Resolved
RESOLVED to: 1. Recommend to the Cabinet Member for Community Empowerment that the following proposals be implemented as shown on the drawing No. QK004/A. (a) Speed control humps along Philip Road on either sides of Edmund Road Junction. (b) Double yellow lines along Philip Road to a distance of 15metres from Edmund Road and the reduced length of 10metres along Edmund Road from Philip Road as shown on the above drawing. 2. That a further review and consultation be carried out in September 2012 to consider if further measures were along Philip Road. 3. That, it be noted that the estimated cost of £12,000 would be met from the Transport for London’s ( TfL ) 2011/12 financial year allocation to Havering for Accident Reduction Programme.