Homelessness Prevention and Ending Rough Sleeping Funding and Contract Awards (Part 1)
ApprovedExecutive1 paper
AI summaryCabinet awarded the outreach and move on contract to Southdown Housing Association Limited, continued two homelessness prevention roles, and approved supported accommodation procurement. Outreach and floating support contracts are due to be mobilised on 1 April 2026, with housing partner funding matched by over £620,000.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedOutreach awarded to Southdown; accommodation procurement approved; prevention roles continued.
Moneyover £620,000Matched investment from Public Health, health and social care partners.
What happens nextSupported accommodation tender and mobilisationMarch 2026 tender; mobilisation by 1 October 2026.
Who it affectsPeople affected across all wardsThose who rough sleep, face homelessness, or use temporary accommodation.
What was decided
Cabinet awarded the HBC Street Outreach and Move On Support Contract to Southdown Housing Association Limited for 2 years from 1 April 2026, with an option for a 12 month extension. Report P8, P21
Cabinet agreed to procure supported accommodation for people with a history of rough sleeping. The contract term is 12 months, with an option for a 24 month extension. Report P8
Cabinet agreed to continue two dedicated homelessness prevention roles within the housing options team for 3 years. BHT Sussex provides the service through a contract with East Sussex County Council within the existing strategic partnership. It approved the related financial implications set out in the part 2 report and delegated final arrangements to the Head of Housing or their nominee. Report P8, P24
Why
The services currently commissioned through the Rough Sleeper Prevention and Recovery Programme are due to end in March 2026. The council intends to continue its priority of preventing homelessness and ending rough sleeping. Its new Hastings Housing Strategy gives this work priority. Report P9, P12, P20
The open tender received 2 bids. Southdown Housing Association Limited submitted the strongest tender for a service that engages people who are rough sleeping and supports access to temporary and settled housing. Report P21
Supported accommodation provides a stable environment for holistic needs assessment and suitable move on options. Floating support reaches people at risk of homelessness early and helps them keep existing accommodation or move into a settled home. Report P22, P24
What happens next
The Head of Housing or their nominee will finalise arrangements for outreach and move on support, supported accommodation, and the homelessness prevention roles. Report P8
An open tender is planned for supported accommodation in March 2026. The service is intended to launch as soon as possible after 1 April 2026. Partner authorities will scope opportunities to grow supported accommodation supply over the coming year. Report P22, P32
The street outreach and move on support contract and the housing related floating support contract are due to be mobilised on 1 April 2026. The supported accommodation contract is due to be mobilised by 1 October 2026. Report P30, P31, P33
The money
over £620,000 Public Health, health and social care investment matching housing partner contributions Report P23
Options considered
Chosen: Award the street outreach and move on support contract to Southdown Housing Association Limited. Two bids were received, and Southdown Housing Association Limited submitted the strongest tender. Report P21
Chosen: Run an open tender for supported accommodation. It provides a stable setting for holistic assessment and suitable move on options for people with high support needs. Report P22
Chosen: Continue two dedicated homelessness prevention roles within the housing options team. The roles help people retain existing accommodation and move from temporary accommodation into settled homes. Report P24
Implications
Financial: Economic and financial implications are identified in the part 2 report. Report P7, P38
Legal: Legal implications are identified in the part 2 report. Report P38
Financial: Housing partner funding contributions will be matched by over £620,000 investment from Public Health, health and social care partners. Report P23
Staffing: Two dedicated homelessness prevention roles will continue within the housing options team. Report P24
Staffing: The new multi disciplinary team will include a dedicated peer support team. Report P23
BHT Sussex and East Sussex County Council Report P24
Timeline
Between 26 November 2025 and 23 January 2026: Open tender exercise for street outreach and move on support. Report P21
March 2026: Existing commissioned services are due to end. Report P20, P35
March 2026: Provisional timing for the supported accommodation open tender. Report P32
25 March 2026: Cabinet approval of commissioning intentions and next steps. Report P29
1 April 2026: Provisional target for HBC Street Outreach and Move On Support contract mobilisation. Report P30
1 April 2026: Provisional target for Housing Related Floating Support, Homelessness Prevention contract mobilisation. Report P31
By 1 October 2026: Provisional target for supported accommodation contract mobilisation. Report P33
until March 2029: Homelessness, Rough Sleeping and Domestic Abuse Grant allocations made over a 3 year period. Report P11
Plain English for the jargon
RSPaR: The grant funded Rough Sleeper Prevention and Recovery Programme, led by the council for 5 local housing authorities in East Sussex.
Street Outreach and Move On Support: Service that engages people who are rough sleeping and helps them access temporary or settled housing.
Supported Accommodation: Temporary accommodation for people with high support needs, with assessment and help finding move on options.
Housing related floating support: Early support to help people keep existing accommodation or move into a settled home.
Multi disciplinary team: Health, mental health, social care and substance dependency specialists working together.
Housing First: Housing for people needing high levels of ongoing support, with a dedicated support service.
Move on support: Support for people in temporary accommodation to find suitable settled housing.
Peer support team: A dedicated part of the new multi disciplinary team, added to strengthen engagement.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7a
Resolved
To award the HBC Street Outreach and Move On Support Contract (Rough Sleeping Prevention and Recovery Programme) to Southdown Housing Association Limited. The term of the contract will be 2 years from 1 April 2026, with the option of a 12- month extension. 2. To carry out a procurement exercise to commission supported accommodation for people with a history of rough sleeping. The term of the contract will be 12 months, with the option of a 24-month extension. 3. To continue co-located homelessness prevention roles within the existing strategic partnership for housing-related floating support. This service is provided by BHT Sussex through a contract with East Sussex County Council. The term of the colocated homelessness prevention roles will be 3 years. 4. To approve the financial implications for recommendations 1, 2 and 3 as set out in the part 2 report. 5. To delegate authority to the Head of Housing or their nominee to finalise arrangements for the HBC Street Outreach and Move On Support, Supported Accommodation and Homelessness Prevention roles within the housing-related floating support service.
Word for word from the decision Hastings published for this meeting.Source: hastings.moderngov.co.uk
Report Title: Homelessness Prevention and Ending Rough Sleeping Funding and Contract Awards
Report By: Chris Hancock, Head of Housing
Key Decision: Yes
Classification: Public (Part 1)
Purpose of Report To provide an overview of the council’s ongoing work to prevent homelessness and end rough sleeping and recommend the award of contracts to support this activity. The financial implications for this work are set out in a part 2 report.
Recommendation(s) 1. To award the HBC Street Outreach and Move On Support Contract (Rough Sleeping Prevention and Recovery Programme) to Southdown Housing Association Limited. The term of the contract will be 2 years from 1 April 2026, with the option of a 12- month extension. 2. To carry out a procurement exercise to commission supported accommodation for people with a history of rough sleeping. The term of the contract will be 12 months, with the option of a 24-month extension. 3. To continue co-located homelessness prevention roles within the existing strategic partnership for housing-related floating support. This service is provided by BHT Sussex through a contract with East Sussex County Council. The term of the co- located homelessness prevention roles will be 3 years. 4. To approve the financial implications for recommendations 1, 2 and 3 as set out in the part 2 report. 5. To delegate authority to the Head of Housing to finalise arrangements for the HBC Street Outreach and Move On Support, Supported Accommodation and Homelessness Prevention roles within the housing-related floating support service.
Reasons for Recommendations The services currently commissioned through the Rough Sleeper Prevention and Recovery Programme are due to end in March 2026. The council is intending to commission services to support our ongoing priority to prevent homelessness and end rough sleeping. Introduction
1. Hastings Borough Council is the lead authority for the Rough Sleeper Prevention and Recovery Programme (RSPaR) on behalf of the 5 local housing authorities in East Sussex. The programme is funded by a grant from the Ministry for Housing Communities and Local Government. The aim of the programme is to end rough sleeping by ensuing that people who are forced to rough sleep have access to holistic support and temporary and longer- term accommodations options which are tailored to meet their needs.
2. In December 2025, the government published a National Plan to End Homelessness. The plan includes a focus on preventing crisis, improving emergency response and ensuring an assessment-led approach to preventing rough sleeping. The funding streams which support this work have also been restructured from April 2026. Previously ring-fenced grants have been combined into a single Homelessness, Rough Sleeping and Domestic Abuse Grant. Grant allocations have been made over a 3-year period until March 2029.
3. The council is well placed to ensure the latest funding allocations can embed the good practice and learning started through our existing programmes having recently adopted a new Hastings Housing Strategy. The strategy with a priority to prevent homelessness and end rough sleeping.
Our Work to End Rough Sleeping
4. The council’s work in partnership to end rough sleeping has been recognised as good practice through the national programme. The county-wide programme was supporting 368 people across the county at the end of the last quarter, including 112 people in Hastings. Key elements of the approach include:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Question Time (30 minutes)RESOLVED - the chair having called over the items on the agenda items 5, 6, 8, and 10a were reserved for discussion. ...
Local Authority Housing Fund - Round 4· To accept grant funding from the Local Authority Housing Fund (LAHF) Round 4, which is expected to be between £3,51...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.