Item85
Resolved
RESOLVED that: a. the continued progression to complete the Planning and Consenting management stage of the project (estimated cost £300k - £400k) be approved; b. the continued work to close the project’s remaining funding gap, while also seeking to decrease costs where possible, and seek certainty over the release of allocated funds, and cost benefit ratios from the Environment Agency be approved; and c. the need to work with partner agencies to deliver this priority project for the borough be endorsed and in doing so, the Leader shall write to National Highways to express the need for their support.
Word for word from the decision Havant published for this meeting.
Source: havant.moderngov.co.uk