London Borough of Haringey
Cabinet, Tuesday 10 November 2026 at 6.30pm

Asbestos Remediation Works, 4 Year Contract

Decided Executive 1 paper

AI summaryHaringey Cabinet approved starting a competitive tender for a four year asbestos remediation contract for council housing, with up to one additional year available. Approval applies at £500,000 and above; works are charged to capital schemes, with no revenue implications. [D] [4.2] [6.6] [6.7] [6.8] [P27] [6.9]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedFour year term with one year extension option [6.6]
Money£500,000 and above [P27]Approval threshold; capital schemes carry the works [P27] [6.9]
What happens nextTender through London Construction Programme [6.7]Competitive process for licensed asbestos removal [6.7]
Who it affectsCouncil housing portfolio only [6.1]Safe removal supporting planned refurbishment work [6.1]

What was decided

Cabinet approved commencement of the procurement exercise for the asbestos remediation contract. No declarations of interest were made for the item. [D] [4.2] Report 4.2

The contract would provide a licensed asbestos removal contractor for the council's housing portfolio only. It would run for four years, with an option to extend for up to one additional year subject to performance and service requirements. [5.1] [6.1] [6.6] Report 5.1, 6.1, 6.6

The proposed works meet the council's capitalisation criteria and would be charged to appropriate capital schemes. The contract has no revenue implications. [6.8] [6.9] [P22] Report 6.8, 6.9, P22

Why

Asbestos removal contractors are needed for day to day repairs and project work, and for residential safety across housing managed stock. [4.1] Report 4.1

Asbestos containing materials are present in some buildings managed by Haringey Housing teams. Removal is needed for compliance, occupant and staff safety, and progress with planned refurbishment. [6.1] [6.2] Report 6.1, 6.2

The council uses surveys, reinspections, registers and management plans. It prioritises remedial work where risk assessments require action, supported by governance, training, contractor assurance and performance monitoring. [6.3] Report 6.3

What happens next

The contract will be procured through the London Construction Programme under the council's Contract Standing Orders and current procurement guidelines. The competitive tender will seek transparency, equal treatment of suppliers, best value and the most economically advantageous compliant service. [6.7] Report 6.7

The appointed contractor will carry out all asbestos remediation and disposal in line with current legislation, industry best practice and requirements for each site. [6.5] Report 6.5

Bidders will answer social value questions on proposed social and economic improvements in the borough during the contract. Bidders should also explain their carbon footprint and measures to reduce greenhouse gas emissions throughout the contract. [7.4] [8.2] Report 7.4, 8.2

The money

  • £500k Cabinet approval threshold before a procurement exercise may begin Report 4.2
  • £500,000 and above Cabinet approval threshold under Contract Standing Order 2.01(b) Report P27
  • £500,000 or more Cabinet approval threshold stated by Legal and Governance Report P31

Options considered

  • Chosen: Competitive tender through London Construction Programme. The route follows the council's Contract Standing Orders and procurement guidelines and is intended to secure best value through competition. Report 6.7
  • Rejected: An alternative option. The council states there is no alternative because licensed asbestos removal works must be carried out by a contractor holding an HSE issued three year licence, which also aligns with council policy. Report 5.1
  • Rejected: Apply the contract to new build homes. Asbestos materials are not used in new build homes, so the contract would not apply. Report 7.2

Implications

  • Financial: The contract has no revenue implications, and the works will be charged to appropriate capital schemes. The HRA Capital Programme forecasts underspends, particularly within Major Works, expected to offset current programme level pressure. [6.8] [6.9] [P22] [P23] Report 6.8, 6.9, P22, P23
  • Legal: The procurement must comply with procurement legislation and the council's Contract Standing Orders. The Director of Legal and Governance confirms there is no legal reason preventing approval. [P30] [P32] Report P30, P32
  • Legal: The contractor must hold an HSE issued three year licence for asbestos removal works. The council's strategy follows the Control of Asbestos Regulations 2012, the Health and Safety at Work etc. Act 1974 and relevant HSE guidance. [5.1] [6.2] Report 5.1, 6.2
  • Staffing: The work is intended to protect the health and safety of building occupants, users and Haringey staff. [6.1] Report 6.1
  • Risk: The council prioritises remedial works and removal where risk assessments require action. Governance, training, contractor assurance and performance monitoring support management through the property lifecycle. [6.3] Report 6.3
  • Climate: The contractor is expected to plan efficiently, reduce vehicle movements and waste, and use low carbon disposal and recycling where practicable. Bidders should explain their carbon footprint and measures to reduce greenhouse gas emissions throughout the contract. [8.1] [8.2] Report 8.1, 8.2
  • Equalities: The council must have due regard to its Public Sector Equality Duty under the Equality Act (2010). This includes eliminating prohibited conduct, advancing equality of opportunity and fostering good relations between people who share protected characteristics and people who do not. [P34] [P35] [P36] [P37] [P38] Report P34, P35, P36, P37, P38
  • Other: The contract supports safe, compliant and well maintained homes and buildings for residents, employees and visitors. It is intended to support regulatory compliance and wider building safety objectives. [7.1] Report 7.1

Who and where

  • Residents, employees and visitors using the council's homes and buildings Report 7.1
  • Building occupants and users in the housing portfolio Report 6.1
  • Haringey staff Report 6.1
  • Workers involved in maintenance, refurbishment and demolition Report 6.3
  • Prospective bidders and the appointed contractor Report 6.5, 6.7

Timeline

  • 2026-11-10: Cabinet meeting and agenda item 14, Asbestos Remediation Works, 4 Year Contract
  • initial period of four years: Initial contract term for asbestos remediation services Report 6.6
  • up to one additional year: Optional extension, subject to satisfactory performance and ongoing service requirements Report 6.6

Plain English for the jargon

  • Asbestos containing materials: Materials that remain in some council buildings constructed before 2000 and require identification, control and safe management. [6.2] [6.3]
  • London Construction Programme: The proposed route to market for the competitive asbestos remediation tender. [6.7]
  • Capital schemes: Appropriate schemes carrying the proposed works because the works meet the council's capitalisation criteria. [6.9]
  • Contract Standing Orders: Council procurement rules that set approval thresholds and govern the tender route. [4.2] [P26] [P30]
  • Social value: Tender questions measuring proposed social and economic improvements in the borough during the contract. [7.4]
  • HSE issued three year licence: The licence required for asbestos removal works, described by the council as an HSE issued three year licence. [5.1]
  • Dynamic purchasing system: A procurement route for which primary consideration will be given, alongside framework agreements. [P30]
  • Risk based asbestos management programme: The council's programme for identifying asbestos risks, keeping records and plans, and controlling work through governance, training, assurance and monitoring. [6.3]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14

Resolved

DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None
Word for word from the decision Haringey published for this meeting. Source: www.minutes.haringey.gov.uk

Follow this further

Built from Haringey's papers

What the report saysPro

Report to Cabinet

Reasons for decision

4.1To ensure compliance with all current asbestos legislation, asbestos removal contractors are a crucial part of the day-to-day operations of Haringey Council’s repairs and project service, and Borough-wide residential safety within Housing Services managed stock that contain asbestos materials used during construction of certain time periods.

4.2The Council’s Contract Standing Order item 2.01.b) requires Cabinet approval to commence a procurement exercise for proposed contracts valued £500k or above.

Alternative options considered

5.1The Council does not have an alternative option as licensed asbestos removal works must be carried out by a contractor holding a HSE issued three-year license to complete such works. This also aligns with Haringey Council policy.

6. Background information

6.1This procurement seeks to engage an experienced licensed asbestos removal contractor to support the safe and compliant delivery of upcoming works across Haringey Council’s Housing property portfolio only. Asbestos-containing materials are known to be present within buildings managed by Haringey Housing teams through our surveying programmes, and their removal is required to ensure ongoing legislative compliance, to protect the health and safety of building occupants and/or users and Haringey staff, and to enable planned refurbishment activities to proceed.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Asbestos Remediation Works, 4 Year ContractMinutes 267 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 20 attended
TE
Taryn EvesCouncil Staff, expected
AD
Andy DonaldOfficer, expected
FA
Fiona AldermanCouncil Staff, expected
AG
Ann GrahamOfficer, expected
BF
Barry FrancisCouncil Staff, expected
JC
Jess CroweOfficer, expected
AS
Ayshe SimsekSecretary, expected
SB
Stephen Bramah-CalvertOfficer, expected
CM
Claire McCarthySecretary, expected
MB
Councillor Mark BlakeChair, expected
TH
Councillor Tammy HymasVice-Chair, expected
GI
Councillor Gio IozziCommittee Member, expected

All 20 on the meeting page

On this subject at Haringey

Search all
  1. Asbestos Remediation Works, 4 Year ContractThis decision
  2. To award a new asbestos remediation contract for a period of 4 yearsApproved

More from Haringey Cabinet

All decisions
MeetingDecisionOutcome
10 Nov 2026 Corporate Delivery Plan 2026-2028DECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Draft 2027-28 Budget and 2027-2032 Medium Term Financial Strategy ReportDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Regulation 19 consultation on Proposed Submission version of Haringey Local Plan 2027-2042 and submission to Secretary of StateDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open
10 Nov 2026 Admission to Schools - Proposed Admission Arrangements for 2028/29DECLARATIONS OF INTEREST FOR THIS ITEM: None Decided Open
10 Nov 2026 Approval to extend current Highways and Street Lighting Contracts and approval of the procurement strategy for a future combined Highways and Street Lighting ContractDECLARATIONS OF INTEREST MADE FOR THIS ITEM: None Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies