Cabinet, Wednesday 15 December 2021 at 5.30pm

Warblington Footbridge

Approved Executive 3 papers

Cabinet approved this item on Wednesday 15 December 2021. Below is the council's own wording, with the papers it was decided on.

Item32

Resolved

RESOLVED that Cabinet APPROVE progression of the Warblington Station footbridge project through Network Rail’s governance stages GRIP3 (option selection) and GRIP4 (single option development) stages (estimated cost up to £300,000), using part of the existing CIL committed funding of £475,000 under the following terms: A Officers be authorised to proceed with undertaking and submitting the Diversity Impact Assessment required to progress the scheme. b) Cabinet supports in principle the use of Havant Borough Council Community Infrastructure Levy to make up funding shortfall (capped at £770,000) to complete the construction phase and will be conditional on the current CIL allocation being reallocated to release the funds should this not be possible to accommodate through other means; c) A funding update to be presented to Cabinet within nine months including written confirmation of HCC’s allocation of S106 funding to the project; d) The least expensive option for the bridge (of three suggested) is confirmed as the Council’s preferred option; e) In order to ensure CIL is spent in accordance with the Council’s legal obligations the Council will need to enter into a legal agreement with Network Rail to control the relationship between the parties as the project moves through the various GRIP stages. f) Approval to progress beyond GRIP4 (single option development) will be conditional on the current CIL contingent allocation being released .
Word for word from the decision Havant published for this meeting. Source: havant.moderngov.co.uk

Follow this further

Built from Havant's papers

What the report saysPro

Report to Cabinet
This report is being read into text

Papers are read newest first, so recent reports come through within hours. Until then, open it at source.

Open the PDF

Papers for this item

Kept in our archive, download once signed in
PDF
Warblington Footbridge 1718Appendix A 272 KB Copy on its way
PDF
Warblington Bid Form 2019Appendix B 248 KB Copy on its way
PDF
Warblington FootbridgeReport 391 KB Copy on its way

At this meeting

Whole meeting

On this subject at Havant

Search all
  1. Warblington FootbridgeThis decision
  2. Warblington FootbridgeAgreed

More from Havant Cabinet

All decisions
MeetingDecisionOutcome
18 Dec 2024 Matters referred by Full Council or the Overview & Scrutiny Committee Under Cabinet (Executive) Standing Order 9.4cRESOLVED that Cabinet approved the Scrutiny and Executive Protocol as set out in Annex 1 of the Overview and Scrutiny... Approved Open
18 Dec 2024 Corporate Strategy Delivery PlanRESOLVED that Cabinet 1. adopted the Corporate Strategy Delivery Plan. 2. delegated authority to the Chief Executive,... Approved Open
18 Dec 2024 Quarter 2 Revenue and Capital Budget Monitoring Report 2024/25RESOLVED that Cabinet consider the results of the Quarter 2 Revenue and Capital Budget Monitoring Report for 2024/25 ... Decided Open
18 Dec 2024 2025/26 Fees and ChargesRESOLVED that Cabinet approved the Fees and Charges Schedule for 2025-26. Approved Open
18 Dec 2024 Council Tax Base 2025/26RESOLVED To rec ommend that Council: 1. Approves the Council Tax base of 43,147.4 for 2025/26. 2. Delegates authority... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies