Who it affectsAlexandra Park and Palace [P2]

What was decided

The Board noted the contents of the Environmental Sustainability Update report.

The Board approved the Carbon Reduction Plan at Appendix 1.

The approved plan has a Net Zero carbon target for 2041 and a Carbon Reduction Actions section for 2026-27. Report P2, P59

Why

Gas used for heating is the biggest contributor to the carbon footprint. The Palace is in use all year round and at all hours, with heating and hot water supplied throughout. Report P2

Since 2019/20, more emission factors have been measured. Emissions from buildings in the Park were included for the first time in 2025/26. Despite the wider measurement scope, measured emissions have reduced as efficiency projects take effect. Report P22, P40

Total emissions for 2025/26 were almost 15% lower than the 2019/20 baseline. Electricity consumption for the main Palace building reduced 22%, likely because of incremental heating pump improvements and low energy lighting upgrades. Report P40

What happens next

Continue lighting upgrades, equipment improvements and conversion to digital plans, record the changes, and issue the heat loss report following winter drone surveys. The lighting action and heat loss report have March 2027 deadlines. Report P61, P66

Progress ZCA work on a funding Masterbid, clean energy recommendations, waste heat capture and heat decarbonisation. The Masterbid and clean energy recommendations are due in Oct 2026, while waste heat recommendations and the heat decarbonisation review are due in Sept 2026. ZCA reports were received in July 2026. Report P62, P63, P64, P69

Continue data logging and use and loss analysis, and produce the partnership water efficiency report due in Oct 2026. Complete Theatre Green Book actions and staff engagement by March 2027, and review the NAA Event Green Guide and A Greener Future certification by Sept 2026. Complete the green electricity tariff review by Sept 2026. Report P65, P67, P68, P70

The money

  • £12k per annum Additional cost of a green electricity tariff. The stated preference is to avoid this additional cost. Report P70

Options considered

  • Chosen: Work towards alternative heat options to decarbonise heating. Heating gas is the biggest carbon contributor. The work is a major project that will take several years to realise. Report P2, P56
  • Chosen: Review green electricity tariff options. The review is complete. The green tariff costs an additional £12k per annum, and the preference is to avoid this additional cost. Report P70
  • Chosen: Review energy conservation measures. The Masterbid is intended to attract funding for items in Package 1. Report P62
  • Chosen: Review clean energy generation for buildings. ZCA reports were received in July 2026. Next steps are under consideration. Report P63
  • Chosen: Explore waste heat capture from the Ice Rink plant. The concept report identified technical uncertainties, so an in depth feasibility study is required. Report P64
  • Chosen: Explore water reduction. New meters are installed. Data logging and use and loss analysis are continuing. Report P65
  • Chosen: Increase building efficiency Report P57
  • Chosen: Improve behaviour and management Report P57

Implications

  • Financial: A green electricity tariff costs an additional £12k per annum. The stated preference is to avoid this additional cost. Report P70
  • Financial: Publication of the Masterbid is intended to attract funding for items in Package 1. Report P62
  • Climate: The plan's Net Zero carbon target for 2041 aligns with the target of Corporate Trustee Haringey Council. Report P2
  • Climate: Total emissions for 2025/26 were almost 15% lower than the 2019/20 baseline. Electricity consumption for the main Palace building reduced 22%, likely because of incremental heating pump improvements and low energy lighting upgrades. Report P40
  • Climate: Visitor numbers increased by 3.6%, while carbon intensity changed from 2.6 to 2.4 kgCO2 per visitor for 2025/26. Report P43
  • Risk: Moving away from gas heating is a major project that will take several years to realise. Report P56
  • Risk: The waste heat concept has technical uncertainties, so an in depth feasibility study is required. Report P64
  • Other: Projects in 2025/26 included storage containers to reduce truck journeys, reusable polycarbonate glasses and carafes, lighting upgrades to 84% low energy LEDs, and the recycled share of Palace waste rising from 47% to 51%. The Theatre Green Book basic level was achieved. Report P2, P55

Who and where

  • Alexandra Palace Report P2, P6
  • Alexandra Park Report P2, P22
  • Palace visitors and event participants Report P2, P13
  • Park visitors Report P2
  • Staff Report P22, P68
  • Theatre and bar operations Report P55
  • Clients and partners Report P54
  • Haringey Council as Corporate Trustee Report P2

Timeline

  • 2019/20: Gas, electricity, recycling and waste disposal were measured. Total emissions were 3,004 tCO2e, with 521,729 visitors and an intensity ratio of 7.5. Report P6, P12, P13, P14, P15
  • 2022: Carbon footprint assessment began, supported by the Mayor of London's Local Energy Accelerator scheme. It led to a clean energy masterplan for reaching Net Zero carbon. Report P2
  • 2025/26: Reported emissions were 2,558 tCO2e, with 1,059,251 visitors and an intensity ratio of 2.4 kgCO2/visitor. The total was almost 15% lower than the 2019/20 baseline. Report P28, P29, P30, P40
  • July 2026: ZCA reports were received for clean energy generation and heat decarbonisation. Report P63, P69
  • Sept 2026: Deadlines cover waste heat recommendations, the NAA Event Green Guide review, the heat decarbonisation review and the green electricity tariff review. Report P64, P67, P69, P70
  • Oct 2026: Deadlines cover Masterbid publication, clean energy recommendations and the water efficiency report. Report P62, P63, P65
  • March 2027: Deadlines cover lighting work, the heat loss report, Theatre Green Book actions and staff engagement. Report P61, P66, P67, P68
  • 2041: Net Zero carbon target. Report P2

Plain English for the jargon

  • Baseline year: 2019/20, when gas, electricity, recycling and waste disposal were measured. [P6]
  • Carbon intensity ratio: Total emissions divided by visitor numbers, giving a per visitor figure for comparison between years. [P15]
  • Net Zero carbon: The plan's emissions target for 2041, aligned with Haringey Council's target as Corporate Trustee. [P2]
  • Zero Carbon Accelerator: A Mayor of London support scheme used for clean energy and heating decarbonisation work. [P56][P62][P69]
  • Masterbid: A document intended to attract funding for items in Package 1. [P62]
  • Theatre Green Book: An industry guide for making environmental improvements to theatres. [P2]
  • A Greener Future: A certification being considered for live events. [P67]
  • Green tariff: A green electricity tariff option, with an additional £12k per annum cost. [P70]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

The Committee noted the contents of this report and approve the Carbon Reduction Plan at Appendix 1.
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Alexandra Park and Palace Board

Environmental Sustainability Update - Appendix 1 – Carbon Reduction Plan

Alexandra Park and Palace Carbon Reduction Plan 2026-27 Introduction Alexandra Park and Palace is a cultural and heritage destination. It’s home to world class events, an ice rink, a theatre and an award-winning Park. Each year, around one million people visit the Palace and participate in events and activities, and the Park receives almost four million visitors. We have a strong creative learning offer and many community and volunteering opportunities. Our environmental sustainability journey began in 2022. We began assessing our carbon footprint and were granted support from the Mayor of London’s Local Energy Accelerator scheme. This led to a clean energy masterplan which outlined, at a high level, the steps required to reach Net Zero carbon. The biggest contributor to our carbon footprint is the gas used for our heating system. This is not surprising, as we are supplying heating and hot water to a seven-acre Victorian building that is in use all year round and at all hours of the day. At an operational level, we have a green team that implements smaller scale environmental improvements and works towards environmental accreditations. One example is the Theatre Green Book, which is the industry guide for making environmental improvements to Theatres. In 2025/26 we achieved basic level of the Green Book. Commitment to achieving Net Zero Our Vision is to be a Sustainable Home for all that we do. We have a dedicated Goal to ‘Build Climate Change Resilience’ and good practice on emissions reduction included across all other charity Goals. Our target for Net Zero carbon target 2041, which aligns with the target of our Corporate Trustee Haringey Council

Figure 1: Vision and Goals

ALEXANDRA PALACE, ALEXANDRA PALACE WAY, LONDON, N22 7AY • 020 8365 2121 • ALEXANDRAPALACE.COM ALEXANDRA PARK AND PALACE CHARITABLE TRUST IS A REGISTERED CHARITY • CHARITY REGISTRATION NUMBER: 281991

1 Environmental Sustainability Update - Appendix 1 – Carbon Reduction Plan

Baseline Emissions Footprint We measured our carbon footprint for our baseline year, 2019/20. This measurement included gas and electricity consumption, plus recycling and waste disposal for the Palace. This was carried out before we introduced our Environmental Sustainability Policy and Strategy and started our journey.

Table 1: Baseline year emissions, 2019/20

EMISSIONS TOTAL (tCO2e)

Scope 1 1,673

Scope 2 1,325

Scope 3 6

Total Emissions (tCO2e) 3,004

Visitor numbers 521,729

Intensity ratio, kgCO2/visitor 7.5

The intensity ratio is calculated by dividing the total emissions by the number of visitors to obtain a ‘per visitor’ figure that allows comparisons from year to year

5.54

3,004 tCO2

44 % - Electricity 1,325 56% - Mains Gas 1,673 <1% - Waste

Figure 2: Carbon Footprint 2019/20, t/CO2e

ALEXANDRA PALACE, ALEXANDRA PALACE WAY, LONDON, N22 7AY • 020 8365 2121 • ALEXANDRAPALACE.COM ALEXANDRA PARK AND PALACE CHARITABLE TRUST IS A REGISTERED CHARITY • CHARITY REGISTRATION NUMBER: 281991

2 Environmental Sustainability Update - Appendix 1 – Carbon Reduction Plan

Subsequent Emissions Recording Since 2019/20 we have measured and calculated the emissions of several additional factors. These include LPG and fuel oil (Scope 1) plus staff commuting, water supply, Park waste and electricity consumption associated with the TV tower (Scope 3). Despite measuring more factors, the total carbon emissions measured have reduced as various efficiency projects take effect.

Table 2: Reporting Year emissions, 2025/26

EMISSIONS TOTAL (tCO2e)

Scope 1 1,647

Scope 2 670

Scope 3 240

Total Emissions (tCO2e) 2,558

Visitor Nos 1,059,251

Intensity ratio, kgCO2/visitor 2.4

26 % - Electricity scope 2

<1% - Electricity scope 3

63 % - Mains Gas

<1 % - Waste 2,558 tonnes CO2e <1 % - LPG

2 % - Fuel (Panorama Rm)

8% - Park (excl waste)

<1 % -Water S&T

<1% - Commuting

Figure 3: Carbon Footprint 2025/26, t/CO2e

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
APPCT 20261029-12-02: Environmental Sustainability Appendix 1: Carbon Reduction PlanMinutes 290 KB DownloadRead as text
PDF
Environmental Sustainability UpdateMinutes 445 KB Download

At this meeting

Whole meeting

Who was there

0 of 10 attended
MG
Councillor Melanie GingellChair, expected
DP
Councillor Daniela ParryVice-Chair, expected
RL
Councillor Rosie LatchfordCommittee Member, expected
ND
Councillor Nick da CostaCommittee Member, expected
MK
Councillor Marie KristensenCommittee Member, expected
EB
Councillor Eva BellCommittee Member, expected
JB
Jason BeazleyCo-Optee, expected
DN
Duncan NeillCo-Optee, expected
NW
Nigel WillmottCo-Optee, expected
CL
Chrisovalantis LiasiSecretary, expected

On this subject at Haringey

Search all
  1. Environmental Sustainability UpdateThis decision
  2. Environmental sustainability reportNoted
  3. Environmental sustainability reportAgreed
  4. Environmental sustainability policyAgreed
  5. Environmental sustainability reportApproved
  6. Low Carbon Investments Review and Environmental Social and Governance (ESG) and Sustainability Indices ReviewAgreed

More from Haringey Alexandra Park and Palace Board

All decisions
MeetingDecisionOutcome
29 Oct 2026 Charitable Trust Progress ReportThe Committee noted the report. Noted Open
29 Oct 2026 FRRAC Chair's Report (Verbal update)The Committee noted the report. Noted Open
29 Oct 2026 Finance ReportThe Committee noted the 2026/27 forecast against revised budget. Noted Open
29 Oct 2026 Panorama Room ReportThe Committee noted the report. Noted Open
29 Oct 2026 Energy Procurement StrategyThe Committee approved remaining within the Crown Commercial Service/Government Commercial Agreement (CCS/GCA) framew... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies